Demanding a Reduction in Retainage
April 01, 2015 —
Craig Martin – Construction Contractor AdvisorOne of the attendees of the Goldleaf Surety presentation asked a great question about reducing retention under the Nebraska Construction Prompt Pay Act, Nebraska Revised Statutes, 45-1201-45-1211. He wanted to know whether there was any way to reduce and recover retainage during the project. The short answer is retainage should be reduced half way through the project, but there is no right to recover retainge for work performed during the first half of the project.
Retainage in Nebraska
Under section 45-1204 of the Prompt Pay Act, a contractor may withhold up to 10% retainage. A contract that allows for greater retainage is not enforceable.