Ohio subcontractor work exception to the “your work” exclusion
August 11, 2011 — CDCoverage.com
In Mosser Construction, Inc. v. Travelers Indem. Co., No. 09-4449 (6th Cir. July 14, 2011)(unpublished), claimant project owner Port Clinton contracted with insured general contractor Mosser for the construction of a building. Following completion, Port Clinton sued Mosser for breach of contract seeking damages because of physical injury to the project occurring after completion resulting from defective backfill material that settled improperly.
Mosser’s CGL insurer Travelers denied a defense and Mosser filed suit against Travelers seeking a declaratory judgment. Mosser and Travelers filed cross-motions for summary judgment on the issue of whether the supplier of the backfill material?Gerken?qualified as a subcontractor for purposes of the subcontractor work exception to the “your work” exclusion—exclusion l.—for property damage to or arising out of Mosser’s completed work.  Mosser had purchased the backfill material from Gerken pursuant to a purchase order specifying that Gerken was to supply Mosser with an industry standard grade of backfill for use in the Port Clinton project.
Read the full story…
Reprinted courtesy of CDCoverage.com
No Coverage for Counterclaim Alleging Construction Defects Pled as Breach of Contract
September 13, 2012 — Tred Eyerley, Insurance Law Hawaii
The Colorado Court of Appeals considered whether counterclaims against the insured for alleged faulty construction work were based in contract or constituted allegations of an "accident" under the policy. TCD, Inc. v. Am. Family Mutual Ins. Co., 2012 WL 1231964 (Colo. Ct. App. April 12, 2012).
The developer, Frisco Gateway Center, LLC, contracted with TCD, the general contractor, to construct a building. TCD, in turn, subcontracted with Petra Roofing to install the roof. The subcontract required Petra to "indemnify, hold harmless, and defend" TCD against claims arising out of resulting from the performance of Petra's work on the project. Petra was also required to name TCD as an additional insured on its CGL policy.
After a dispute arose between TCD and Gateway regarding payment and performance on the project, TCD sued Gateway and other parties seeking payment. Gateway counterclaimed against TCD for breach of contract and negligence. TCD demanded coverage from Petra's insurer, but coverage was denied.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Boston Tower Project to Create 450 Jobs
November 18, 2011 — CDJ Staff
Continuing the development of Boston’s Theater District, Millennium Partners broke ground for the building of Hayward Place, a 15-story residential tower with street-level shops. The project is expected to take two years to complete and will employ about 450 construction workers.
Thomas Menino, the mayor of Boston said that the “ground breaking of Hayward Place is another sign of economic growth and forward progress on the revitalization of this area.” The project will be built by Suffolk Construction. John Fish, their CEO, said they were “fortunate as a contractor to be the beneficiary of this.”
The report in the Boston Herald notes that a few blocks away, the site of the former Filenes department store is still “an empty eyesore.” Menino joked, “anyone want to bid for it?” He promised that site would also be developed.
Read the full story…
Construction on the Rise in Denver
September 13, 2012 — CDJ Staff
In another sign of a recovery in the housing industry, the Denver Business Journal reports that the pace of new home construction has accelerated in the Denver area. According to the article, in the first seven months of 2012, forty-eight percent more permits were issued than in the first seven months of 2011. In July, 2012, there were sixty-six percent more permits than a year previously. For the Denver metropolitan area, July was the sixteenth consecutive month in which permits were up from a year previously.
Read the full story…
Hospital Construction Firm Settles Defect Claim for $1.1 Million
September 13, 2012 — CDJ Staff
Law360 reports that Bovis Lend Lease has settled claims of $10 million in damages for $1.1 million. Bovis was building three annexes to a hospital in Oklahoma. The hospital alleged that a faulty moisture barrier system lead to damage throughout the hospital.
Bovis is a division of the Lend Lease Group, a multinational construction firm based Sydney, Australia.
Read the full story…
Construction Defect Exception Does Not Lift Bar in Payment Dispute
September 13, 2012 — CDJ Staff
The Court of appeals of Oregon has affirmed the ruling of a lower court, agreeing that ORS 701.131(1) bars John Pincetich from pursuing a payment dispute against his clients, Thomas and Frances Nolan. The Nolans hired Mr. Pincetich to build a home, during which time Mr. Pinchtich lost his license due to a lapse in liability insurance. Mr. Pincetich was reinstated after reestablishing insurance.
After the house was concluded, a dispute over payment arose. The Nolans claimed that Mr. Pincetich was unable to bring an action against them as ORS 701.131(1)(b) specifies that the contractor must hold a license “continuously while performing the work for which compensation is sought.” As there were fourteen days in which Mr. Pincetich did not hold a license, the trial court concluded that this law did not apply.
Mr. Pincetich claimed that in hiring him, the defendants became residential developers. Mr. Pincetich argued that developers are exempted under ORS 701.121(2)(C), but this was rejected by the trial court. This formed the basis of his appeal. The appeals court concluded that the exception he cited was motivated to “further benefit consumers by providing authority for unlicensed contractors to pursue third-party claims in construction-defect cases.” The court concluded that Mr. Pincetich’s reasoning would “allow unlicensed contractors to do the very thing that the claims bar is intended to prevent them from doing.”
Read the court’s decision…
Another Colorado District Court Refuses to Apply HB 10-1394 Retroactively
October 28, 2011 — David M. McLain, Colorado Construction Litigation
In Martinez v. Mike Wells Construction Company, 09CV227, Teller County District Court Judge Edward S. Colt refused to apply C.R.S. § 13-20-808 retroactively to provide coverage for the underlying construction defect allegations. According to the recitation of facts in Judge Colt’s March 2011 order, Martinez contracted with Mike Wells Construction to serve as the general contractor for the construction of a home. At that time, Mike Wells Construction was insured through ProBuilders Specialty Insurance Company, RRG. Disputes arose between Martinez and Mike Wells Construction, resulting in Martinez ordering it off of the project in mid-November 2007 and terminating its right to work there by letter dated November 28, 2007.
Mike Wells, the owner of the corporation, subsequently died. Martinez sued Mike Wells Construction in July 2009 for breach of contract and various claims relating to alleged defecting workmanship. Martinez provided notice of the suit to the special administrator of the probate estate. No answer having been filed, the court entered a default judgment against Mike Wells Construction and Martinez sought to garnish Mike Wells Construction’s ProBuilders insurance policy.
Read the full story...
Reprinted courtesy of Higgins, Hopkins, McLain & Roswell, LLC. Mr. McClain can be contacted at mclain@hhmrlaw.com
Construction Jobs Expected to Rise in Post-Hurricane Rebuilding
November 7, 2012 — CDJ Staff
Businessweek reports that construction jobs and materials will see increased demand as property owners in New York and New Jersey rebuild after hurricane Sandy. Tom Jeffery, of Irvine, California-based CoreLogic, a real estate information service, noted that “a high percent of damaged properties are going to be repaired.” Experts estimate property damage to total anywhere from $7 billion to $40 billion.
It is also estimated that about 739,000 properties in the area are underwater in the way that has nothing to do with flooding, with negative equity of 25 percent or more. Many of these homeowners are likely to walk away from their mortgages.
Ken Simonson, chief economist of the Associated General Contractors of America, expects “localized spikes in construction employment throughout November and the winter.” Martin Connor, the chief financial officer of Toll Brothers, expects to see more a rise in labor costs than in materials.
Read the full story…
Can Negligent Contractors Shift Blame in South Carolina?
July 10, 2012 — CDJ Staff
Clay Olson looks back to a 1991 Carolina case, Nelson v. Concrete Supply Company. The court concluded in that case that “a plaintiff in South Carolina may recover only if his/her negligence does not exceed that of the defendant’s and amount of plaintiff’s recovery shall be reduced in proportion to amount of his or her negligence; if there is more than one defendant, plaintiff’s negligence shall be compared to combined negligence of all defendants.” In 2005, he reports, as part of tort reform in South Carolina, the legislature further addressed this.
He then suggests a possible outcome of this is that negligent contractors may be able to shift some of the blame (and cost of the settlement) to other defendants who may not be to blame. He offers a scenario in which a contractor is sued for construction defects and a jury has to allocate responsibility for indivisible damage. “A jury need only find the two subcontractors to have each contributed 15% of the indivisible damage.” He adds in another 15% for claims against the architect. Minor blame is given to the manufacturers, and suddenly the negligent contractor is paying less than 50% of the total settlement.
He notes that the previous system in place also had its problems, but notes that this one may not be “fair and equitable.”
Read the full story…
Arbitration Clause Found Ambiguous in Construction Defect Case
October 28, 2011 — CDJ Staff
The California Court of Appeals ruled on September 28 in the case of Burch v. Premier Homes. Ms. Burch bought a home after negotiating various addendums to the contract. The contract was a standard California Association of Realtors contract to which both the buyer and seller made additions. At issue in this case was paragraph 17 of the contract which included that “Buyer and Seller agree that any dispute or claim in Law or equity arising between them out of this Agreement or resulting transaction, which is not settled through mediation, shall be decided by neutral, binding arbitration.”
The seller/defendant’s Addendum 2 “included provisions relating to the arbitration of disputes that may arise.” Ms. Burch’s realtor, Lisa Morrin, told Burch that “she had never seen a proposed contractual provision that would require a home buyer to agree to arbitrate with a builder over construction defects.” Ms. Burch told Morrin that she did not want to buy the property if she would have to give up her rights under California law.
As part of Addendum 2, the buyer had to buy a warranty from the Home Buyers Warranty Corporation. The sale was held up for a while, as Ms. Burch waited for a copy of the warranty. When she received it, she took further exception to Addendum 2. Scott Warren of Premier Homes said he could not sell the property without Addendum 2. Ms. Burch told her realtor that despite the claims made by Mr. Warren that this was for her benefit, she felt it was more to the benefit of Premier Homes. Don Aberbrook of HBW agreed to the clause, contained in the final sentence of Addendum 2, being struck.
Subsequent to buying the home, Burch submitted a claim concerning construction defects. HBW denied the claim and Burch began an action against the defendants. Premier filed a motion to compel arbitration which Burch opposed.
The trial court ruled that the striking out of the arbitration clause at the end of Addendum 2 “created a conflict with respect to the parties’ intent as to the scope of arbitration.” The trial court found that “the parties’ intention was to preserve Burch’s right to make state law claims including her right to a jury trial for any non-warranty claims against the builder.”
The appeals court in their ruling looked at the standard of review and concluded that the purchase agreement was ambiguous and that extrinsic evidence was required to resolve that ambiguity. As the contract contained contradictory provisions as to whether or not arbitration was required, it was necessary for the trial court to examine these claims. The appeals court found that the evidence supported the conclusions of the trial court.
Finally, the appeals court found that “there was no valid agreement to arbitrate disputes.” The court noted that arbitration can only happen by mutual consent and “it is clear that Burch did not enter into an agreement to arbitrate any construction defect disputes she might have.”
Read the court’s decision…
LEED Certified Courthouse Square Negotiating With Insurers, Mulling Over Demolition
June 6, 2011 — Douglas Reiser in the Builders Counsel Blog
Apparently, Courthouse Square is still unresolved. The County hasnow hired an attorney to handle its insurance claim against Affiliated FM. Is there a lawsuit coming?
Right now, no lawsuit is expected. According to officials, the insurer has been acting in good faith. But, its been quite a while since Salem officials learned that the Courthouse Square building had significant concrete issues that would result in probable demolition of the LEED certified building.
If you have yet to hear about Courthouse Square, let me fill you in briefly. The Salem building was substantially completed in 2000 and LEED certified by the US Green Building Council in 2002. The project cost more than $30 Million to complete and the building was revered for its innovation as a crowning achievement for city leaders.
But, structural problems in the building’s core were discovered as early as 2002, writes Chris Cheatham of Green Building Law Update. Final tests earlier in the year, determined that the building had to be vacated. The building has been clear since July 2010.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Construction on the Rise in Washington Town
June 16, 2011 — CDJ Staff
The Kitsap Sun reports that Gig Harbor, a town in the area near Tacoma, Washington, has had a 60% increase in building permit applications as compared to 2010. May, 2011 had as many permits issued for single-family residences in Gig Harbor as were issued for all of 2010. Additionally, a Safeway shopping center on Point Fosdick is described by Dick Bower, Gig Harbor Building and Fire Safety Director, as “a huge project and it’s going to bring in quite a bit of revenue.” He called the increase in building “economic recovery at the grassroots level.”
Bower said that the building officials in other towns have also seen upswings in construction. He anticipates more activity in the future.
Read the full story…
Condo Buyers Seek to Void Sale over Construction Defect Lawsuit
November 7, 2012 — CDJ Staff
A Michigan couple seeks to void their purchase of a condo in Texas after discovering that the complex was undergoing a construction defect lawsuit. ABQ Journal reports that Charles M. Lea and Olga Y. Ziabrikova said that they would not have purchased the condo if they had known the association was already alleging construction defects. The condo association discovered the defects “by at least late 2010,” according to the suit. The couple bought their condo in August 2011 and heard of the defects only in March 2012.
The couple notes that no one involved with the sale informed them of the construction defect complaints. The community association’s lawsuit states that problems have lead to $2.5 million in damages. The developer, Vegas Verde Condo Partners, have filed a general denial of the construction problems.
Read the full story…
A Performance-Based Energy Code in Seattle: Will It Save Existing Buildings?
August 11, 2011 — Douglas Reiser, Builders Counsel
The City of Seattle has one of the most stringent energy codes in the nation. Based upon the Washington State Energy Code (which has been embroiled in litigation over its high standards), the code demands a lot from commercial developers. But, does it prevent developers from saving Seattle?s classic and old buildings? Perhaps.
The general compliance procedure requires buildings to be examined during the permitting process. This means that buildings are examined before they begin operating. The procedure is not malleable and is applicable to all buildings, old and new, big and small.
The downside of this procedure is that it eliminates awarding compliance to those buildings exhibiting a number of passive features, such as siting, thermal mass, and renewable energy production. This problem has prevented a number of interesting and architecturally pleasing existing building retrofits from getting off the ground. The cost of complying with the current system can be 20% more, and it might prevent builders from preserving a building?s historical integrity.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Gilroy Homeowners Sue over Leaky Homes
February 10, 2012 — CDJ Staff
Two years into a lawsuit against Shapell Homes, the builder of a subdivision called Eagle Ridge in Gilroy, California, homeowners have joined or left the lawsuit. About fifty homeowners are still in the suit, which contends that construction defects have lead to water intrusion in their homes. The lawyer for the homeowners contends that more than a hundred homes have construction defects.
One homeowner said that soon after he joined the suit, Sharpell sent workers to his home who repaired problems to his satisfaction. “They came in within two weeks and fixed everything,” said Frank Lowry. Another homeowner, Wilson Haddow, said that he was “quite happy” after Shapell repaired problems.
Others weren’t quite so happy. Greg Yancey said that problems had “been a nightmare” and that “it just doesn’t feel like home.” He said that his “house is possessed,” with problems that include walls that bow out and a balcony that drips rainwater to the front door. His home is currently worth far less than the $700,000 he paid in 2007.
Read the full story…
Contractor’s Coverage For Additional Insured Established by Unilateral Contract
November 18, 2011 — Tred Eyerley, Insurance Law Hawaii
The contractor was covered as an additional insured under the subcontractor’s policy even though the parties had never actually signed an agreement to add the contractor to the policy. Evanston Ins. Co. v. Westchester Surplus Lines Ins. Co., 2011 U.S. App. LEXIS 20081 (9th Cir. Oct. 3, 2011).
The policies held by Bellevue Master, the general contractor, required it to be an additional insured under any subcontractor’s liability policy. Northwest Tower Crane Services was a subcontractor. Bellevue Master LLC, faxed a message that Northwest could continue to be a subcontractor on the project if it complied with Bellevue Master’s insurance requirements. Northwest contacted its insurance broker and requested an insurance certificate be issued to Bellevue Master so that it would be an additional insured under Northwest’s policy.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Bill Seeks to Protect Legitimate Contractors
December 20, 2012 — CDJ Staff
The California construction industry sees Senate Bill 863 as a needed help to legitimate construction businesses. The bill introduces regulations that will help shut down fraudulent contractors and help reduce workers’ compensation fraud. John Upshaw of the Independent Roofing Contractors of California described the revenue lost to California and other states as “phenomenal,” saying that “we need to continue the coordinated efforts if we are to see true workers’ compensation reform.”
Read the full story…
An Upward Trend in Commercial Construction?
March 28, 2012 — Melissa Dewey Brumback, Construction Law North Carolina
Year-end economic indicators demonstrate that private commercial construction may be increasing in 2012, primarily as demand grows for new projects built in the United States.
According to an article in Businessweek, the Architecture Billings Index held at 52 in December, indicating a modest expansion in the market. The American Institute of Architects said that the commercial and industrial component of the number climbed to 54.1 in December, the highest in 10 months.
The monthly survey of U.S.-based architecture firms is one of the main indicators of nonresidential construction, and these numbers suggest that modest improvement may be on the horizon.
The information is confirmed by data from the Census Bureau that shows that spending on lodging, office, commercial and manufacturing buildings grew 8.2 percent in November to $9.2 billion from a year ago. These types of commercial and industrial projects are historically canaries in the mine and are usually the first part of the industry to improve as the economy expands.
Read the full story…
Reprinted courtesy of Melissa Dewey Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.