The Ever-Growing Thicket Of California Civil Code Section 2782
January 6, 2012 — Michael D. Worthing, Borton Petrini
California Civil Code section 2782 imposes limits on indemnity and defense provisions in construction contracts. Since the initial adoption of S.B. 8001 in 2002 (eff. January 1, 2003) section 27822 has been revised several times, and legislative history suggests that interest groups representing builders, developers and sub-contractors, as well as the insurance industry, have seen legislative action on these indemnity and defense issues as part of the overall response to the same economic pressures resulting from construction defect litigation that gave rise to S.B. 800. Amendments in 2005, 2007, 2008 and 2011 (each effective January 1 of the following year) have increasingly entangled the provisions of Section 2782 with various provisions of S.B. 800. The application of section 2782 to construction contracts, and in particular contracts between developer-builders and subcontractors, executed after January 1, 2006, will require a concurrent reading and understanding of S.B. 800, the application of which is itself still in flux.
The time a construction contract was executed will likely determine which version of section 2782, read in connection with provisions of S.B.800, is applicable. Because of the nature of construction defect litigation, the determination of relative rights and liabilities of developer-builders vis-à-vis subcontractors under construction contracts does not become the subject of litigation, and legal and judicial interpretation, until years after the contracts were entered and work performed. As of the date this article is submitted, there has been no case law interpreting or applying any of the post S.B. 800 amendments, in part, and perhaps primarily, because litigation arising from construction contracts executed after January 1, 2006, has not yet reached the appellate courts.
SECTION 2782 AT THE TIME S.B. 800 WAS ENACTED
Section 2782 was originally enacted in 1967 and amended several times to the version in effect when S.B. 800 became law, at which time the section was relatively simple and straightforward. It then consisted of two subdivisions, which have essentially remained unchanged until the most recent amendment during the 2011 legislative session.
Section 2782 (a) prohibited, and still prohibits, provisions in construction contracts that “purport to indemnify the promisee against liability for damages for death or bodily injury to persons, injury to property, or any other loss, damage or expense arising from the sole negligence or willful misconduct of the promise.” This provision essentially prohibits what had been referred to as so-called Type I or “specific” indemnity provisions. In such agreements, the indemnitor [the promisor, that is, the person or entity indemnifying] will indemnify the indemnitee [the promisee, that is, the person or entity being protected by the indemnity] for the indemnitee’s own negligence, whether active or passive, whether the indemnitee is solely negligent or concurrently negligent with the indemnitor. (See, MacDonald & Kruse, Inc. v. San Jose Steel Co. (1972) 29 Cal.App.3d 413, 419.)3 Section 2782 (a) has remained essentially intact since the enactment of S.B. 800. It still must be considered and applied to interpret a construction contract. Generally, it will apply to contracts not involving a public agency; the next part of section 2782 specifically governs such contracts.
The second subdivision prohibits provisions in any construction contract with a public agency which purport to impose on the contractor, or relieve the public agency from, liability for the active negligence of the public agency. Subdivision (b) has been revised by the 2011 amendment, discussed below. If a construction contract with the public agency is for residential construction, the standards of S.B. 800 likely apply.4
This was the extent of section 2782 on January 1, 2003, when S.B. 800 went into effect, and remained so until January 1, 2006. This version will govern interpretation and application of indemnity and defense provisions in construction contracts executed before January 1, 2006.5
2005 AMENDMENT
The first “post S.B. 800” change to Section 2782 was in enacted in 2005, effective January 1, 2006, and added two new sections. Subdivision (c) stated (in somewhat greater detail than paraphrased here) that for residential construction contracts, or amendments thereto, entered into after January 1, 2006, a subcontractor cannot be required to indemnify (including the cost to defend) a builder for construction defects that arise out of negligence or design defects of the builder or other independent contractors, or that do not arise out of the scope of the subcontractor=s scope of work. The term “residential construction” was defined by reference to S.B.800 generally, and the term “builder” was defined by reference to section 911 (a part of S.B. 800), for the first time expressly connecting provisions of section 2782 to S.B. 800. Contractual provisions not expressly prohibited were reserved to the agreement of the parties.
What subdivision (c) took away was partially given back by subdivision (d). It stated that “subdivision (c) does not prohibit a subcontractor and builder from mutually agreeing to the timing or immediacy of the defense and provisions for reimbursement of defense fees and costs, so long as that agreement, upon final resolution of the claims, does not waive or modify the provisions of subdivision (c).”6 In addition, it stated that this subdivision (c) did not affect the obligations of an insurance carrier under Presley Homes, Inc. v. American States Insurance Company (2001) 90 Cal.App.4th 571, which holds that where an insurer has a duty to defend a developer pursuant to an additional insured endorsement obtained under a subcontractor’s policy, that duty generally applies to the entire action, even if the suit involves both covered and uncovered claims, or a single claim only partially covered by the policy. Finally, subdivision (d) stated that the amendment did not affect the builder’s or subcontractor’s obligations under S.B. 800. Both of these latter provisions, relating to the Presley Homes case, and obligations under S.B. 800, have been carried forward essentially intact in subsequent amendments of section 2782.
This version of section 2782 will be applicable to any contract between a builder as defined by section 911 (see fn. 4, above) and a subcontractor executed between January 1, 2006, and December 31, 2008. Thus, a general contractor, etc., who is not a builder is not subject to the provisions added by the 2005 amendment; this changed with the next amendment.
It is not clear whether this version would apply to a contract entered before January 1, 2006, but amended after that date. Subdivision (c) applies to “all construction contracts, and amendments thereto, entered into after January 1, 2006, for residential construction.” It would seem that the clearest and most logical construction would apply it only to contracts originally made after January 1, 2006, and thereafter amended, but there has been no judicial determination of this issue.
In addition, logically it would seem that this version of section 2782 should be applicable to construction contracts for residential construction between a builder and a subcontractor, entered between January 1, 2006, and December 31, 2008; however, legislative history relating to the 2008 amendment discussed below suggests a different result might occur.
2007 AMENDMENT
The second “post S.B. 800” amendment in 2007 (effective January 1, 2008), added subdivisions (e)(1) and (e)(2).
Subdivision (e)(1) added general contractors and subcontractors not affiliated with the builder and imposed essentially the same restrictions on provisions to indemnify, including the cost to defend, them as had been imposed on the “builder” by the 2005 amendment. The amendment refers to section 911 (b), again part of S.B. 800, to define general contractors, etc., not affiliated with the builder.
Subdivision (e)(1) essentially repeated the provisions of subdivision (d) permitting agreement to the timing and immediacy of the defense, the reference to the Presley Homes case, and the general contractor’s or subcontractor’s obligations under S.B. 800.
It appears this amendment was an attempt to harmonize the new restrictions on indemnity and defense provisions with S.B. 800. The 2005 amendment, whether by oversight or intent, covered only builders and not general contractors, although both classes are subject to the provisions of S.B. 800; the 2007 amendment added non-builder-affiliated general contractors.
Again, logically, it would seem that this version of section 2782 should be applicable to construction contracts for residential construction between a general contractor or contractor not affiliated with a builder and a subcontractor, entered between January 1 and December 31, 2008; however, legislative history relating to the 2008 amendment discussed below suggests a different result might occur. The same potential uncertainty regarding applicability to a contract entered before January 1, 2008, but amended after that date, exists for this provision as for the prior amendment, discussed above.
2008 AMENDMENT
The third “post S.B. 800” amendment in 2008 (effective January 1, 2009), reorganized the language relating to prohibited indemnity provisions, added a reference to insurance in that same prohibition, extensively rewrote the provisions governing agreements relating to the timing or immediacy of defense, added language preserving equitable indemnity claims, and added language defining “construction defect” by reference to the standards set forth in S.B. 800.
Subdivisions (a) and (b) remained unchanged.
Subdivision (c) now made a combined reference to builders (again by reference to section 911), as well as general contractors or contractors not affiliated with the builder (again by reference to section 911 (b)), rather than dealing with the two groups in separate but nearly identical subdivisions as previously. It otherwise restated the same limitations that were previously set forth separately in subdivisions (c) and (e), as well as the reference to the Presley Homes case, and the general contractor’s or subcontractor’s obligations under S.B. 800, but with one important addition. The word “insure” was added to the description of prohibited provisions, to-wit: “provisions? that purport to insure or indemnify, including the cost to defend, the builder, [etc.]? are unenforceable” to the extent they arise out of claims of the type previously described.
It is unclear what impact the addition of this single word “insure” will have; and, it will have to be read in light of the preservation of the language that it shall not affect the obligations of an insurance carrier under the holding of the Presley Homes case. Suppose a carrier had issued an additional insured endorsement under which it would otherwise be required to defend a builder or general contractor consistent with the Presley Homes rule: would this newly added single word (restricting the construction contract, to which the carrier is not a party) give the carrier a basis for denying coverage under the insurance contract? Or would the continued inclusion of the express language that it does not affect the obligations of an insurance carrier under Presley Homes control? That is surely an issue that will have to be worked out by the courts.
The new subdivision (d) addressed defense obligations. Again it permitted parties to agree to the timing and immediacy of the defense and provision for reimbursement of defense fees and costs, but imposed a very detailed scheme that appears to limit the extent of such agreement. A subcontractor owes no defense or indemnity obligation until the builder or general contractor provides a written tender of the claim, which has the same force and effect as notice of commencement of a legal proceeding. Upon that tender the subcontractor shall elect to follow one of two ways of performing: subdivision (d) (1) permits the subcontractor to defend with counsel of its choice and to control the defense, if the subcontractor gives written notice of this election within a reasonable time after receipt of the written tender and in no event later than 90 days following that receipt; subdivision (d) (2) provides an alternative by which the subcontractor pays a reasonable allocated share of the builder’s or general contractor’s defense fees and costs within 30 days of receipt of an invoice, subject to reallocation upon final resolution of the claim by settlement or judgment. Subdivision (e) sets forth remedies available to the builder or general contractor if a subcontractor fails to timely and adequately perform its obligations under either of the two alternatives in subdivision (d), including compensatory and consequential damages, reasonable attorneys’ fees in connection with the first alternative, and interest on defense and indemnity costs in connection with the second alternative. Subdivision (e) ends with provisions relating to reallocation of defense costs, and damages for failure to reallocate.
Application of these requirements in actual litigation is likely to be cumbersome and potentially fraught with conflicts. If retained pursuant to subdivision (d) (1) does the attorney represent the builder, the subcontractor, or both? To whom does the attorney owe his or her fiduciary duty? Can an appropriate informed written consent be formulated, for example, under Rule 3-310 of the California Rules of Professional Conduct, or Rule 1.7, ABA Model Rules of Professional Conduct? Could an attorney retained by a subcontractor blame the subcontractor if that is in the developer’s best interests? If multiple subcontractors elect to defend directly, how would the defense be coordinated among the potentially multiple attorneys so retained? Would an attorney retained by one subcontractor be able, or inclined, to blame another subcontractor who also chose to defend directly, in other words, what would prevent inconsistent defense positions amongst the various counsel retained by subcontractors for the developer? There may be solutions to such practical and professional considerations but it seems an ethical thicket awaits any attorney involved in such circumstances.
Subdivision (e) and (f) preserve equitable indemnity claims for the builder, general contractor or subcontractor, the first in general, the second as against any supplier, design profession, or product manufacturer. Finally, the 2008 amendment added for the first time, in subdivision (h), language defining "construction defect" as used in section 2782 as a violation of standards set forth in S.B. 800.
The inclusion of these last three subsections would seem to work against simplification of litigation. A builder or general contractor is likely to allege a claim for equitable indemnity against any and all subcontractors in addition to claims for contractual indemnity and defense (however limited by the other provisions of section 2782). Nothing in the section suggests the subcontractor should, or even can, somehow take on the representation of the builder, etc., in connection with a claim of equitable indemnity back against the subcontractor.
And the limited definition of “construction defect” in subdivision (h) appears to raise an issue of the applicability of the limitations set forth in subdivision (c). Although there is a school of thought that section 941 limits residential construction defect claims only to breach of the performance standards under S.B. 800, it is still common for CD complaints to plead other legal theories, e.g., breach of contract, breach of warranty, negligence, etc., in addition to violation of S.B. 800 standards. With the addition of subdivision (h) it is arguable that the restrictions on indemnity and defense provisions spelled out in subdivisions (c) and (d), both of which relate to claims for residential construction defects, are applicable only to claims for violation of S.B. 800 standards, and not other residential construction defect claims. In other words, a developer might conceivably still be entitled to a broader scope of indemnity and concomitant defense for other types of claims, such as breach of contract, breach of warranty, negligence, etc., so long as the indemnity does not violate the limitation of subdivision (a) against Type I indemnity, which as noted above, has remained intact through these revisions.
Finally, it would seem that this version of section 2782 should be applicable to contracts executed between builders, general contractors, etc., on the one hand and subcontractors on the other hand on and after January 1, 2009. And, as noted above in connection with the 2005 and 2007 amendments, logic would suggest that those versions would ordinarily apply to contracts executed during the time periods mentioned above. But, the Legislative Counsel’s Digest for the 2008 amendment as it finally was enacted into law includes the following statements:
This bill would delete the provisions applicable to construction contracts entered into on or after January 1, 2008, that purport to indemnify the general contractor or contractor not affiliated with the builder. The bill would revise the provisions applicable to contracts entered into after January 1, 2006, to instead apply to contracts entered into after January 1, 2009, and to apply to agreements that purport to insure or indemnify the builder or the general contractor or contractor not affiliated with the builder, as described.
Although it seems a startling result, this legislative history suggests an argument can be made that the 2008 amendment retroactively nullified the effect of the 2005 and 2007 amendments, so that contracts executed from January 1, 2006, as to builders or January 1, 2008, for general contractors, etc., through December 31, 2008, are still governed by the provisions of section 2782 as it was on the books prior to the first post-S.B. 800 amendment in 2005.
2011 AMENDMENT
Section 2782 has been amended yet again in the 2011 session of the California Legislature, effective January 1, 2012; however, the substantive changes affect certain contracts entered on or after January 1, 2013. All of the provisions contained in the 2008 amendment have been carried forward in the most recent amendment, although re-numbered: (c) became (d), etc., through (h) becoming (i). So, the law governing construction contracts entered into after January 1, 2009, for residential construction, as between a builder, or a general contractor, etc., not affiliated with a builder, and regarding insurance, indemnity or defense relating to claims for construction defects, remains the same as in the 2008 amendment.
As noted above the substantive changes to section 2782 all affect contracts entered into on or after January 1, 2013. Subdivision (b) has been amended such that any provision in a contract with a public agency that purports to impose on any contractor, etc., or relieve the public agency from, liability for the active negligence of the public agency will be void and unenforceable. A new subdivision (c) has been added that imposes a similar restriction on construction contracts with the owner of privately owned real property to be improved and as to which the owner is not acting as a contractor or supplier of materials or equipment to the work. This new restriction in subdivision (c) does not apply to a homeowner performing a home improvement project on his or her own single family dwelling.
The 2011 bill amending section 2782 also added a new section 2782.05, which will make void and unenforceable any provision in any construction contract (again, entered on or after January 1, 2013) that purports to insure or indemnify, including the cost to defend, a general contractor, construction manager, or other subcontractor, by a subcontractor for claims that arise out of the active negligence or willful misconduct of the general contractor, etc., or other independent contractors, etc., or to the extent the claims do not arise out of the scope of work of the subcontractor. However, the section also includes a long list of situations to which it does not apply, including all of those covered by section 2782 (residential construction subject to S.B. 800, public agency contracts subject to section 2782 (b), and direct contracts with private property owners subject to the new section 2782 (c)) as well as eight other categories. This apparently is intended to serve as a “catch-all” to extend a limitation on indemnity agreements to all construction contracts not previously swept into this widening legislative scheme, although the exact phrasing is slightly different.7
The new section 2782.05 then permits a mutual agreement to the timing or immediacy of a defense under a scheme essentially identical to that imposed in the 2008 amendment to section 2782: defend with counsel of choice, and maintain control of the defense; or, pay a reasonable allocated share of defense fees and costs. The same logistical and ethical difficulties presented by the 2008 scheme discussed above would likely be present in cases that fall under the new section 2782.05.
CONCLUSION
The California Legislature has been revising section 2782 since shortly after the adoption of S.B. 800. Each revision has been more complicated than the last, and each has tied certain provisions of section 2782 more closely to S.B. 800. In particular, with regard to construction defect claims relating to residential dwellings which are subject to S.B. 800, the Legislature has apparently attempted to exercise more and more control over the scope of allowable indemnity and dictated a very narrow scheme to govern how the defense obligation arising from a contractual indemnity is to be implemented. It seems likely that any attempt to manage the defense of a construction defect case under the options that allow a subcontractor to defend directly and control the defense will create a logistical problem and an ethical difficulty for any attorney attempting to defend a developer at the behest and direction of a subcontractor. Finally, as set forth in the current version of section 2782 relating to contractual indemnity and defense of S.B. 800 type cases (subdivisions (c) through (h) in the 2008 version, now subdivisions (d) through (i) in the 2011 amendment), the Legislature has apparently narrowed the application to only claims of violation of S.B. 800 standards. This may have, in essence, removed the restrictions on indemnity and defense provisions as they relate to other theories pleaded against developers in construction defense cases, e.g., breach of contract, breach of warranty, negligence, and the like. It is not at all clear that the Legislature has accomplished what it set out do accomplish. Rather, the law may have come full circle back to where it began, except for one legal theory, i.e. violation of S.B. 800 standards, currently being used in residential construction defect cases. For any other legal theory the limitation of section 2782 (a) may be solely controlling.
- California Civil Code section 43.99, and sections 895 to 945.5.
- All statutory references in this article are to the California Civil Code unless otherwise specified.
- Type I or specific indemnity does not exactly match the scope of proscribed indemnity as described in section 2782 (a) but it is the closest. More recent case law in California has eschewed a mechanical application of the MacDonald & Kruse typology in favor of examining the precise text of the actual contract (See, e.g., St. Paul Mercury Ins. Co. v. Frontier Pacific Ins. Co. (2003) 111 Cal.App.4th 1234, 1246, n. 6) but some recent cases still use the Type I, II and II classifications. And, an understanding of that “historical” typology is useful as an aid to evaluating and understanding express indemnity in general.
- The provisions of S.B. 800 other than the prelitigation procedures of sections 910 through 938 apply to general contractors, subcontractors, etc., pursuant to section 936. The prelitigation procedures generally involve a “builder,” which is specifically defined in section 911 (a) by reference to entities or individuals in the business of selling residential units to the public or of building, developing, or constructing residential units for public purchase. Pursuant to section 911 (b) the term builder does not include general contractors, etc., not affiliated with the builder. Thus, a general contractor who constructs residential housing pursuant to a contract with a public agency is still subject to claims for violation of the standards set forth in sections 896 and 897, resulting from its negligent act or omission or breach of contract, pursuant to section 936.
- As noted above, there has been no case law yet interpreting any of the “post S.B. 800” changes to Section 2782. One of the most important legal decisions relating to express indemnity and defense obligations and rights between developer-builders and sub-contractors was published after two of the amendments but based upon contracts executed and the language of section 2782 prior to January 1, 2006. (See, Crawford v. Weather Shield Mfg., Inc. (2008) 44 Cal.4th 541, 547, 566-67, fn. 14).
- Subcontractor dissatisfaction with the perceived inadequacy of protection afforded by this provision apparently became the impetus for a 2008 amendment to section 2782, discussed below, at least based upon the numerous (form) letters submitted to legislators in connection therewith.
- Section 2782 (a), where we started, and which has continued without change, prohibits indemnity for claims arising out of the sole negligence or willful misconduct of the promisee; sole negligence can be either active or passive. The various versions relating to residential construction prohibit indemnity for the negligence of the builder, etc., suggesting there is no express contractual indemnity for the negligence of the subcontractor if the builder, etc., is at all negligent. This is tempered a bit by the preservation of the right to equitable indemnity, which will now be found in section 2782 (g) and (h).
Courtesy of Michael D. Worthing of Borton Petrini, LLP. Mr. Worthing can be contacted at mworthing@bortonpetrini.com.
Florida Construction Defect Case Settled for $3 Million
June 19, 2012 — CDJ Staff
The Runaway Beach Club Condominium Association of Kissimmee, Florida has settled its construction defect claims against the parties involved in the construction and development of the buildings. The association claimed that defective roofs and improperly installed windows had lead to leaks and associated damages. A trial date had been set, but parties involved were able to reach this settlement instead.
Read the full story…
Georgia Law: “An Occurrence Can Arise Where Faulty Workmanship Causes Unforeseen or Unexpected Damage to Other Property”
March 5, 2011 — By
CDCoverage.com, March 5, 2011
In American Empire Surplus Lines Ins. Co. v. Hathaway Development Co., Inc., No. S10G0521 (Ga. March 7, 2011), insured plumbing subcontractor Whisnant was sued by general contractor Hathaway seeking damages for costs incurred by Hathaway in repairing damage to property other than Whisnant’s plumbing work resulting from Whisnant’s negligently performed plumbing work on three separate projects. On one project, Whisnant installed a pipe smaller
Read the full story...Reprinted courtesy of CDCoverage.com
Recent Case Brings Clarity and Questions to Statute of Repose Application
August 16, 2012 — Douglas Reiser, Builders Counsel
I have often chatted about the Washington Statute of Repose on this blog. The Statute of Repose prevents construction claims, for the most part, from being raised 6 years from the date of substantial completion or termination. Well, a recent Court of Appeals case dove deep into the specific determinative factors that tell us when to start the clock. It certainly raises questions about how long we really have to file suit.
The Statute of Repose has been a frequent topic here, so I will simply direct you to my prior post for further information on how this law works. A recent post was published about a lawsuit that might raise some questions about when and how the clock begins to roll, and claim periods begin to diminish.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
After $15 Million Settlement, Association Gets $7.7 Million From Additional Subcontractor
November 7, 2012 — CDJ Staff
The stucco subcontractor for a condominium complex did not join in with the other defendants in a settlement of more than $15 million, preferring to take the case to a jury trial. That jury has found the stucco installer liable for $7.7 million to make repairs. Mark Wiechnik of Herrick Feinstein LLP wrote about the case on the Lexology web site. Mr. Wiechnik notes that the jury was shown “samples of rotted wood taken from the property as well as numerous pictures of damage resulting from the various defects.”
Read the full story…
Foundation Arbitration Doesn’t Preclude Suing Over Cracks
March 28, 2012 — CDJ Staff
The Louisiana Court of Appeals has reversed the decision of a lower court, allowing a construction defect case to go through. In Greer v. Town Construction Company, the Greers hired Town Construction to build a home in Baton Rouge. The business relationship went sour, with disputes over “costs, change orders, workmanship, and timeliness issues.”
Town Construction filed an arbitration claim for the unpaid contract balance. In the counterclaim, the Greers made claims of mold and mildew problems, and wall cracks that they attributed to a “structural defect in the foundation.” In arbitration, Town Construction was awarded the full contract balance plus extra costs and interest, while the Greers were awarded for their structural claims.
Three years later, the Greers found additional cracks and filed a suit against Town Construction. Town Construction argued that the Greer’s lawsuit should be dismissed, as the claims had already been through the arbitration process. The district court agreed with Town Construction and dismissed the suit.
The appeals court noted that the Greers would have no ground for a suit if the arbitration was a “valid and final judgment,” and went on to note that there was no evidence in the trial record that the arbitration met this qualification. The court noted that although it was clear that both parties had agreed to the decisions of the arbiter, under Louisiana law, arbitration is not final until it has been “rendered by a court with jurisdiction over subject mater and over parties.”
The court remanded the case to the lower court, noting that “the district court is obligated to first determine whether a valid arbitration award is in existence and had been confirmed before considering the merits of the exception. The court noted that their decision “should not be read to express any opinion as to the merits of the claims or as to the propriety of damages sought in the Greer’s lawsuit.”
Read the court’s decision…
Workers Hurt in Casino Floor Collapse
February 10, 2012 — CDJ Staff
More than a dozen construction workers fell about thirty feet when a floor collapsed in a Cincinnati casino. The workers were pouring cement on the second-floor level when the accident happened. The area in question will be the gaming area in the completed casino. Scott Allen, OSHA’s regional spokesperson, said their investigation of the accident would probably take about a month to complete.
The cause of the collapse is still undetermined. Although the weather has been wet in the area, experts thought it unlikely to be the cause. A construction forensics professor at Ohio State University said that “concrete pouring is very common” and that “you cannot go wrong unless something happens with the connection.” Engineering experts said it was more likely an issue with the metal decking.
Read the full story…
Restitution Unlikely in Las Vegas Construction Defect Scam
October 23, 2012 — CDJ Staff
The San Francisco Chronicle reports that the money lost in the Las Vegas HOA fraud cause is probably not recoverable. Victims of the scam have asked the court for restitution, but Judge Lloyd George doubts any of the money will be found, saying “the money is not available, it would appear.”
One Vistana board members not part of the conspiracy told reporters that the $8 million construction defect settlement never went for needed repairs. “Within six months that money was gone,” said Bruce Wallace, a retired Air Force colonel. After the construction defect account was depleted to $450,000, two board members disappeared with the funds.
Read the full story…
The Montrose Language Interpreted: How Many Policies Are Implicated By A Construction Defect That Later Causes a Flood?
March 17, 2011 — By Shaun McParland Baldwin, March 17, 2011
The Court of Appeals of Indiana recently addressed the “Montrose” language added to the CGL ISO form in 2001 in the context of a construction defect claim where a fractured storm drain caused significant flooding a year after the drain was damaged. The insuring agreement requires that “bodily injury or “property damage” be caused by an occurrence and that the “bodily injury or “property damage” occur during the policy period. The Montrose language adds that the insurance applies only if, prior to the policy period, no insured knew that the “bodily injury or “property damage” had occurred in whole or in part. Significantly, it also states that any “bodily injury” or “property damage” which occurs during the policy period and was not, prior to the policy period known to have occurred, includes a continuation, change or resumption of that “bodily injury” or “property damage” after the end of the policy period.
In Grange Mutual Cas. Co. v. West Bend Mut. Ins. Co., No. 29D04-0706-PL-1112 (Ct. App. IN March 15, 2011), http://www.ai.org/judiciary/opinions/pdf/03151109ehf.pdf, Sullivan was the General Contractor for a school construction project. Its subcontractor, McCurdy, installed the storm drain pipes. One of the storm pipes was fractured in 2005 while McCurdy was doing its installation work. More than a year later, the school experienced significant water damage due to flooding. It was later discovered that the flooding was due to the fractured storm drain. Sullivanrsquo;s insurer paid $146,403 for the water damage. That insurer brought a subrogation claim against McCurdy and its two insurers: West Bend and Grange. West Bend had issued CGL coverage to McCurdy while the construction was ongoing, including the date in which the storm pipe was fractured. Grange issued CGL coverage to McCurdy at the time of the flooding. Those two carriers jointly settled the subrogation claim and then litigated which insurer actually owed coverage for the loss. Significantly, the loss that was paid included only damages from the flooding, not any damages for the cost of repairing the pipe.
Read the full story...
Reprinted courtesy of Shaun McParland Baldwin of Tressler LLP. Ms Baldwin can be contacted at sbaldwin@tresslerllp.com
Ohio “property damage” caused by an “occurrence.”
May 18, 2011 — May 18, 2011 - CDCoverage.com
In JTO, Inc. v. State Automobile Mut. Ins. Co., No. 2010-L-062 (Ohio Ct. App. March 25, 2011), general contractor JTO was sued by hotel project owner Marriott for breach of contract and warranties seeking damages for the repair of construction defects resulting in moisture penetration property damage to interior components. JTO filed a third party complaint against subcontractor Farizel and also tendered its defense as an additional insured under Farizel’s State Auto CGL policy.
Read the full story…
Reprinted courtesy of CDCoverage.com
Census Bureau, HUD Show Declines in Residential Construction
May 17, 2011 – CDJ Staff
The U.S. Census Bureau and the Department of Housing and Urban Development released their summary of residential construction for April 2011 on May 17.
Building permits for privately owned housing units were down 4% from last month and 12% from last year. Similarly, privately-owned housing starts were down 10% from March and 23% below the previous year.
For further details, read the Census Bureau/HUD report
Federal Judge Dismisses Insurance Coverage Lawsuit In Construction Defect Case
December 9, 2011 — CDJ Staff
A federal judge dismissed a coverage lawsuit brought by Mid Continent Casualty Company against its insured, Greater Midwest Builders Ltd.
Plaintiff brought this declaratory judgment action in response to a suit filed in Johnson County District Court, seeking a judicial determination that it had no coverage obligation for claims asserted against its insured. This case was stayed until the state court action entered judgment against the insured. The prevailing parties then commenced a garnishment action against the plaintiff, and another insurance company, in state court in Missouri. The court was asked whether it should lift the stay and proceed with the case, or decline jurisdiction in favor of resolution in the Missouri state court.
The court granted the motion to dismiss holding that proceeding with the case would lead to protracted, piecemeal litigation, while deferring to the Missouri state court would decide all the claims involved in the dispute.
Read the court’s decision…
South Carolina “occurrence” and allocation
September 1, 2011 — CDCoverage.com
In Crossman Communities of North Carolina, Inc. v. Harleysville Mutual Insurance Co., No. 26909 (S.C. Aug. 22, 2011), insured Crossman was the developer and general contractor of several condominium projects constructed by Crossman’s subcontractors over multiple years. After completion, Crossman was sued by homeowners alleging negligent construction of exterior components resulting in moisture penetration property damage to non-defective components occurring during multiple years. Crossman settled the underlying lawsuit and then filed suit against its CGL insurers to recover the settlement amount. Crossman settled with all of the insurers except for Harleysville. Crossman and Harleysville stipulated that the only coverage issue was whether there was an “occurrence.” The trial court subsequently entered judgment in favor of Crossman, determining that there was an “occurrence.” The trial court also ruled that Harleysville was liable for the entire settlement amount without offset for the amounts paid by the other insurers.
Read the full story…
Reprinted courtesy of CDCoverage.com
New Construction Laws, New Forms in California
July 10, 2012 — CDJ Staff
New construction laws came into effect in California on July 1. Writing for the Martindale-Hubble Legal Library, Glenn Mau, J. Michael McGuire, and John Tonsing, all of Archer Norris, discuss these changes. They note that the most important part of the changes to California construction law is that “all mechanics liens, stop notices and bond claims recorded after July 1, 2012 must use the new standardized forms and follow the new definitions, notice prerequisites and statutory release form language.”
Read the full story…
No Coverage For Damage Caused by Chinese Drywall
October 28, 2011 — Tred Eyerley, Insurance Law Hawaii
The pollution exclusion barred coverage for alleged property damage and bodily injury in Evanston Ins. Co. v. Harbor Walk Dev., LLC, No. 2:10cv312 (E.D. Va. Sept. 9, 2011).
Homeowners sued the insured, Harbor Walk, in three lawsuits, alleging the Chinese drywall installed in their homes emitted sulfides and other noxious gases. This caused corrosion and damage to the air-conditioning and ventilation units, refrigeration coils, copper tubing, faucets, metal surfaces, electrical appliances and other personal items. The homeowners also alleged the compounds emitted by the drywall caused bodily injury, such as allergic reactions, headaches, etc.
Harbor Walk’s insurer, Evanston, filed for a declaratory judgment that the pollution exclusion precluded coverage.
Read the full story...
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
David McLain to Speak at the CDLA 2012 Annual Conference
June 19, 2012 — CDJ Staff
The Colorado Dense Lawyers Association will be holding their 2012 Annual Conference from July 26 through the 28, in Crested Butte, Colorado. The CDLA provides benefits to its member defense trial lawyers, including educational and information resources.
David McLain of Higgins, Hopkins, McLain & Roswell, LLC will be joining in a discussion with William J. McConnell, PE of Vertex Engineering on Saturday, July 28. Their topic will be common building code violations alleged in construction defect cases and how to respond to these allegations.
Read the full story…
HOA Has No Claim to Extend Statute of Limitations in Construction Defect Case
October 28, 2011 — CDJ Staff
The California Court of Appeals ruled on September 20, 2011 in the case of Arundel Homeowners Association v. Arundel Green Partners, a construction defect case involving a condominium conversion in San Francisco. Eight years after the Notice of Completion was filed, the homeowners association filed a lawsuit alleging a number of construction defects, including “defective cabinets, waterproofing membranes, wall-cladding, plumbing, electrical wiring, roofing (including slope, drainage and flashings), fire-rated ceilings, and chimney flues.” Three years of settlement negotiations followed.
Negotiations ended in the eleventh year with the homeowners association filing a lawsuit. Arundel Green argued that the suit should be thrown out as California’s ten-year statute of limitations had passed. The court granted judgment to Arundel Green.
The homeowners then filed for a new trial and to amend its complaint, arguing that the statute of limitations should not apply due to the doctrine of equitable estoppel as Arundel Green’s actions had lead them to believe the issues could be solved without a lawsuit. “The HOA claimed that it was not until after the statute of limitations ran that the HOA realized Arundel Green would not keep its promises; and after this realization, the HOA promptly brought its lawsuit.” The trial court denied the homeowners association’s motions, which the homeowners association appealed.
In reviewing the case, the Appeals Court compared Arundel to an earlier California Supreme Court case, Lantzy. (The homeowners also cited Lantzy as the basis of their appeal.) In Lantzy, the California Supreme Court set up a four-part test as to whether estoppel could be applied. The court applied these tests and found, as was the case in Lantzy, that there were no grounds for estoppel.
In Arundel, the court noted that “there are simply no allegations that Arundel Green made any affirmative statement or promise that would lull the HOA into a reasonable belief that its claims would be resolved without filing a lawsuit.” The court also cited Lesko v. Superior Court which included a recommendation that the plaintiffs “send a stipulation?Ķextending time.” This did not happen and the court upheld the dismissal.
Read the court’s decision…
Colorado Court of Appeals holds that insurance companies owe duty of prompt and effective communication to claimants and repair subcontractors
March 1, 2011 — Courtesy
Colorado Construction LitigationIn Dunn v. American Family Insurance, 09CA2173, 2010 WL 4791948 (Colo. App. Nov. 24, 2010), the Dunns reported a claim to American Family on their homeowners insurance policy after sewer and water backup caused sewage to flood their basement. American Family gave the Dunns contact information for a contractor (ICA) to remediate the flooding. However, ICA was unsuccessful and sewage began to infiltrate the Dunns’ HVAC system. Subsequently, black mold was detected in the HVAC system, the Dunns suffered health and respiratory problems, and they soon after vacated the home. The Dunns hired and fired two more contractors for unsatisfactory work throughout the winter before hiring a fourth to finish the job. Because the home remained vacant and unheated throughout the winter, the water pipes ruptured. The mold spread throughout the entire home and all of the contents needed to be replaced, which amounted to a claim of $340,000 on the policy.
American Family agreed to pay the full $340,000. However, the Dunns brought suit claiming that American Family breached the implied duty of good faith and fair dealing by: 1) failing to screen ICA for expertise; 2) failing to screen ICA for liability insurance coverage; 3) failing to monitor ICA’s work; 4) failing to advise them that flooding can cause further damage, including freezing pipes and mold; and, 5) failing to adequately and promptly communicate with them and remediation subcontractors in the course of investigating and handling their claim.The trial court found no duty owed by American Family beyond adjustment and timely payment of claims. Because American Family paid timely and in full, they dismissed all of the Dunns’ claims. However, the Court of Appeals reversed in part.
Read the full story...
Reprinted courtesy of Chad Johnson, Higgins, Hopkins, McLain & Roswell, LLC. Mr. Johnson can be contacted at johnson@hhmrlaw.com
Washington Court of Appeals Upholds Standard of Repose in Fruit Warehouse Case
August 4, 2011 — CDJ Staff
On July 28, the Washington Court of Appeals ruled in Clasen Fruit & Cold Storage v. Frederick & Michael Construction Co., Inc. that more than six years had passed since a contractor had concluded work and so granted a summary dismissal of the suit.
Frederick & Michael Construction Co., Inc. (F&M) was contracted to construct several buildings for Clasen Fruit and Cold Storage. These were completed in March, 1999. The buildings suffered wind damage to the roofs in 2001, 2003, 2005, and 2006. In the first two incidents, F&M repaired the roofs with Clasen paying for repairs.
In 2005, Clasen hired Continuous Gutter to make repairs. The final incident was the collapse of the roof of one building. This was attributed to “excessive moisture in the roof’s vapor barriers.” At this point, Clasen demanded that F&M pay for repair and replacement costs. In 2008, Clasen sued F&M for damages for breach of contract and negligent design and construction of the roof.
The decision then covered the meanings, in Washington law, of “termination of services” and “substantial completion.” The panel concluded that construction was “substantially completed in 1997” and “relevant services” by 2001. “But Clasen did not sue until 2008, some seven years after termination of any roof related services.”
Read the court’s decision…