Gut Feeling Does Not Disqualify Expert Opinion
July 6, 2011 — CDJ Staff
The New Jersey Supreme Court issued a ruling in June on the case of Nevins v. Toll in which they reversed an earlier decision and remanded the case to a lower court for retrial. At issue in the case was the testimony of the plaintiff’s expert, J. Anthony Dowling. In depositions, Mr. Dowling said that his estimates for repair were based on a “gut feeling.” Dowling said he had “very little” experience in cost estimates for single-family homes. The defendants sought to bar Dowling’s testimony which was granted by the judge. Without an expert, Ms. Nevin’s case was dismissed.
Describing Dowling’s report as “far from a model of how an expert’s opinion in a construction case should be presented,” the court noted that Dowling is not a professional expert witness. However, the court did note that Dowling is a professional cost estimator. Despite Mr. Dowling using his “gut feeling” to construct his estimate, the New Jersey Supreme Court felt that whether his estimate is convincing is “a question for the jury.”
Read the court’s opinion…
Federal District Court Continues to Find Construction Defects do Not Arise From An Occurrence
May 10, 2012 — CDJ Staff
Coverage for construction defects continues to be hotly contested in Hawaii state and federal courts. In a recent decision, Judge Mollway felt bound to follow the Ninth Circuit’s decision in Burlington Ins. Co. v. Oceanic Design & Constr., Inc., 383 F.3d 940, 944 (9th Cir. 2004), where the court found construction defect claims arise from breach of contract, not from an occurrence. Judge Mollway’s most recent decision on the issue is Illinois Nat. Ins. Co. v. Nordic PCL Constr., Inc., 2012 U.S. Dist. LEXIS 58464 (D. Haw. April 26, 2012).
Nordic constructed a grocery store for Safeway. In addition to the grocery store, Nordic built a 165-space rooftop parking deck, retail shops and related improvements. After opening for business in 2007, Safeway experienced significant leaks. Safeway demanded that Nordic repair the parking deck. Nordic sent the demand letter to the insurer, who agreed to appoint counsel subject to a reservation of rights.
Safeway filed suit against Nordic in state court alleging, among other things, breach of contract and negligence. The insurer provided Nordic with a defense, but Nordic hired independent counsel.
The insurer filed for declaratory relief in federal district court.
Read the full story…
Renovation Contractors: Be Careful How You Disclose Your Projects
December 9, 2011 — Derek J. Lindenschmidt, Colorado Construction Litigation
In Palu and Beyer v. Toney, 2011 WL 2560249 (Bankr. D. Colo.), the United States Bankruptcy Court for the District of Colorado determined that a Colorado District Court order granting summary judgment in favor of plaintiff home buyers was binding on the Bankruptcy Court in the defendant contractor’s bankruptcy proceeding based on issue preclusion.
Pertinent to this column is the subject matter of the summary judgment motion: Colorado’s Seller’s Property Disclosure (Form LC-18-5-04). In the underlying state court action, the plaintiff home buyers filed a motion for summary judgment contending that the defendant contractor represented to them, through the Seller’s Property Disclosure, that there were no present or past conditions involving moisture or water problems, roof problems or leaks, skylight problems, or gutter downspout problems.
In granting plaintiffs’ motion, the state court determined that the defendant contractor made these representations on her Seller’s Property Disclosure despite witnessing water leaking from the skylight onto the floor and being aware of repairs to the roof, skylight, and interior drywall prior to the sale of the property.
Read the full story…
Reprinted courtesy of Derek J. Lindenschmidt of Higgins, Hopkins, McClain & Roswell, LLP. Mr. Lindenschmidt can be contacted at lindenschmidt@hhmrlaw.com
Denver Court Rules that Condo Owners Must Follow Arbitration Agreement
November 7, 2012 — CDJ Staff
Prior to initiating a construction defect lawsuit, the Glass House Residential Association voted to invalidate the arbitration agreement that had been written into its declaration and bylaws by the developer and general contractor. After the association started their construction defect claims, the developer and general contractor argued that the case must go to arbitration, as the arbitration clause contained a provision that it could not be altered without the agreement of the developer and general contractor.
The Denver District Court has ruled against that association, determining that the res triction was not in violation of Colorado condominium law. And, as a post from Polsinelli Shughart PC on JDSupra notes, the Colorado Common Interest Ownership Act encourages the use of arbitration procedures to settle disputes. The CCIOA does prohibit “certain restrictions on the homeowners association’s ability to amend the condominium declarations,” however, preserving an arbitration agreement is not one of them.
Read the full story…
Court finds subcontractor responsible for defending claim
May 18, 2011 — May 18, 2011 - CDJ Staff
In an unpublished decision, the California Fourth Appellate District Court has reversed the judgment of Judge Linda B. Quinn of the Superior Court of San Diego. In the case Inland California, Inc. v. G.A. Abell, Inland, a general contractor had subcontracted with Apache Construction and Precision Electric Company (G.A. Abell).
Apache alleged that extra demolition and drywall work was needed due to Precision’s electrical work. Inland tendered a defense of Apache’s claims. However, Precision did not provide any defense. Inland withheld payment from Precision.
At trial, Inland “conceded Precision earned the $98,000 in progress payments Inland withheld.†They were obligated to additionally pay Precision’s costs and attorney fees.
The Fourth Appellate District court has overturned this and remanded the case back to the lower court. The judges determined that Precision was obligated to defend itself against the claims raised by Apache and therefore vacated the judgment against Inland.
Read the court’s decision…
Insurance for Defective Construction Now in Third Edition
November 7, 2012 — CDJ Staff
Available both in print and online, the International Risk Management Institute, Inc has brought out a third edition of Insurance for Defective Construction. The work is written by Patrick J. Wielinski of Cokinos, Bosien & Young, a Dallas-Fort Worth law firm. Mr. Wielinski practice focuses on insurance coverage. Insurance for Defective Construction is described as “a must read for anyone who buys, sell, or underwrites construction insurance or who becomes involved in construction claims.”
Read the full story…
Quarter Four a Good One for Luxury Homebuilder
December 20, 2012 — CDJ Staff
Toll Brothers has announced that their fourth-quarter net income is $2.35 per share, which they attribute in part to an income tax benefit. Their revenue, at $632.8 million, easily exceeded analysts’ projections of $565.1 million. Additionally, their number of signed contracts jumped seventy percent while their cancellation rate dropped nearly half to 4.9 percent.
Read the full story…
Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses
April 25, 2012 — Douglas Reiser, Builders Cousel
Ever had that lingering problem with a contracting partner that went away for awhile and then came back to bite you ? years later? In Washington, construction contract claims can be raised for up to six years after substantial completion. Six years!? Why would I want to wait that long to find out if I have a problem? You don’t have to.
Over the past few years, I have discussed the notion of “contractual claim periods” on The Builders Counsel. For today’s Save a Legal Fee column, I cannot think of a better topic. These provisions are specifically intended to save you from unnecessary legal fees that might arise if a problem goes unnoticed for too long.
Contractual claim periods are simply a way to reduce the amount of time that a contracting party has to raise a claim against its contracting partner. For example, a subcontractor might require that a general contractor raise any claim that it might have ? for defective or incomplete work, injury, damages, etc ? within a particular amount of time or forever lose the ability to raise the claim in a legal proceeding.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Construction Defect Litigation at San Diego’s Alicante Condominiums?
March 25, 2011 — Alicante HOA Website
According to recent posts in the Alicante HOA website, construction experts and legal counsel have been retained. The HOA board has been informed that testing of a variety of the building’s components are underway or will begin in the near future.
Read More...
Architectural Firm Disputes Claim of Fault
May 27, 2011 — CDJ Staff
Lake-Flato Architects has disputed the arbitration panel’s conclusion that problems with the home of Tom Hanks and Rita Wilson were due to design flaws. The firm settled with the couple for $900,000, however the Idaho Mountain Express reports that David Lake said, “the settlement in the case in no way represents that Lake Flato was responsible for faulty design.” The Express reported that “the arbitrators found that problems at the home were attributable to design errors that did not take into account the cold winter climate of the Sun Valley area.”
Read the full story…
Contractor’s Home Not Covered for Construction Defects
September 13, 2012 — CDJ Staff
The US District Court in Seattle has rejected most of the claims made by a Des Moines man over insurance coverage for water damage to his home. Judge John C. Coughenour granted summary judgment to Liberty Northwest in Ayar v. Liberty Northwest Insurance Corporation.
Sayad Ayar was the general contractor for the construction of his house. As a homeowner held a $1.5 million insurance policy from Liberty Northwest (LNW) that excluded “faulty, inadequate, or defective construction.”
In 2008, less than three years after his house was constructed, Mr. Ayar filed a claim after water leaked through his living room ceiling. LNW hired an engineering firm to investigate the damage. The engineering firm, CASE Forensics, concluded that the water intrusion was due to “the failure to install an adequate and continuous waterproof membrane, flashing, and drainage system within the balcony at the time of construction.” Ayar’s expert attributed the leakage to “damage done to the weather deck waterproofing during a storm event with high winds,” which would be covered under the policy. CASE Forensics reviewed these conclusions and rejected them. LNW denied coverage.
Further problems lead to further investigations, and in each case, LNW attributed the problems to construction defects. During this process, LNW “authorized Ayar to cut into the ceiling’s drywall in order to assist in determining the source of the water intrusion.” Mr. Ayar moved his family to a rental home. He requested that LNW cover the rental and other other costs.
LNW’s adjuster concluded that no coverage was available, but recommended paying Mr. Ayar $19,648.68 to reinstall drywall and repair the hole in the ceiling. The insurance company paid $2,000 to cover the cost of cutting into the ceiling. The also claimed the amount of drywall he removed was “excessive” and would not cover his relocation as “his home had been livable and because the loss was not covered.”
Ayar made four claims to the court in support of the argument that LNW misrepresented “pertinent facts or insurance policy provisions.” The court rejected three of these, noting that as all water damage was excluded, LNW’s citation of other sources of water intrusion was not a misrepresentation. “LNW did not rely on this provision as the reason for denying coverage.” Nor was LNW’s reference to “fungi, wet or dry rot” a misrepresentation. As for their reference to construction defects, it “was clearly appropriate given that the construction defect exclusion was the principal basis or denying the claim.” However, the court found that regarding the removal of drywall, “a triable issue of the facts exists.”
Ayar also claimed that LNW did not conduct a reasonable investigation, but the court found no evidence to support this conclusion. “This is not a case where the insurer failed to investigate or did so only half-heartedly.” Although the thoroughness of the investigation could not questioned, the court concluded that its timing could. Ayar claimed that LNW engaged in unreasonable delays. LNW counters that the delays were due to “Ayar’s own obstructive behavior and failure to cooperate with LNW’s investigation.”
The court dismissed all of Ayar’s claims, with the exception of whether LNW should have informed him that they would not pay for drywall repair unless there was damage, and whether LNW’s investigation failed to conclude its investigation within a thirty-day time line.
Read the court’s decision…
Manhattan Developer Breaks Ground on $520 Million Project
November 18, 2011 — CDJ Staff
Rebuilding an area of Midtown West that has been condemned for decades, the Gotham Organization has broken ground on a 1,200-unit project that will include housing for a variety of household incomes and a school. One unit of the project will be affordable housing for families of annual incomes up to $40,000. Another will be for middle-income households. Additionally, there will be a 31-story tower with 550 luxury units.
The site CityBiz quotes Mayor Michael Bloomberg, as saying that the project “will grow our economy by creating 2,900 construction-related jobs.” The president of the Gotham Organization, David L. Picket notes that it will “create hundreds of new jobs, generate millions of dollars in revenue for the construction industry, contribute towards the building of a new primary, and provide homes to thousands of New Yorkers.”
Read the full story…
After Construction Defect Case, Repairs to Austin Building
August 2, 2012 — CDJ Staff
The Austin Business Journal reports that remediation is about to begin on Met Center 10, a building that was “at the center of a complex structural defect case.” Claims were made that Grubb & Ellis failed to disclose known structural defects to a group of investors who purchased the building. The brokerage was ordered to pay $6.75 million. Repairs will take an estimated six months at a cost of $3.7 million.
Read the full story…
After $15 Million Settlement, Association Gets $7.7 Million From Additional Subcontractor
November 7, 2012 — CDJ Staff
The stucco subcontractor for a condominium complex did not join in with the other defendants in a settlement of more than $15 million, preferring to take the case to a jury trial. That jury has found the stucco installer liable for $7.7 million to make repairs. Mark Wiechnik of Herrick Feinstein LLP wrote about the case on the Lexology web site. Mr. Wiechnik notes that the jury was shown “samples of rotted wood taken from the property as well as numerous pictures of damage resulting from the various defects.”
Read the full story…
Insurance Company Must Show that Lead Came from Building Materials
August 17, 2011 — CDJ Staff
The Fourth Circuit Court of Appeals for Louisiana has reversed the summary judgment of a lower court in the case of Widder v. Louisiana Citizens Property Insurance Company. Judge Roland L. Belsome wrote the opinion for the panel of three judges. Ms. Widder discovered that her home and its content were contaminated by lead. She applied to her insurer, Louisiana Citizens Property Insurance, which denied her claim.
In response to Ms. Widder’s suit, LCPIC applied for a summary judgment on the grounds that there was no physical loss and that the policy did not cover defective material, latents defects, and pollution damage.
The appeals court found that the lead contamination of Widder’s home did meet the standards of a direct physical loss, citing a recent Chinese Drywall case. There, it was found, “when a home has been rendered unusable or uninhabitable, physical damage is not necessary.”
The lower court addressed only one of LCPIC’s exclusions, addressing only the exclusion on basis of “faulty, inadequate or defective material.” The appeals court noted that the evidence offered at trial does not show that the building materials were the source of the lead. This provided the appeals court with a matter of fact to remand to the lower court.
Read the court’s decision…
Defective Shingle Claims Valid Despite Bankruptcy
June 19, 2012 — CDJ Staff
The Third Circuit Court has allowed claims to go forward against Owens Corning for making allegedly defective shingles. The shingles split, leading to leaking roofs. The building products manufacturer filed for bankruptcy in 2000, which “extinguished” claims against it. The company was facing millions in liabilities over asbestos lawsuits.
The lawsuit was filed in 2009. The courts initially found the lawsuit timely, but the Third Circuit Court later applied determined the exposure stated before the bankruptcy. On appeal, the court has reversed this and is again allowing the suit to proceed.
Read the full story…
2011 Worst Year Ever for Home Sales
September 9, 2011 — CDJ Staff
So few new single-family homes have sold in 2011 that expectations are that this will be the worst year for new homes sales since the Commerce Department started tracking this in 1963. The Harford Courant notes that previously builders created a new supply to which was added homes under foreclosure.
Ed Leamer, economist and director of UCLA’s Anderson Forecast, says that recovery would be driven by two sectors, manufacturing and construction. “It doesn’t look like there is going to be a big recovery in manufacturing,” he says. “It is going to have to come in housing.”
The soft housing market, however, is leading to a loss of construction jobs, as reported by the Associated General Contractors of America. As a result, stock prices for the twelve largest publicly-traded home builders have declined 22.7 percent in a market that has declined 4.2 percent overall.
Read the full story…
Changes To Indemnification Statute Are Here! Say Hello To Defense Duties
June 19, 2012 — Douglas Reiser, Builders Counsel
A months back, I discussed the passage of SHB 1559. The law changes the existing statutory indemnification regulation to include the costs of defense and to rid contracts of unfair indemnification for someone else’s sole negligence. The law went into effect last week!
Check back to my recent article on the changes set forth in the new law. The amendments to RCW 4.24.115 will broaden the existing law and clarify what types of indemnification are unenforceable. In short, an “up the chain” contractor (such as a general contractor) cannot expect to pass 100% of the defense and indemnification obligations downward if it is partially liable.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com