Illinois Court Determines Insurer Must Defend Property Damage Caused by Faulty Workmanship
July 11, 2011 — Tred R. Eyerly, Insurance Law Hawaii
The Illinois Court of Appeals determined the insurer must defend allegations of property damage arising from faulty workmanship. Milwaukee Mut. Ins. Co. v. J.P. Larsen, Inc., 2011 Ill. App. Unpub. LEXIS 1443 (Ill. Ct. App. June, 20, 2011).
Larsen was a subcontractor for Weather-Tite in a condominium building. Weather-Tite installed windows on the project and hired Larsen to apply sealant to the windows. The windows subsequently leaked and caused water damage within the complex.
The homeowner’s association sued Weather-Tite for breach of express and implied warranties. Weather-Tite filed a third-party complaint against Larsen, seeking contribution and alleging that Larsen was in breach of contract by failing to add Weather-Tite as an additional insured under Larsen’s CGL policy.
Both Weather-Tite and Larsen tendered to Larsen’s insurer. Both tenders were denied because the insurer contended the complaints alleged only construction defects, and not “property damage” or an “occurrence” within the terms of the policy.
The insurer filed suit for a declaratory judgment. The trial court granted the insurer’s motion as to Weather-Tite, but granted Larsen’s cross-motion for summary judgment.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Connecticut Gets Medieval All Over Construction Defects
February 10, 2012 — CDJ Staff
The Hartford Courant reports that Connecticut is trying a very old tactic in a construction defect suit. The law library building at the University of Connecticut suffered from leaks which have now been repaired. The state waited twelve years after was complete to file lawsuit, despite that Connecticut has a six-year statute of limitations on construction defect claims. Connecticut claims that the statute of limitations does apply to the state.
The state is arguing that a legal principle from the thirteenth century allows it to go along with its suit. As befits a medieval part of common law, the principle is called “nullum tempus occurrit regi,” or “time does not run against the king.” In 1874, the American Law Register said that nullum tempus occurrit reipublicae “has been adopted in every one of the United States” and “is now firmly established law.”
In the case of Connecticut, Connecticut Solicitor General Gregory D’Auria said that “the statute of limitations does not apply to the state.” He also noted that “the state did not ‘wait’ to file the lawsuit. The lawsuit was filed only after all other options and remedies were exhausted.”
Connecticut also argued that “nullus tempus occurrit regi” applied in another construction defect case at the York Correctional Institution. The judge in that case ruled in December 2008 to let the case proceed. But in the library case, Judge William T. Cremins ruled in February 2009 that the statute of limitations should apply to the state as well. Both cases have been appealed, with the library case moving more quickly toward the Connecticut Supreme Court.
Read the full story…
Fifth Circuit Asks Texas Supreme Court to Clarify Construction Defect Decision
November 7, 2012 — CDJ Staff
The Fifth Circuit Court has withdrawn its decision in Ewing Construction Company v. Amerisure Insurance Company, pending clarification from the Texas Supreme Court of its decision in Gilbert Texas Construction, L.P. v. Underwriters at Lloyd’s London. The Fifth Circuit had applied the Gilbert case in determining that a contractual liability exclusion barred coverage for faulty workmanship. The Insurance Journal reports that this decision was both applauded and criticized, with a concern noted that “an insurer would now have its pick of either the ‘your work’ exclusion or the contractual liability exclusion without the exception for subcontracted work.”
The Fifth Circuit is now asking the Texas Supreme Court two questions to clarify Gilbert, which Brian S. Martin and Suzanne M. Patrick see as a sign that the Court has realized that it overly expanded the scope of the earlier ruling. A response is expected from the Texas Supreme Court by spring 2013.
Read the full story…
Who Is To Blame For Defective — And Still LEED Certified — Courthouse Square?
September 1, 2011 — Douglas Reiser, Builders Counsel
Remember Courthouse Square? I sure do. We have talked about the closed and evacuated LEED certified building a couple of times here on Builders Counsel. Well, it’s back in the news. This time building professionals are pointing fingers — but there is some talk about a fix. Still, its LEED certification remains.
If you read my past articles about Courthouse Square, you can get caught up on this mess. The short of it is that Salem, Oregon had the five-story government building and bus mall completed in 2000 for $34 Million. It was awarded LEED certification during the USGBC’s infancy. Last year, it became public that the building had significantly defective concrete and design. The Salem-Keizer Transit District worked with the City of Salem to shut the building down, and it has not been occupied since.
Last fall, Courthouse Square failed thorough forensic testing leading to a lengthy bout with a number of insurers. The contractors and designers had been hauled into court, but the Transit District was able to settle with the architect and contractors. The only remaining party involved in the lawsuit appears to be the engineering firm, Century West Engineering. Most expert reports have pinned the responsibility for the poor design and materials on Century West’s shoulders.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Policyholder Fails to Build Adequate Record to Support Bad Faith Claim
May 19, 2011 — May 19, 2011 -
Tred R. Eyerly,
Insurance Law HawaiiThe importance of careful preparation and documentation was the take away lesson in a Texas bad faith case, C.K. Lee v. Catlin Specialty Ins. Co., 2011 U.S. Dist. LEXIS 19145 (S.D. Tex. Feb. 28, 2011).
C.K. Lee owned a commercial shopping center in Houston. Catlin issued a commercial property policy to Lee. On September 12, 2008, Hurricane Ike hit and caused substantial property damage throughout the Texas Gulf Coast area. On September 24, 2008, Lee submitted a claim for damage to the roof of his shopping center to Catlin.
Catlin hired Engle Martin to represent its interests in adjusting the claim. Engle Martin eventually adjusted over 200 Ike-related claims for Catlin.
In November 2008, Engle Martin and Emergency Services Inc., retained by Lee, inspected Lee’s property. Engle Martin observed evidence of roof repairs that had apparently been made both before and after Hurricane Ike. Engle Martin decided it was necessary to use an infrared scan of the roof to help identify which damages, if any, were attributable to wind and which, if any, were attributable to sub par, prior repairs or natural deterioration.
Engle Martin retained Project, Time & Cost (PT&C) to conduct the infrared inspection. PT&C’s inspection determined there was no wind-related damage to the roof and no breaches or openings created by wind. Instead, the roof had exceeded its life expectancy and was in need of replacement due to normal wear and weathering. Consequently, Catlin decided that the damage to Lee’s roof was not caused by winds from Hurricane Ike.
Meanwhile, Lee’s contractor, Emergency Services, prepared a report estimating that the total cost of repairing the roof would be $871,187. Engle Martin’s estimate for repair of the roof was $22,864.
Lee filed suit for breach of contract, breach of the duty of good faith and fair dealing, and violations of the Texas Insurance Code. Catlin moved for summary judgment on all claims but breach of contract, arguing that because there was a bona fide dispute concerning the cause of the damages and whether they were covered under the policy, there was no evidence of bad faith or violations of the Texas Insurance Code.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
SB800 Cases Approach the Courts
July 10, 2012 — CDJ Staff
California’s Right to Repair Law turns ten this year and cases under the statute are finally coming to trial, as John V. O’Meara of Bremer Whyte Brown & O’Meara writes for the Martindale-Hubble Legal Library. Mr. O’Meara notes that SB800 eliminated “the traditional definitions of construction defect,” replacing them with “functionality standards.” He argues that these standards are not uniform: “some standards require damage and others do not.” He also wonders what terms like “significant cracks,” “intended water” and “materially comply” mean in a court.
Mr. O’Meara states that “defendants in construction defect cases have a right to know the standards that apply to a case, the definitions that will be presented to the jury, and the burden of proof that attaches.”
Read the full story…
Williams v. Athletic Field: Hugely Important Lien Case Argued Before Supreme Court
June 17, 2011 — Douglas Reiser, Builders Counsel
Well, it finally made it. The most important Washington lien case of recent memory was argued in front of the Washington Supreme Court on Tuesday, June 14, 2011. So, what should we all expect?
As I was reading through my RSS feeds this afternoon ? I was stopped dead in my tracks. Williams v . Athletic Field, the Division II case that has been a frequent topic here on Builders Counsel, has finally been argued before the Supreme Court. All of you who have been anxiously awaiting this day, you can check out the Supreme Court submissions by following this link.
The Williams case has been the center of attention for construction lawyers and construction organizations over the past year. Some have called for complete lien law reform, others have tried to patch a hole in the law. Now, we can expect a ruling from the highest court in the state. That ruling will have a major impact on whether the Legislature feels compelled to change lien law.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Mandatory Arbitration Provision Upheld in Construction Defect Case
May 18, 2011 — May 18, 2011 Beverley BevenFlorez - Construction Defect Journal
The Superior Court of New Jersey reversed the decision in Frumer v. National Home Insurance Company (NHIC) and the Home Buyers Warranty Corporation (HBW), stating that the mandatory arbitration provision within the Frumer’s home warranty policy was binding.
The Frumers alleged that the construction defects were discovered immediately after moving into their million dollar home. After failing to achieve any results from dealing with the builder, they turned to their home warranty. There was some dispute over claims, and a settlement offer was rejected by the Frumers. The Frumers elected to commence litigation rather than utilize the binding arbitration.
The NHIC and the HBW filed a motion to compel arbitration, however, the motion judge denied the motion: “…the Warranty leaves open the option for [plaintiffs] to commence litigation, which [plaintiffs have] done in this case. The clause also states that ‘the filing of a claim against this limited Warranty shall constitute the election of remedy and shall bar the Homeowner from all other remedies.’ However, the provision does not state that the filing of a claim elects arbitration as the exclusive remedy, and any ambiguity in the language must be inferred against the drafter.”
The NHIC and the HBW appealed the decision. The Superior Court reversed the decision: “Where, such as here, the homeowner files a claim against the warranty for workmanship/systems defects, the warranty clearly and unequivocally establishes binding arbitration as the exclusive remedy. There is, however, no election of remedies for a dispute involving a major structural defect claim. The warranty clearly and unequivocally establishes binding arbitration as the exclusive remedy.”
Charles Curley of Halberstadt Curley in Conshohocken, Pa., the local counsel for National Home and Home Buyers, told the New Jersey Law Journal that “the ruling reaffirms New Jersey’s commitment to enforcing arbitration agreements and requiring people to go to mandatory arbitration when the contracts call for it.”
“At this point, their hope is that the warranty company will do what it's supposed to do — repair covered defects,” Eric McCullough, the Frumer’s lawyer said to the New Jersey Law Journal.
Read the full story…
Homeowners May Not Need to Pay Lien on Defective Log Cabin
July 1, 2011 — CDJ Staff
The Idaho Supreme Court has ruled in the case of Perception Construction Management v. Bell. The Bells hired PCM to build a log home, agreeing to play monthly invoices in full within ten days. The Bells paid the first four invoices in full, part of the fifth, and ceased payment after that. Beofre seventh invoice, the Bells terminated the contract and hired a new contractor. PCM filed a claim of lien and ceased work.
The Bells responded that PCM was in breach of contract and had failed to fulfill the contract in a workmanlike manner. They claimed construction defects and in the lien suit, sought to include testimony from an architect and a plumber reviewing PCM’s work. The court only allowed the architect to testify as to whether the amount of the lien was reasonable. No testimony was permitted from the plumber.
The Idaho Supreme Court concluded that the claims of construction defects were important to case and remanded it to the lower court for a new trial taking into evidence that Bell’s contention that PCM’s work was defective.
Read the court’s decision
Water Damage Covered Under Efficient Proximate Cause Doctrine
August 2, 2012 — Tred Eyerly, Insurance Law Hawaii
A U.S. District Court in Washington found coverage in what it described as a text book study of the efficient proximate cause rule. Hiller v. Allstate Pro. & Cas. Ins. Co., 2012 U.S. Dist. LEXIS 84862 (E.D. Wash. June 19, 2012).
The Hillers purchased a newly constructed home in December 2006. They also purchased an all-risk homeowner's policy from Allstate.
In July 2010, the Hillers discovered that the carpet in the basement of the residence was saturated with water. Allstate was immediately notified. Hiller began an investigation to attempt to determine the source of the water. He poured water into a downspout drain at the northwest corner of the residence. This caused water to leak into the northwest corner of the home's basement.
An area was excavated around the northwest downspout drain. The end of the drain pipe was partially blocked by rocks and had been wrapped with fabric landscaping material. Further, a “T” pipe installed at the foot of the drain was directing water toward the house's concrete foundation. Hiller notified Allstate that the problems with the drain was due to construction defects and the system was designed to fail.
Allstate denied the claim. Based upon Hiller's information, coverage was excluded under the policy's surface water, subsurface water, inherent vice, and latent defect exclusions.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Appeals Court Upholds Decision by Referee in Trial Court for Antagan v Shea Homes
May 10, 2012 — CDJ Staff
In the case Antangan v. Shea Homes Ltd. Partnership (Cal. App., 2012), Plaintiffs appealed “an order vacating a judgment and entering a modified judgment in their construction defect action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership,” while the Defendant, Shea Homes Limited Partnership (Shea Homes) appealed “an order of the judicial referee denying its motion to strike and tax costs.”
On the Antagon issue, the appeals court concluded that “the trial court did not err by vacating and modifying its judgment so that the cost of referee’s fees would be equally divided by the parties and consistent with a prior stipulation they filed in court.”
On the Shea Homes issue, the appeals court concluded: “1) the judicial referee did not err by ruling that plaintiffs’ offers to compromise (§ 998) were validly served on Shea Homes’ counsel, 2) the offers substantially complied with statutory requirements, 3) the offers were not required to be apportioned, and 4) the referee’s award of $5,000 as costs for a person assisting plaintiffs’ counsel was not an abuse of discretion.” The appeals court affirmed the judgment.
Here is a brief history of the trial case: “Plaintiffs Chito Antangan, Jimmy Alcova and other homeowners brought an action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership for damages alleging that the properties they purchased from these ‘developer defendants’ were defective. Plaintiffs claimed numerous construction defects required them ‘to incur expenses’ for ‘restoration and repairs’ and the value of their homes had been diminished.”
In response, Shea Homes filed a motion for an order to appoint a judicial referee. The motion was granted and it was ruled that “a referee would ‘try all issues’ and ‘report a statement of decision to this court.’”
On May 10, 2010 the judicial referee (Thompson) “awarded plaintiffs damages and various costs, and ruled that ‘Shea Homes shall bear all of the Referee’s fees.’” The latter ruling would become a matter for contention later on.
In July of 2010, the plaintiffs “sought, among other things, $54,409.90 for expert fees, and $14,812.50 for the services of Melissa Fox for ‘exhibit preparation & trial presentation.’ Shea Homes filed a motion to strike and/or tax costs claiming: 1) Fox was a paralegal, 2) plaintiffs were not entitled to attorney’s fees, and 3) the fees for Fox’s services were an indirect and improper method to obtain attorney’s fees. The referee disagreed and awarded $5,000 for Fox’s services. The referee also ruled that plaintiffs had properly served valid offers to compromise (§ 998) on Shea Homes’ counsel in 2009. He said those offers to defendants in the case at that time did not have to be apportioned.”
“Antangan contends the trial court erred when it vacated and modified its original judgment, which ordered Shea Homes to pay all the referee’s fees. We disagree.”
Antagon contended that the trial court erred when it vacated and modified its original judgment regarding Shea Homes paying the referee’s fees. The appeals court disagreed: “A trial court has inherent authority to vacate or correct a judgment that is void on its face, incorrect, or entered by mistake. (§ 473; Rochin v. Pat Johnson Manufacturing Co. (1998),67 Cal.App.4th 1228; Olivera
Read the court’s decision…
Contractor Convicted of Additional Fraud
November 18, 2011 — CDJ Staff
A Pennsylvania contractor in prison for fraud has been convicted with insurance fraud. The York Daily Record reports that Steven D. Gebhart was already in jail for fraud for about $350,000 for work he either failed to finish or even start or by using substandard materials and practices when he was convicted of insurance fraud. Gebbert’s offices were destroyed in a fire that was later determined to be arson. He was not charged with this, but instead for overestimating his losses to the insurance company. Sentencing for the fraud charge will be on December 21.
Read the full story…
Another Colorado District Court Refuses to Apply HB 10-1394 Retroactively
October 28, 2011 — David M. McLain, Colorado Construction Litigation
In Martinez v. Mike Wells Construction Company, 09CV227, Teller County District Court Judge Edward S. Colt refused to apply C.R.S. § 13-20-808 retroactively to provide coverage for the underlying construction defect allegations. According to the recitation of facts in Judge Colt’s March 2011 order, Martinez contracted with Mike Wells Construction to serve as the general contractor for the construction of a home. At that time, Mike Wells Construction was insured through ProBuilders Specialty Insurance Company, RRG. Disputes arose between Martinez and Mike Wells Construction, resulting in Martinez ordering it off of the project in mid-November 2007 and terminating its right to work there by letter dated November 28, 2007.
Mike Wells, the owner of the corporation, subsequently died. Martinez sued Mike Wells Construction in July 2009 for breach of contract and various claims relating to alleged defecting workmanship. Martinez provided notice of the suit to the special administrator of the probate estate. No answer having been filed, the court entered a default judgment against Mike Wells Construction and Martinez sought to garnish Mike Wells Construction’s ProBuilders insurance policy.
Read the full story...
Reprinted courtesy of Higgins, Hopkins, McLain & Roswell, LLC. Mr. McClain can be contacted at mclain@hhmrlaw.com
Instant Hotel Tower, But Is It Safe?
March 28, 2012 — CDJ Staff
Broad Sustainable Building has leapfrogged in China’s construction boom by building a thirty-story hotel in just fifteen days in the city of Changsha. According to an article in the Los Angeles Times, most of the building was prefabricated, but most prefabricated buildings require a longer time for assembly. Broad claimed that it cut no corners on safety. However, Zhang Li, a Beijing architect, told the Times that “incredible speed also means incredible risk.”
At the completion date, the interior was still partially finished. Some rooms were furnished, while others weren’t quite so ready. The hotel will be used to house clients who are visiting Broad and some of its employees.
Broad called their process “the most profound innovation in human history” and predicted that soon a third of new buildings worldwide would be constructed this way. The company anticipates using the same process to build taller buildings, with hopes of eventually constructing a 150-story building.
China is currently undergoing a building boom which Zhang attributed to a desire to catch up to the developed world. As a result of this boom, he noted that building inspections are often skipped in China to speed up building.
Read the full story…
Harmon Towers Duty to Defend Question Must Wait, Says Court
March 1, 2012 — CDJ Staff
The Harmon Towers project in Las Vegas was eventually halted short of the planned forty-seven stories after “it was determined that there was substantial defective construction, including defective installation of reinforcing steel throughout the Harmon.” The American Home Insurance Company and Lexington Insurance Company put forth a claim that they had no duty to defend Perini Construction, the builder of the defective Harmon Towers. Further, American Home seeks to recover the monies American reimbursed Perini. The United States District Court of Nevada ruled in the case of American Home Assurance Co. v. Perini Building on February 3, 2012.
The two insurance companies covered Perini and its subcontractors, Century Steel, Pacific Coast Steel, and Ceco Concrete Construction. Century Steel was the initial subcontractor for the reinforcing steel; they were later acquired by Pacific Coast Steel. In this current case, Perini Construction is the sole defendant.
Perini sought a dismissal of these claims, arguing that without the subcontractors joined to the case, “the Court cannot afford complete relief among existing parties.” The court rejected this claim, noting that the court can determine the duties of the insurance companies to Perini, which the court described as “separate and distinct from those of the subcontractors.” The subcontractors “have not claimed an interest in the subject matter of the action.” The court concluded that it could determine whether Perini was entitled or not to coverage without affecting the subcontractors. The court rejected Perini’s claim.
Perini also asked the court to abstain from the case, arguing that it was better heard in a state court. The court noted that several considerations cover whether a case is heard in state or federal courts. The court noted that if the case weighed heavily on state law, the state courts would be the obvious location. Further, if there were a parallel action in the state courts, “there is a presumption that the whole suit should be heard in state courts.” This is, however, no parallel state suit, although the court noted that Perini has “threatened” to do so.
However, the issue of who is to blame for the problems at Harmon Towers has not been resolved. The court concluded that until the “underlying action” was concluded, it was premature to consider the issues raised in this case while the earlier lawsuit was still in progress. The court denied Perini’s motion to dismiss the case. Given that the outcome of the earlier construction defect case may lead to further litigation in state court, the District Court granted Perini’s motion to abstain, but staying their judgment until the construction defect case is resolved.
Read the court’s decision…
Joinder vs. Misjoinder in Colorado Construction Claims: Roche Constructors v. One Beacon
July 10, 2012 — David McLain, Higgins, Hopkins, McLain & Roswell, LLC
Often, those practicing in the construction defect field have faced questions concerning the joinder of a party. Recently, the U.S. District Court for the District of Colorado weighed in on the requirements for joinder under the Colorado Rules of Civil Procedure. See Roche Constructors, Inc. v. One Beacon America Ins. Co., 2012 WL 1060000 (D. Colo. 2012). Roche secured a construction contract to build a detention facility for the Lincoln County Sheriff’s Office in Lincoln County, Nebraska. In turn, Roche entered into a subcontract with Dobberstein Roofing Company, Inc. in October 2009 to install the roofing system and other related work at the detention facility. The subcontract agreement required Dobberstein to maintain adequate commercial general liability insurance and to add Roche as an additional insured under the policy. Roche maintained a builder’s risk policy issued by OneBeacon America Insurance Company and Dobberstein secured a certificate of liability insurance underwritten by Transportation Insurance Company (“TIC”). Id. at *1.
Roche alleged that Dobberstein constructed the roofing system in a negligent manner in violation of the subcontract. Roche claims it incurred additional costs to repair structural damage to the roofing system as a result of Dobberstein’s negligent work. In order to cover said damage, Roche tendered insurance claims to OneBeacon and TIC.
Read the full story…
Reprinted courtesy of David McLain, Higgins, Hopkins, McLain & Roswell, LLC. Mr. McLain can be contacted at mclain@hhmrlaw.com
Contractor Manslaughter? Safety Shortcuts Are Not Worth It
August 11, 2011 — Douglas Reiser, Builders Counsel
It’s been a while since I discussed the importance of safety. But, a recent article on ENR.com compelled this brief article. Don’t shortcut safety — you could be facing serious criminal repercussions.
A New York crane company owner and one of his employees are each facing a second-degree manslaughter charge for the death of two construction workers.  The charges stem from the collapse of a crane in New York City. The district attorney determined that the crane owner cut a few corners to reduce its operation costs, significantly sacrificing safety.
Another example was the 2010 trial of another New York crane operator who was charged with manslaughter. In that case, the criminal charges failed to stick, but an administrative judge found that the contractor used a damaged sling to support the steel collar binding the tower-crane mast to the 18th floor of a high-rise building being constructed. The company also used four slings instead of the eight, as specified by the crane manufacturer; improperly attached the slings and failed to pad or soften them.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
“Other Insurance” and Indemnity Provisions Determine Which Insurer Must Cover
September 1, 2011 — Tred Eyerley, Insurance Law Hawaii
A policy’s “other insurance” clause and a contractual indemnity provision were at the root for determining which of two insurers had to cover for injuries at a construction site. Valley Forge Ins. Co. v. Zurich Am. Ins. Co., 2011 U.S.Dist. LEXIS 76061 (N.D. Calif. July 14, 2011).
Hathaway was the general contractor at a demolition and construction project. Hathaway was insured by Zurich. Reinhardt Roofing was the roofing subcontractor. Reinhardt was insured by Valley Forge under a policy which named Hathaway as an additional insured. The subcontract also required Reinhardt to indemnify Hathaway for acts or omissions arising from Reinhardt’s work unless Hathaway was solely negligent.
Four of Reinhardt’s workers were injured when a canopy roof on which they were working collapsed. At the time of the accident, Hathaway’s on-site supervisor was inspecting a gap in the canopy roof, but did not order Reinhardt’s workers to stop working.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com