Association May Not Make Claim Against Builder in Vermont Construction Defect Case
October 23, 2012 — CDJ Staff
The Vermont Supreme Court issued a ruling on September 28 on Long Trail House Condominium Association. The case was heard by a panel of two Supreme Court justices, Marilyn Skoglund and Brian Burgess, and three justices specially assigned for the case, Kupersmith, Davenport, and Johnson. The decision came down with a 3-2 split; Judges Kupersmith and Johnson joining in a dissent.
In the underlying case, Stratton Corporation entered into an agreement with Engelberth Construction in which Engelberth would supply “recommendations on construction feasibility, consultation as to the selection of materials and equipment, assistance with zoning requirements and permits, and cooperation with the ‘design team’ to provide valuable engineering services.” Engelberth was not responsible to determine that the drawings and specifications were in accordance with the law and building codes, nor were they responsible “for the design team’s designs, errors, or omissions.”
Subsequent to the agreement was a construction project which culminated in the incorporation of the Long Trail House Condominium Association. The condominium owners initiated a lawsuit over alleged defects. Stratton, Intrawest, and the association settled claims for $7,025,00 with Stratton and Intrawest both pursuing claims against Engelberth. This case is still unsettled.
The association progressed on remediation, which cost about $1,500,00 more than was provided by the settlement, and so the association also sued Engelberth. In this case, the court granted a summary judgment to Engelberth, concluding that negligence claim was barred both “by the economic loss rule and that the absence of contractual privity was fatal to the warranty claims.”
The court upheld both determinations of the lower court. The court noted that “the economic loss rule ‘prohibits recovery in tort for purely economic losses’” and that “in tort law, duties are imposed by law to protect the public from harm.” A negligence claim could only be supported with evidence of “some accompanying physical harm, which does not include economic loss.”
The association made the claim that the economic loss rule applies only when there is a contractual relationship between the two parties. The court rejected this argument, citing a reference that “economic interests are protected, if at all, by contract principles, rather than tort principles.”
Nor did the court find it persuasive that a “professional services” exception to the economic loss doctrine applied, noting that the court has rejected this notion in two prior cases. The noted that the association’s losses were purely economic, and their inability to settle those claims with Engelberth did not mean that they had not means of settling them, as they were able to settle these very claims with Stratton and Intrawest.
The association also raised claims of an implied warranty, resting on the construction contract between Engelberth and Stratton. This was also rejected by the court, noting that Vermont “case law plainly contemplates the existence of contractual privity before a breach of implied warranty claim can be raised.” The court noted that there was neither a contract nor a sale between Engelberth and the association, and thus there were no grounds for an implied warranty. The court concluded that “the Association’s warranty remedy lies against the entity that sold it the condominium units and implicitly warranted through the sale that the units were built in a good and workmanlike manner and that they were suitable for habitation.”
Read the court’s decision …
Arizona Supreme Court Confirms Eight-Year Limit on Construction Defect Lawsuits
July 18, 2011 — CDJ Staff
Acting on the case of Albano v. Shea Homes Ltd. Partnership, the Arizona Supreme Court has ruled that Arizona’s eight-year statute of repose applies. The case was referred to the court by the Ninth Circuit Court of Appeals which had asked for a clarification of Arizona law. The case focused on three questions:
1. Does the filing of a motion for class certification in an Arizona court toll the statute of limitations for individuals, who are included within the class, to file individual causes of action involving the same defendants and the same subject matter?2. If so, does this class-action tolling doctrine apply to statutes of repose, and more specifically, to the statute of repose for construction defects set forth in Arizona Revised Statutes ("A.R.S.") § 12-552?3. If the doctrine applies to statutes of repose, and specifically § 12-552, may a court weigh the equities of the case in determining whether, and to what extent, an action is tolled?
The litigation at hand has a lengthy history, starting with a case referred to as “Hoffman” in 2003. The Albano plaintiffs were not able to join in Hoffman, and they filed their own lawsuit in 2006. An additional lawsuit was filed by the Albano plaintiffs in 2007. The courts decided that the Albano plaintiffs’ lawsuit was untimely.
The Arizona Supreme Court concluded that the statute of repose was the appropriate standard for this case. They noted that “the eight-year statute of repose period began to run on November 6, 1997, the date of the Town of Gilbert’s final inspection. Albano II was filed on November 5, 2007.”
The court found that the plaintiffs had waited too long for start their suit. As a result, they found it unnecessary to answer the first or third questions. Justice A. John Pelander of the Arizona Supreme Court wrote the opinion, dated June 30, 2011.
Read the court’s decision…
Court finds subcontractor responsible for defending claim
May 18, 2011 — May 18, 2011 - CDJ Staff
In an unpublished decision, the California Fourth Appellate District Court has reversed the judgment of Judge Linda B. Quinn of the Superior Court of San Diego. In the case Inland California, Inc. v. G.A. Abell, Inland, a general contractor had subcontracted with Apache Construction and Precision Electric Company (G.A. Abell).
Apache alleged that extra demolition and drywall work was needed due to Precision’s electrical work. Inland tendered a defense of Apache’s claims. However, Precision did not provide any defense. Inland withheld payment from Precision.
At trial, Inland “conceded Precision earned the $98,000 in progress payments Inland withheld.†They were obligated to additionally pay Precision’s costs and attorney fees.
The Fourth Appellate District court has overturned this and remanded the case back to the lower court. The judges determined that Precision was obligated to defend itself against the claims raised by Apache and therefore vacated the judgment against Inland.
Read the court’s decision…
Can Negligent Contractors Shift Blame in South Carolina?
July 10, 2012 — CDJ Staff
Clay Olson looks back to a 1991 Carolina case, Nelson v. Concrete Supply Company. The court concluded in that case that “a plaintiff in South Carolina may recover only if his/her negligence does not exceed that of the defendant’s and amount of plaintiff’s recovery shall be reduced in proportion to amount of his or her negligence; if there is more than one defendant, plaintiff’s negligence shall be compared to combined negligence of all defendants.” In 2005, he reports, as part of tort reform in South Carolina, the legislature further addressed this.
He then suggests a possible outcome of this is that negligent contractors may be able to shift some of the blame (and cost of the settlement) to other defendants who may not be to blame. He offers a scenario in which a contractor is sued for construction defects and a jury has to allocate responsibility for indivisible damage. “A jury need only find the two subcontractors to have each contributed 15% of the indivisible damage.” He adds in another 15% for claims against the architect. Minor blame is given to the manufacturers, and suddenly the negligent contractor is paying less than 50% of the total settlement.
He notes that the previous system in place also had its problems, but notes that this one may not be “fair and equitable.”
Read the full story…
Allowing The Use Of a General Verdict Form in a Construction Defect Case Could Subject Your Client to Prejudgment Interest
August 16, 2012 — Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC
A recent opinion from the Colorado Court of Appeals is a cautionary tale concerning the calculation of pre-judgment interest. See Hendricks v. Allied Waste Transportation, Inc., 2012 WL 1881004 (Colo. App. 2012). The Hendricks sued Allied after one of its drivers backed into the corner of their home with an Allied garbage truck. At trial, a jury awarded the Hendricks $160,100 in damages. Although the jury was instructed on the cost of repairs, diminution in value, and non-economic damages, the parties agreed to a general verdict form that did not ask the jury to specify the types of damages awarded. Id. at *1. The Hendricks sought to amend the judgment to include prejudgment interest and costs, which the trial court granted.
Allied appealed, arguing that the trial court erred by awarding the Hendricks prejudgment interest from the date their property was damaged. Id. at *7. The Colorado Court of Appeals found no error, and affirmed.
Read the full story…5
Reprinted courtesy of Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC. Ms. Anderson can be contacted at anderson@hhmrlaw.com
Australian Developer Denies Building Problems Due to Construction Defects
June 15, 2011 — CDJ Staff
The Sunland Group, the developer, is objecting to claims that it is responsible for corrosion damage in a residential building in Gold Coast, Australia, as reported in the Courier & Mail. Residents of Q1, the world’s tallest residential tower, are suing the developer, claiming that defects and corrosion “compromise the long-term durability and appearance of” the six-year-old building.
The developer has not only denied that there are defects in the building, but has also stated that the construction contract “did not warrant that the construction would be defects-free.” Sunland claimed that corrosion was due to the homeowners association having “failed to carry out the maintenance requirements.”
Repair of the building is expected to cost millions of dollars. Sunland denies that it should pay any of that.
Read the full story…
Micropiles for bad soil: a Tarheel victory
March 14, 2011 — Original article by by Melissa Brumback on March 14, 2011
Despite foundation challenges, construction is almost complete on the expansion at University of North Carolina’s Kenan stadium. The project started with a deep foundation system from design-build contractor GeoStructures. Known as the Carolina Student-Athlete Center for Excellence, the addition was built on a parcel with a knotty mix of fill soils, subsurface boulders and varying depths to rock. To achieve uniform foundation support, GeoStructures designed a Micropile system (also known as a Mini pile system) which could be drilled into the variable ground conditions.
Read the full story...
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl law.com.
Parking Garage Collapse May Be Due to Construction Defect
November 7, 2012 — CDJ Staff
A parking garage under construction at the Doral campus of Miami Dade College collapsed on October 9. Experts state that the collapse may have been due to errors in the construction process, either in the fabrication of the pre-cast components or in their assembly. The Bradenton Herald quotes Mark Santos, a structural engineer, who “would look at erection procedures ?Äì that’s probably the one question to ask first.”
During the failure, floors separated from the south wall of the structure. The contractor responsible for the garage, Ajax Building Corp, said there was “no indication of any potential cause.”
Read the full story…
Construction Suit Ends with Just an Apology
February 10, 2012 — CDJ Staff
After suing a contractor for failing to complete the remodeling of their home, an Orange County couple has settled for an apology. Douglas J. Pettibone represented the contractor, who had lost his business after a broken neck, multiple surgeries, and an addiction to pain medicine. Mr. Pettibone represented his client pro bone. The case was settled in arbitration by JAMS.
Mr. Pettibone noted that his client gave “a heartfelt and very moving apology.” The remodeling was completed by another contractor, two years after Thorp Construction stopped work on the project. After the apology, the case was dismissed.
Read the full story…
Southern California Lost $8 Billion in Construction Wages
August 17, 2011 — CDJ Staff
Los Angeles and Orange Counties are first on a list no area wants to be on. According to the Sacramento Bee, reporting on data from the U.S. Bureau of Economic Analysis, LA and Orange Counties saw an $8 billion drop in construction wages in 2010, as compared to 2006. In 2006, the region saw payrolls of $26.8 billion, but in 2010, that was reduced to $18.5 billion.
This was not the largest percentage change. Of the metropolitan areas with the largest declines in construction earnings, Las Vegas saw a $3.6 billion drop, however that represented half of their 2006 totals of $7.2 billion. Conversely, a $3.3 billion drop in the New York area represented only 10% of what had been $33.8 billion in payroll in 2006.
Read the full story…
Insurance Firm Defends against $22 Million Claim
June 15, 2011 — CDJ Staff
The Houston law firm of Eggleston & Briscoe successfully defended their client, Colony Insurance Company, which was being sued for $22 million over roof hail damage. The Summer Hill Village Community Association did not convince a jury that the insurance company had violated state law or breached its contract when it denied coverage for the roofs. The homeowners association contended that the roof damage was due to a hail storm in 2007. The jury agreed with experts who contended the damage was already present at that time.
Mr. Eggleston noted that “when your client is sued for a claim of $22 million, it is very satisfying to hear a jury agree that they in fact acted honorably and owed nothing.”
Read the full story…
MGM Seeks to Demolish Harmon Towers
September 1, 2011 — CJD Staff
Citing public safety concerns and the cost of repair, MGM Resorts International is seeking to demolish the unfinished hotel tower. The company has a few hurdles to go through before they start laying the charges to implode the structure. Any plans would have to be approved by not only Clark County officials, but also the district court has an order blocking any activity during litigation between MGM and the general contractor on the project, Perini Building Company.
Architectural Record reports that MGM states it would take “approximately 18 months to conduct test and come up with an approved, permitted design to fix the Harmon.” MGM feels that repairs would then take another two to three years. Perini contends that they could “provide stamped drawings detailing all necessary repairs within three months.” They attribute MGM’s desire to demolish the building as “buyer’s remorse.”
Read the full story…
When is a Construction Project truly “Complete”? That depends. (law note)
August 2, 2012 — Melissa Dewey Brumback, Construction Law North Carolina
Long-time readers of the blog may remember my earlier post on substantial completion. However, in looking over my blog stats to see what search terms lead people here, it looks like this is hot topic. The blog searches came in two general categories:
1. Those searching strictly for a definition of substantial completion. Some examples:
- What does “substantial completion” mean?
- when does a building achieve substantial completion
- contracts “substantial completion”
- substantial completion undefined
- when is a project substantially complete
Read the full story…
Reprinted courtesy of Melissa Dewey Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
Local Government Waives Construction Fees to Spur Jobs
June 19, 2012 — CDJ Staff
Warren Township in New Jersey has waived building and electrical permit fees, up to $5,000, for businesses that create at least five new jobs. The fee reductions are available for construction in areas zones under various designations. Buildings that have received a zoning variance are not eligible. The Echoes-Sentinel notes that other towns in Somerset County, New Jersey have adopted similar ordinances.
Read the full story…
Construction Worker Dies after Building Collapse
November 18, 2011 — CDJ Staff
A Bronx construction worker died when the pillars gave way in the basement where he was working. The two-story commercial building collapsed, burying Mr. Kebbeh under about six feet of rubble. The New York Times reports that firefighters dug him out with their bare hands. Mr. Kebbeh was taken to Jacobi Medical Center where he died. Two other construction workers escaped unharmed.
Read the full story…
Defective Drains Covered Despite Water Intrusion Exclusion
July 10, 2012 — CDJ Staff
The US District Court in Washington State has granted a summary judgment in Hiller v. Allstate Prop. & Cas. Ins. Co. The Hillers bought a new home in Wenatchee, Washington and insured it with an “all risk” policy from Allstate. Subsequently, Mr. Hiller discovered that the carpet in the basement was saturated with water. Hiller notified Allstate who requested that he determine the source of the water intrusion. Hiller poured water into a downspout drain and found this caused water to leak into the home’s basement.
Further investigation with the homes original excavation contractor revealed that “the end of the drain pipe was partially blocked by rocks and had been wrapped with fabric landscaping material.” Additionally, “a ‘T’ pipe installed at the foot of the drain was directing water toward the house’s concrete foundation.” Allstate denied the claim “under the policy’s surface water, subsurface water, inherent vice, and latent defect exlusions.” After the denial, Hiller “discovered that the foundation had not been treated with waterproof sealant and that several concrete form pins were still in place.”
The court noted that “there is no genuine dispute about the cause of the claimed loss.” This left the court concluding that “the only relevant question for the purposes of the instant cross-motions for summary judgment is whether a loss caused by defective construction is covered under the Hillers’ ‘all risk’ insurance policy.” Under Washington’s “efficient proximate cause” rule, “where an insured risk itself sets into operation a chain of causation in which the last step may have en an excepted risk, the excepted risk will not defeat recovery.” The court found that a loss caused by defective construction is in fact covered under the policy, noting that “the policy does not contain an exclusion for defective construction.”
The court concluded that the defective drain was not an inherent vice, as it “cannot properly be characterized as defects ‘inherent [in the] nature of the commodity which will cause it to deteriorate with a lapse of time.” Nor was it a latent defect, “one that could not have been discovered by inspection.” The court concluded that “both of the construction defects at issue could have been discovered by a reasonable inspection.”
With these facts determined, the court found for the Hillers.
Read the court»s decision…
Important Information Regarding Colorado Mechanic’s Lien Rights.
November 7, 2012 — David McLain, Colorado Construction Litigation
With payment problems in the construction economy having accelerated over the past few years, there has been a substantial increase in mechanic’s lien activity and associated litigation. The typical mechanic’s lien claimant is a material supplier, a trade subcontractor, or even a general contractor that has not been paid by the developer/owner of the construction project. The reason for filing a mechanic’s lien claim is that it offers the prospect in many cases to make the unpaid construction professional a priority creditor, with a lien on the real estate that is superior to the construction lender.
One of the primary rules governing a mechanic’s lien claim is that the creditor’s formal written “Notice of Intent to File a Mechanic’s Lien” (hereafter “Lien Notice”) must be (1) served on the owner of the property for which the work was done or the materials used, and (2) served at the same time on the general contractor who has handled the construction project. After the creditor has made service of the lien claim by USPS certified mail (using the green return receipt card for proof of service) or separate personal delivery of the notice to the property owner and general contractor, ten full days must pass (not including the date of mailing of the notices) before the lien notice is filed in the public records.
After ten days have expired following the date of mailing using certified mail, or personal delivery of the notice to the property owner and the general contractor, the lien notice can be filed to make the lien valid.
Reprinted courtesy of David M. McLain, Higgins, Hopkins, McLain & Roswell, LLC. Mr. McLain can be contacted at mclain@hhmrlaw.com
Read the full story…
Lawsuit over Construction Defects Not a Federal Case
August 16, 2012 — CDJ Staff
The United State District Court in California has dismissed the claims of a contractor against the United States government, on the grounds that it was not within the subject matter jurisdiction of the court. The origins of the case are in a related construction defect claim. The current plaintiff, Performance Contracting, Inc., did the lath and plaster work for a building for the Department of Veterans Affairs. After the building was completed, the Veterans Affairs complained to the general contractor, Wynema, Inc., of water intrusion problems.
Wyema and Performance conducted testing and the water intrusion was found to be due to “a variety of design defects and omissions, including: 1) omission of proper window flashing; 2) inadequate waterproof membrane around the windows; 3) inadequate T-molding around the windows; 4) lack of a window sill pan for the windows; 5) lack of any backing in the window framing; 6) lack of any backing for the stucco expansion joints and seams; and 7) failure to require that a performance mock-up of the window assembly and adjacent areas be built and water tested.” Wyema filed a construction defect action against Performance and other subcontractors.
In the current case, Performance claims that Veteran Affairs was negligent, that it “breached its duty to Plaintiff when it provided deficient plants and specifications” and “failed to properly oversee construction and inspect Project work.” The court determined that it could not hear this case, noting that “Federal Courts are presumptively without jurisdiction over civil actions.”
Performance raised its claims under the Federal Tort Claims Act. The judge was not persuaded by this claim, noting that the FTCA does not apply to purported breach of the General Contract. The FTCA waives the government’s sovereign immunity in cases of “injury or loss of property, or personal injury or death caused by the negligent or wrongful act or omission of an employee of the Government while acting within the scope of his office or employment, under circumstances where the United States, if a private person, would be liable to the claimant in accordance with the law of the place where the act or omission occurred.”
Performance was unable to pursue its claims in the Court of Federal Claims as there was no contract between Performance and the government. However, the court noted that Performance’s inability to file suit in the Court of Federal Claims does not open up a path to the District Court. “Litigants are not guaranteed a forum in which to sue the United States.” The court further noted that “if this Court were to accept Plaintiff’s logic, non-parties to contracts, but not parties, would be free to pursue contract claims in the fora of their choosing.”
Read the court’s decision…