Ohio subcontractor work exception to the “your work” exclusion
August 11, 2011 — CDCoverage.com
In Mosser Construction, Inc. v. Travelers Indem. Co., No. 09-4449 (6th Cir. July 14, 2011)(unpublished), claimant project owner Port Clinton contracted with insured general contractor Mosser for the construction of a building. Following completion, Port Clinton sued Mosser for breach of contract seeking damages because of physical injury to the project occurring after completion resulting from defective backfill material that settled improperly.
Mosser’s CGL insurer Travelers denied a defense and Mosser filed suit against Travelers seeking a declaratory judgment. Mosser and Travelers filed cross-motions for summary judgment on the issue of whether the supplier of the backfill material?Gerken?qualified as a subcontractor for purposes of the subcontractor work exception to the “your work” exclusion—exclusion l.—for property damage to or arising out of Mosser’s completed work.  Mosser had purchased the backfill material from Gerken pursuant to a purchase order specifying that Gerken was to supply Mosser with an industry standard grade of backfill for use in the Port Clinton project.
Read the full story…
Reprinted courtesy of CDCoverage.com
Pennsylvania Court Extends Construction Defect Protections to Subsequent Buyers
December 20, 2012 — CDJ Staff
The Pennsylvania courts have long held that there is an implied warranty of habitability for the initial purchaser of a home. Now, as some defects may not immediately show up, the court has extended that implied warranty to second and subsequent purchasers. As Marc D. Brookman, David I. Haas, and Christopher Bender of Duane Morris note, “this judicially created doctrine shifts the risk of a latent defect in the construction of a new home from the purchaser to the builder-vendor.”
The Pennsylvania Supreme Court concluded that a contractual relationship is not needed for an implied warranty of habitability. The court’s concern was inequalities would result when a home was sold while other homes were protected by being within the statute of repose.
Read the full story…
Utah Construction Defect Claims Dependant on Contracts
July 10, 2012 — CDJ Staff
An owner who wants to sue a subcontractor directly may find limited ability to do so under Utah court decisions. Writing on the JDSupra site, Stewart O. Peay and Mark O. Morris of Snell & Wilmer discuss the distinction the Utah courts make between contractor (with whom an owner has direct contracts) and subcontractors (with whom an owner does not). In the Utah courts, construction defect claims must be based on contract, rather than tort. With no contract, there is no way to pursue claims against a subcontractor alone.
They note that the Utah couts do not “accept negligence and negligent misrepresentation claims that many other jurisdictions embrace.” They recommend that in setting up contracts for a construction project, owners should ensure that they are provided with “third-party beneficiary rights to purse claims against subs.” They suggest that “the owner may require his generals to include language in the various subcontracts that incorporates some or all of the terms of the prime contract into the subcontracts.” Additionally they suggest that the owner “require the general to include ‘flow down’ provisions in the various subcontracts.”
Read the full story…
Exclusion Bars Coverage for Mold, Fungus
October 23, 2012 — Tred Eyerly, Insurance Law Hawaii
The court considered whether rain damage to a house was barred by the policy's mold exclusion. Stewart v. State Farm Fire & Cas. Co., 2012 U.S. Dist LEXIS 127804 (D. S.D. Sept. 7, 2012).
The insureds hired DJ Construction to build a new home. Before construction was completed, it was discovered that DJ Construction and some of its subcontractors had failed to protect the partially constructed house from the elements, which allowed melting snow and rain to intrude into the house. Soon after this discovery, DJ Construction abandoned the project. The house remained incomplete and uninhabitable.
The insureds sued DJ Construction.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Demand for Urban Living Leads to Austin Building Boom
August 16, 2012 — CDJ Staff
The New York Times reports that Austin is undergoing a building boom as a high-tech firms, including Facebook and Google, have moved into the downtown area. With them, comes a need for more apartment buildings and more retail space. Mike Kennedy, the president and chief executive of an Austin real estate firm, told the Times “the office space was here, the housing came, and retail is arriving last to the scene.” Currently, two large projects that will add about 500 apartment units is underway, including a 222-unit, 18-story building, and another that will contain 277 units. Apartment occupancy in Austin is at ninety-seven percent.
Developers also have hotels and more office space planned. The area has about 6,000 hotel rooms with an additional 2,000 planned, but events in Austin can bring in more people than the city’s 30,000 hotel rooms can accommodate. Office space is eighty-eight percent occupied, and a lack of office space could cause firms to look elsewhere.
Read the full story…
Defective Drains Covered Despite Water Intrusion Exclusion
July 10, 2012 — CDJ Staff
The US District Court in Washington State has granted a summary judgment in Hiller v. Allstate Prop. & Cas. Ins. Co. The Hillers bought a new home in Wenatchee, Washington and insured it with an “all risk” policy from Allstate. Subsequently, Mr. Hiller discovered that the carpet in the basement was saturated with water. Hiller notified Allstate who requested that he determine the source of the water intrusion. Hiller poured water into a downspout drain and found this caused water to leak into the home’s basement.
Further investigation with the homes original excavation contractor revealed that “the end of the drain pipe was partially blocked by rocks and had been wrapped with fabric landscaping material.” Additionally, “a ‘T’ pipe installed at the foot of the drain was directing water toward the house’s concrete foundation.” Allstate denied the claim “under the policy’s surface water, subsurface water, inherent vice, and latent defect exlusions.” After the denial, Hiller “discovered that the foundation had not been treated with waterproof sealant and that several concrete form pins were still in place.”
The court noted that “there is no genuine dispute about the cause of the claimed loss.” This left the court concluding that “the only relevant question for the purposes of the instant cross-motions for summary judgment is whether a loss caused by defective construction is covered under the Hillers’ ‘all risk’ insurance policy.” Under Washington’s “efficient proximate cause” rule, “where an insured risk itself sets into operation a chain of causation in which the last step may have en an excepted risk, the excepted risk will not defeat recovery.” The court found that a loss caused by defective construction is in fact covered under the policy, noting that “the policy does not contain an exclusion for defective construction.”
The court concluded that the defective drain was not an inherent vice, as it “cannot properly be characterized as defects ‘inherent [in the] nature of the commodity which will cause it to deteriorate with a lapse of time.” Nor was it a latent defect, “one that could not have been discovered by inspection.” The court concluded that “both of the construction defects at issue could have been discovered by a reasonable inspection.”
With these facts determined, the court found for the Hillers.
Read the court»s decision…
Pier Fire Started by Welders
August 2, 2012 — CDJ Staff
Welders working on Pier 29 in San Francisco were preparing the building for the America’s Cup sailing race. Instead, they accidentally caused $2.4 million in damages. Mindy Talmadge, a fire department spokesperson, attributed the fire to crews welding a latter to a wall. According to Talmadge, a spark entered a crack in the concrete wall and “the wood on the building underneath was really dry.” It took firefighters more than two hours to extinguish the blaze.
Read the full story…
Louisiana Politicians Struggle on Construction Bills, Hospital Redevelopment
June 16, 2011 — CDJ Staff
Louisiana politicians are still working on a compromise in the state’s construction budget, as reported in the Times-Picayune. Rob Marrianneax, the chair of the Senate Revenue and Fiscal Affairs Committee, removed a $45 million request from Governor Bobby Jindal and added $4 million for projects that Jindal vetoed last year.
Two senators have formed competing plans to fund redevelopment construction for New Orleans’s Methodist Hospital. Mitch Landrieu, the mayor of New Orleans, hoped for $30 million dollars in state bonds. Senator Cynthia Willard-Lewis proposed an amendment that would supply $1.6 million, while Senator J.P. Morrell has an amendment that would supply $4 million.
Read the full story…
Subcontractor Not Liable for Defending Contractor in Construction Defect Case
February 10, 2012 — CDJ Staff
The California Court of Appeals has ruled on January 9, 2012 in Hensel Phelps Construction Company v. Urata & Sons Cement, upholding the judgment of the lower court.
Hensel Phelps was the general contractor for a high-rise in Sacramento. They were sued by the owners of the building after problems were discovered in the concrete slabs of the building’s parking garage. Instead of welded steel wire mesh, the slabs had been constructed with fiber mesh. Hensel Phelps filed a cross-complaint against Urata Cement, the subcontractor that had performed the cement work. Urata refused to defend Hensel Phelps. The owners’ case was subsequently dismissed due to the statute of limitations.
Although the original case was over, Hensel Phelps continued in their claims against Urata. “Urata argued that a handwritten interlineation required Hensel Phelps to prove Urata was at fault for the injury alleged in the building owners’ complaint before Urata was obliged to defend Hensel Phelps in that action.”
The lower court concluded that Urata would have been obligated to defend Hensel Phelps if the owners’ lawsuit had alleged that the damage was due to the subcontractor’s work or if evidence at trial established this. The lower court found neither of these true. Instead, the use of the fiber mesh was a design issue and “that decision was outside the scope of the subcontractor’s work.”
During the trial, Hensel Phelps conceded that Urata was not at fault. The appeals court could find no reading of the contract that would cause Urata to be obligated to defend Hensel Phelps, calling Hensel Phelps’s reading of the contact as “grammatically infeasible.”
Judges Nicholson, Raye, and Butz upheld the decision of the lower court and awarded costs on appeal to Urata.
Read the court’s decision…
Homebuilders Go Green in Response to Homebuyer Demand
May 10, 2012 — CDJ Staff
McGrawHill Construction reports that 17 percent of new homes and remodels in 2011 were done with green building practices. Their report estimates that by 2016, this will rise to 29 to 38 percent of the market for home construction and remodeling.
Consumers see the green buildings as more desirable, particularly where they are more energy efficient. Two thirds of builders noted their customers were interested in features that would lower the energy use of their homes. Consumers also feel that green building materials are more durable and see green homes as higher quality.
Read the full story…
California Lawyer Gives How-To on Pursuing a Construction Defect Claim
September 13, 2012 — CDJ Staff
On his recently started blog, Harry Kaladjian writes about construction defect litigation in California. He notes that after taking possession, homeowners sometimes notices problems such as “slab cracks in the garage, water leaking through the ceiling, warped floors, improper framing, cracking stucco, etc.” He goes on to note that once that happens, there are series of things homeowners must do.
The first is to be concerned about the statute of limitations. Then, “once it has been established that defects exist, the homeowner must refer to the ‘Right to Repair Act’ and ‘Calderon Procedures.’” These, he notes set out the “pre-litigation procedures prior to filing a lawsuit.”
Read the full story…
Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses
April 25, 2012 — Douglas Reiser, Builders Cousel
Ever had that lingering problem with a contracting partner that went away for awhile and then came back to bite you ? years later? In Washington, construction contract claims can be raised for up to six years after substantial completion. Six years!? Why would I want to wait that long to find out if I have a problem? You don’t have to.
Over the past few years, I have discussed the notion of “contractual claim periods” on The Builders Counsel. For today’s Save a Legal Fee column, I cannot think of a better topic. These provisions are specifically intended to save you from unnecessary legal fees that might arise if a problem goes unnoticed for too long.
Contractual claim periods are simply a way to reduce the amount of time that a contracting party has to raise a claim against its contracting partner. For example, a subcontractor might require that a general contractor raise any claim that it might have ? for defective or incomplete work, injury, damages, etc ? within a particular amount of time or forever lose the ability to raise the claim in a legal proceeding.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Changes to Arkansas Construction and Home Repair Laws
September 30, 2011 — CDJ Staff
A new law, set to take effect in 2012, lowers the ceiling on when work must be done by a licensed contractor. Through the end of the year, projects costing $20,000 or more had to be done by an Arkansas licensed contractor. As of January 1, 2012, that new limit will be $2,000.
This will apply to all single-family residences and according to Lovely County Citizen, covers “construction, alteration, renovation, repair, modification, improvement, removal, demotion, or addition to a pre-existing structure.” Residential building contractors will be required to have workers compensation insurance, as will home improvement contactors if they take jobs worth more than $20,000.
Morris Dillow, a building inspector in Holiday Island, said, “It will get these scammers out of here who are ripping people off.” He cited the example of a contractor who after getting paid for roof repairs and painting, left the job unfinished.
Read the full story…
Texas covered versus uncovered allocation and “legally obligated to pay.”
April 27, 2011 — April 27, 2011, by CDCoverage.com
In Markel American Ins. Co. v. Lennar Corp., No. 14-10-00008-CV (Tex. Ct. App. April 19, 2011), insured homebuilder Lennar filed suit against its insurer Markel seeking recovery of costs incurred by Lennar to repair water damage to homes resulting from defective EIFS siding. Following a jury trial, judgment was entered in favor of Lennar and against Markel. On appeal, the intermediate appellate court reversed. Applying Texas law, the court first held that Lennar failed to satisfy its burden of allocating damages between covered and uncovered. In a prior decision, the court had held that, while the costs incurred by Lennar for the repair of the resulting water damage
Read the full story…
Reprinted courtesy of CDCoverage.com
Court Orders House to be Demolished or Relocated
April 26, 2011 — April 26, 2011 Beverley BevenFlorez - Construction Defect Journal
Decision Affirmed in Central Arkansas Foundation Homes, LLC v. Rebecca Choate
The Arkansas Court of Appeals affirmed the decision by the trial court in Central Arkansas Foundation Homes, LLC v. Rebecca Choate. In the trial case, Central Arkansas Foundation Homes (CAFH) sought payment for a home built for Choate, while Choate alleged that the builders committed multiple construction defects including using the wrong foundation materials and positioning the house in the wrong direction.
After the house was built, CAFH contacted Choate regarding payment, however, Choate alleged that the finished product did not match the contract. “ After CAFH completed construction, it obtained permanent home financing for Choate and tried to contact her to close the transaction. Choate did not respond until October 2005, when she sent CAFH a list of alleged construction defects, including that the house was facing in the wrong direction; that it was not built on a slab; and that the fireplace, garbage disposal, driveway, and storage area were missing. CAFH replied to Choate in writing, telling her that she had until January 6, 2006, to close on the house or CAFH would sell it. The correspondence enclosed worksheets showing that the amount Choate would owe at closing exceeded $94,000, which included interest that had accrued on the as-yet unpaid construction loan.”
Initially, the court found in favor of CAFH. “On April 18, 2007, Choate’s attorney withdrew from representing her. Soon thereafter, CAFH’s attorney asked the court to set a final hearing on the case. The attorney purportedly sent Choate a letter by regular mail on May 15, 2007, advising her that the case was set for trial on July 9, 2007. Choate, however, did not appear. CAFH did appear, and its general manager, John Oldner, testified to events leading up to the case and the amount of damages claimed. According to Oldner, the interest on the construction loan had accrued to the point that CAFH now sought $104,965.88 from Choate. The court found in favor of CAFH and entered judgment for that amount, plus attorney fees, on July 18, 2007. The court ruled that CAFH could sell the house and either remit any excess to Choate or look to Choate for the deficiency if the sales price did not cover the judgment.”
However, Choate successfully argued that she did not receive notice of the trial. A new trial was ordered, and the outcome was quite different. “On June 6, 2008, the circuit court entered judgment for Choate, ruling that the house was not in substantial compliance with the parties’ contract and that the contract should be rescinded. The court found that the house suffered from numerous construction defects, that the contract contemplated a slab rather than a concrete-pier foundation, and that CAFH ignored Choate’s complaints that the house was facing the wrong way. The judgment directed CAFH to hold Choate harmless on the construction loan, to deed Choate’s two acres back to her, and to remove the house from Choate’s property.”
The Court of Appeals “found that Choate would be unjustly enriched by retaining the benefit of the septic systems and utility lines that CAFH installed on her land. The court therefore awarded $5340 to CAFH as a quantum-meruit recovery for the value of that work. CAFH contends that the award is not sufficient, but we see no clear error.” In the end, the Court of Appeals provided this reason for declining to reverse the trial court’s decision: “The court in this case apparently concluded that the house constructed by CAFH was so fundamentally at odds with Choate’s contractual expectations that she was not unjustly enriched and should simply be, as nearly as possible, returned to the status quo ante. Accordingly, the court ordered the house removed from her property and permitted CAFH to either relocate the house or salvage the house’s materials and unused appliances. We decline to reverse the court’s weighing of the equities in this manner.”
Read the court’s decision…
Guilty Pleas Draw Renewed Interest In Nevada’s Construction Defect Laws
December 9, 2011 — CDJ Staff
A report this week by David McGrath Schwarz of the Las Vegas Sun suggests that Nevada’s construction defect laws will be a point of much contention in upcoming legislative sessions. The report cites renewed interest in the state’s construction defect laws due to ongoing federal investigations of construction defect attorney Nancy Quon and construction company owner Leon Benzer. Guilty pleas have been entered by at least ten individuals including an attorney, property managers, straw purchasers, and former HOA board members.
The article suggests that Nevada’s Chapter 40 laws are easily manipulated to the detriment of Nevada’s homebuilding industry. Construction industry lobbyists have tried unsuccessfully to change the laws in past legislative sessions.
The Sun’s article speculates that the building industry might be able to gain legislative concessions due to the volume of guilty pleas and what it refers to as examples of Chapter 40 abuses. ”With federal authorities collecting guilty pleas, the construction industry has prime examples of the system being abused, and how lucrative it can be for attorneys.”
Read the full story…
Judge Rejects Extrapolation, Harmon Tower to Remain Standing
November 7, 2012 — CDJ Staff
CityCenter has filed an emergency motion asking the Nevada Supreme Court to intervene in Judge Elizabeth Gonzalez’ order that the building’s defects cannot be extrapolated from those tested. CityCenter’s structural engineering expert “evaluated 397 of the Harmon’s critical structural elements and found all but one defective,” according to the article on Vegas.Inc. Judge Gonzalez would not permit this to be extrapolated to the untested 1,072, as the locations tested were not random.
Judge Gonzalez also ruled that if CityCenter does additional testing, they may not appeal her order that ruled the extrapolation inadmissible. CityCenter argued to the Nevada Supreme Court that “the notion that CityCenter should be forced to incur additional millions of dollars in testing costs and sanctions ?Äì on the condition that it waive its right to appeal this ruling ?Äì just to be permitted to present its own damages evidence, shocks the conscience.”
Gonzalez gave the okay to CityCenter to demolish the building, but its demolition would make any further testing impossible. Under Gonzalez’ ruling, the untested structural elements cannot b assumed to be defective.
Read the full story…
Bound by Group Builders, Federal District Court Finds No Occurrence
August 11, 2011 — Tred Eyerly, Insurance Law Hawaii
The homeowners sued their contractor, alleging the contractor had defectively constructed and failed to complete their home.  State Farm Fire and Casualty Co. v. Vogelgesang, 2011 U.S. Dist. LEXIS 72618 (D. Haw. July 6, 2011). The homeowners' complaint pled, among other things, damage caused by breach of contract and negligence. State Farm agreed to defend under a reservation of rights.
State Farm filed suit in federal court for declaratory relief. Judge Mollway granted State Farm's motion for summary judgment. Relying on the Hawaii Intermediate Court of Appeal's decision in Group Builders, Inc. v. Admiral Ins. Co., 123 Haw. 142, 231 P.3d 67 (Haw. Ct. App. 2010), Judge Mollway determined that the claims asserted in the underlying litigation arose from the contractor's alleged breach of contract.  Group Builders held that breach of contract claims based on allegations of shoddy performance were not covered under CGL policies.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com