Eighth Circuit Remands to Determine Applicability of Collapse Exclusion
January 6, 2012 — Tred Eyerly, Insurance Law Hawaii
The Eighth Circuit determined a jury instruction regarding the applicability of the "all-risk" policy’s exclusion for "collapse" was inadequate. See KAAPA Ethanol, LLC v. Affiliated FM Ins. Co., 2011 U.S. App. LEXIS 22158 (8th Cir. Nov. 3, 2011).
KAAPA had nine large, cylindrical, stainless steel tanks fabricated at its location. Soon after operations began in 2003, some of the tanks experienced unusual movement and began to shift. A geotechnical engineer found "silty clay" had been used for infill instead of compacted granular fill called for in engineering drawings. A year long plan to repair all nine tanks was implemented.
Affiliated’s "all-risk" policy excluded damage caused by faulty workmanship. It also excluded damage caused by settling or cracking. The settling exclusion went on to provide, "This exclusion will not apply to loss or damage resulting from collapse of: a building or structure; or material part of a building or structure." Affiliated denied coverage because of the faulty workmanship and settling exclusions.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
School District Marks End of Construction Project by Hiring Lawyers
June 19, 2012 — CDJ Staff
A school district in northeastern Pennsylvania has retained legal services as they approach the end of a construction project. The Mid Valley School Board cited concerns about the project’s budget, but Randy Parry, Superintendent of Mid Valley schools referenced “possible litigation at the end of the project.” Mr. Parry told the Scranton Times Tribune that construction delays could be a reason for litigation.
In addition to approving an additional $20,000 for legal representation, the board also approved $21,579 for additional project costs.
Read the full story…
Contractors Admit Involvement in Kickbacks
December 9, 2011 — CDJ Staff
Two New Jersey contractors have pleaded guilty to charges that they made false representations for a government contract in a case related to kickbacks for construction work done in two school districts. New Jersey is recommending that the two men, Martin Starr and Stephen Gallagher, will each pay $50,000 in penalties, serve up to a year in jail, and be unable to accept public contracts for five years.
Last month, another individual in the case, Kenneth Disko, who had been the engineer for the school district, pleaded guilty on a similar charge. In addition to a $50,000 penalty, he will be serving three to five years in prison. A fourth conspirator, Robert Berman, the former business administrator for one of the school districts, has to pay a $13,000 fine and cooperate with the investigation. He is also barred from public employment in New Jersey and has been terminated from his position.
Starr admitted to preparing fictitious quotes which appeared to be from other contractors in order that his firm would seem to be the lowest bidder. Gallagher helped in preparing the fictitious bids and also provided cash kickbacks to Disko.
Read the full story…
Contractor Sues License Board
June 30, 2011 — CDJ Staff
Judge Kendall J. Newman of the US District Court handed down a decision on June 24 on the case of Kent v California Department of Consumer Affairs. Mr. Kent, appearing as his own counsel, had brought the suit against the California Department of Consumer Affairs and the Contractors State Licensing Board after he was arrested in a sting operation and, as the plaintiff put it, “was absurdly arrested and uncooperatively detained for a time longer than necessary or allowed by law under the false pretense of contracting with out a license.” Mr. Kent’s alleged that Rick Lopez, one of the defendants, formed him to read allow from the California Business and Professions Code. He said he was later handcuffed and placed in an uncomfortable chair, “enduring physical pain and emotional agony.”
Although Kent was given a Notice to Appear, he alleged that a further defendant, Stuart Rind, “closed the plaintiff’s case marked citation A7773 without giving written notice to anyone.” As a result, the Placer County District Attorney’s Office had no record of his Notice to Appear.
Kent alleged that subsequently his firm was essentially shut down for two years and that he was prevented from “legally contracting or selling services for any other contractor or qualifying for any other licensed capacity governed by the CSLB.” After this, the CSLB suspended the license for his firm, DSI Construction. He was assessed a $1,500 fine, after which he claims he sent a letter to the CSLB demanding money damages. The judge noted that the letter was not included in the plaintiff’s Ninth Amended Complaint.
Judge Kendall recommended that the plaintiff’s Complaints be dismissed, although he did allow that sixth, and perhaps the eighth and ninth, could be amended with a tenth amended complaint.
Read the court’s decision…
David McLain to Speak at the CDLA 2012 Annual Conference
June 19, 2012 — CDJ Staff
The Colorado Dense Lawyers Association will be holding their 2012 Annual Conference from July 26 through the 28, in Crested Butte, Colorado. The CDLA provides benefits to its member defense trial lawyers, including educational and information resources.
David McLain of Higgins, Hopkins, McLain & Roswell, LLC will be joining in a discussion with William J. McConnell, PE of Vertex Engineering on Saturday, July 28. Their topic will be common building code violations alleged in construction defect cases and how to respond to these allegations.
Read the full story…
Lower Court “Eminently Reasonable” but Wrong in Construction Defect Case
July 10, 2012 — CDJ Staff
Noting that “circuit court’s orders are eminently reasonable, logical and just” the Supreme Court of Appeals of West Virginia has granted a writ to halt enforcement of these orders and to compel arbitration instead in the case of State v. Tucker. The initial case concerned claims that an HVAC system had been improperly designed, constructed, manufactured, or maintained, leading to serious problems. Glenmark Holding, the owner of the Suncrest Executive Plaza brought a lawsuit against seven defendants. Three of the defendants, Morgan Keller, Inc, York International Corporation, and Johnson Controls, Inc. argued that Glenmark was obligated to enter into arbitration.
Glenmark and the other defendants argued that the motions for arbitration should be denied “so all the claims and cross-claims of the parties could be litigated in one forum, in one proceeding.” The circuit court noted that arbitration is preferred over litigation because of its supposed “expeditious, economic resolution of issues,” but that in this case, “the petitioners would expend additional, not fewer resources responding to the parties’ claims and cross-claims.” As “compulsory arbitration would be insufficient and inequitable” the court denied the request, finding the arbitration clauses “unconscionable and, therefore, unenforceable.”
Morgan Keller, York, and Johson argued that “the interpretation of arbitration clauses is governed exclusively by the Federal Arbitration Act.” The appeals court found that “the circuit court was within its authority to consider Glenmark’s claim that the arbitration clauses were unenforceable.” However, the appeals court rejected the circuit court’s conclusion about the “piecemeal” resolution of the conflict, as it contradicts a Supreme Court ruling. The Supreme Court stated in 1983 that the FAA “requires piecemeal resolution when necessary to give effect to an arbitration agreement.” In a 1985 decision, the Court held that a court could “not substitute [its] own views of economy and efficiency.”
Nor could the court find the arbitration clause to be unconscionable or unenforceable. The court noted that the contract was a standard AIA form, and was amended by the parties involved, whom the court characterized as “commercially sophisticated.” The court found that the agreement limited the rights of all parties and was not one-sided.
As the arbitration clause was neither unconscionable nor unenforceable, and Supreme Court rulings preclude a court from substituting its own procedures, even when these are “eminently reasonable, logical and just,” the appeals court halted the order of the circuit court, sending the matter to arbitration.
Read the court’s decision…
Allowing the Use of a General Verdict Form in a Construction Defect Case Could Subject Your Client to Prejudgment Interest
August 2, 2012 — Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC
A recent opinion from the Colorado Court of Appeals is a cautionary tale concerning the calculation of pre-judgment interest. See Hendricks v. Allied Waste Transportation, Inc., 2012 WL 1881004 (Colo. App. 2012). The Hendricks sued Allied after one of its drivers backed into the corner of their home with an Allied garbage truck. At trial, a jury awarded the Hendricks $160,100 in damages. Although the jury was instructed on the cost of repairs, diminution in value, and non-economic damages, the parties agreed to a general verdict form that did not ask the jury to specify the types of damages awarded. The Hendricks sought to amend the judgment to include prejudgment interest and costs, which the trial court granted.
Allied appealed, arguing that the trial court erred by awarding the Hendricks prejudgment interest from the date their property was damaged. Id. at *7. The Colorado Court of Appeals found no error, and affirmed.
Read the full story…
Reprinted courtesy of Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC. Ms. Anderson can be contacted at anderson@hhmrlaw.com
Legislatures Shouldn’t Try to Do the Courts’ Job
March 1, 2012 — CDJ Staff
David Thamann, writing in Property Casualty 360, argues that current actions by legislatures on insurance coverage amount to “legislative interference or overreach.” He notes that under current Colorado law, “a court shall presume that the work of a construction professional that results in property damage — including damage to the work itself or other work — is an accident unless the property damage is intended and expected by the insured.” He argues that here legislators are stepping into the role of the courts. “Insureds and insurers are not always going to be pleased with a court ruling, but that is the system we have.”
Read the full story…
Injured Construction Worker Settles for Five Hundred Thousand
October 28, 2011 — CDJ Staff
An upstate New York man who was injured when an unsecured truss fell off the railings of a scissor lift has settled for $500,000. As the accident happened at the building site for a casino for the Seneca Nation, attorneys for the construction firm had argued that New York labor laws were inapplicable as the injury happened on Seneca Nation land. The state appeals court ruled that as none of the parties involved were Native Americans, it was not internal to the affairs of the Seneca Nation.
Read the full story...
Boston Tower Project to Create 450 Jobs
November 18, 2011 — CDJ Staff
Continuing the development of Boston’s Theater District, Millennium Partners broke ground for the building of Hayward Place, a 15-story residential tower with street-level shops. The project is expected to take two years to complete and will employ about 450 construction workers.
Thomas Menino, the mayor of Boston said that the “ground breaking of Hayward Place is another sign of economic growth and forward progress on the revitalization of this area.” The project will be built by Suffolk Construction. John Fish, their CEO, said they were “fortunate as a contractor to be the beneficiary of this.”
The report in the Boston Herald notes that a few blocks away, the site of the former Filenes department store is still “an empty eyesore.” Menino joked, “anyone want to bid for it?” He promised that site would also be developed.
Read the full story…
The Montrose Language Interpreted: How Many Policies Are Implicated By A Construction Defect That Later Causes a Flood?
March 17, 2011 — By Shaun McParland Baldwin, March 17, 2011
The Court of Appeals of Indiana recently addressed the “Montrose” language added to the CGL ISO form in 2001 in the context of a construction defect claim where a fractured storm drain caused significant flooding a year after the drain was damaged. The insuring agreement requires that “bodily injury or “property damage” be caused by an occurrence and that the “bodily injury or “property damage” occur during the policy period. The Montrose language adds that the insurance applies only if, prior to the policy period, no insured knew that the “bodily injury or “property damage” had occurred in whole or in part. Significantly, it also states that any “bodily injury” or “property damage” which occurs during the policy period and was not, prior to the policy period known to have occurred, includes a continuation, change or resumption of that “bodily injury” or “property damage” after the end of the policy period.
In Grange Mutual Cas. Co. v. West Bend Mut. Ins. Co., No. 29D04-0706-PL-1112 (Ct. App. IN March 15, 2011), http://www.ai.org/judiciary/opinions/pdf/03151109ehf.pdf, Sullivan was the General Contractor for a school construction project. Its subcontractor, McCurdy, installed the storm drain pipes. One of the storm pipes was fractured in 2005 while McCurdy was doing its installation work. More than a year later, the school experienced significant water damage due to flooding. It was later discovered that the flooding was due to the fractured storm drain. Sullivanrsquo;s insurer paid $146,403 for the water damage. That insurer brought a subrogation claim against McCurdy and its two insurers: West Bend and Grange. West Bend had issued CGL coverage to McCurdy while the construction was ongoing, including the date in which the storm pipe was fractured. Grange issued CGL coverage to McCurdy at the time of the flooding. Those two carriers jointly settled the subrogation claim and then litigated which insurer actually owed coverage for the loss. Significantly, the loss that was paid included only damages from the flooding, not any damages for the cost of repairing the pipe.
Read the full story...
Reprinted courtesy of Shaun McParland Baldwin of Tressler LLP. Ms Baldwin can be contacted at sbaldwin@tresslerllp.com
Las Vegas Home Builder Still in Bankruptcy
October 23, 2012 — CDJ Staff
American West Development attempted to exit Chapter 11 bankruptcy on September 27, but their plan was turned down by U.S. Bankruptcy Court Judge Mike Nakagawa. According to the Las Vegas Review-Journal, Judge Nakagawa rejected the plan over a trust fund for construction defects. America West’s attorney said they were hoping to complete the process by the end of the year.
Under approved portions of the plan, America West’s owner, Lawrence Canarelli, will retain control of the corporation, although he must contribute $10 million into the firm and an additional $1.5 million into the fund for construction defects. America West faces charges for construction defects reported in the broad range of “less than $20 million” to “as much as $80 million.”
Read the full story…
No-Show Contractor Can’t Hide from Construction Defect Claim
June 19, 2012 — CDJ Staff
The failure of R. J. Haas to produce documents or make himself available for deposition has worn out the patience of the US District Court in San Jose. Judge Howard Lloyd issued a ruling inProbuilders Specialty Ins. Co. v. Valley Corp. (N.D. Cal., 2012).
Probuilders issued an insurance policy covering Haas for their work on the construction of a single-family home for Ty and Karen Levine. The Levines sued Haas for “shoddy and incomplete work.” Probuilders contends that Haas “made material misrepresentations with respect to verifying that the subcontractors had insurance.” Since November 2011, Haas has been without legal counsel in this matter.
Despite Probuilder’s attempts, the court noted that “Hass any not provided any documents in response to the plaintiff’s three sets of requests for production of documents.” Haas also “has refused to make himself available for deposition.” Haas was first scheduled for deposition in September, 2011. Subsequently, Haas has rescheduled his deposition repeatedly, postponing it to January 4, then February 13, and then agreed to be deposed “before the then-scheduled March 15 mediation,” after which he said he would “be unavailable to be deposed before April.
The court noted that although Haas “hay have had legitimate reasons for wishing to continue his deposition, such as illness and his attempt to retain new counsel,” however, the court concluded that “Haas has had ample time to retain new counsel and prepare for deposition.
The court also found fault with Haas’s objections to certain terms in the Request for Admissions, among them “named,” “independent contractor,” and “work,” noting that Haas called these “vague and ambiguous.” The court called it “quibbling,” and noted that the federal courts disfavor this. Later in the decision, the court made it clear that Haas “is obligated under the Federal Rules of Civil Procedure to respond to discovery requests.” And concludes, “that he has apparently been seeking to retain new counsel for over five months does not give him license to ignore plaintiff’s discovery requests entirely.
The court granted Probuilders the option of filing a motion for sanctions. Mr. Haas did not attend or participate.
Read the court’s decision…
Cogently Written Opinion Finds Coverage for Loss Caused By Defective Concrete
November 7, 2012 — Tred Eyerly, Insurance Law Hawaii
If ever in need of a concise, well-reasoned opinion on “occurrence,” “property damage” and applicability of the business risk exclusions, turn to Pamperin Rentals II, LLC v. R.G. Hendricks & Sons Construction, Inc., 2012 Wis Ct. App. LEXIS 698 (Wis. Ct. App. Sept. 5, 2012).
A contractor was hired to install concrete during construction of seven gas stations. Red-D-Mix provided the concrete. The contractor and Red-D-Mix were eventually sued by the gas stations, based upon allegations that the concrete was defectively manufactured and installed. The gas stations alleged that Red-D-Mix supplied concrete that was defective and resulted in damages, including the need to repair nearby asphalt.
Red-D-Mix tendered to its insurers, who denied coverage. Suit was filed and the insurers moved for summary judgment. The trial court determined there were no allegations of either “property damage” or an “occurrence.” Therefore, there was no duty to defend or indemnify Red-D-Mix.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Virginia Chinese Drywall and pollution exclusion
May 27, 2011 — CDCoverage.com
In Nationwide Mut. Ins. Co. v. The Overlook, LLC, No. 4:10cv69 (E.D. Va. May 13, 2011), homeowner Edmonds sued insured developer/general contractor Overlook seeking damages resulting from defective Chinese drywall installed in Edmonds’ home. Overlook’s CGL insurer Nationwide defended Overlook under a reservation of rights and filed a declaratory judgment action. The federal district trial court granted Nationwide’s motion for summary judgment.
Read the full story…
Reprinted courtesy of CDCoverage.com
Insurance Firm Under No Duty to Defend in Hawaii Construction Defect Case
September 13, 2012 — CDJ Staff
The US District Court for Hawaii has granted a motion for summary judgment in Evanston Insurance v. Nagano. The case is related to a construction defect claim, Hu v. Nagano, and the issue at hand is whether Evanston Insurance is obligated to defend the Naganos in the underlying case.
The Hus hired Eric Nagano and his firm PMX to construct a house. Mr. Nagano’s firm was insured by Evanston, however, he lost his contractor’s license in “approximately March 2006.” Mr. Nagano sought the Hus’ authorization to allow HC Builders to take over the contract. HC Builders is headed by Mr. Nagano’s wife, Hiroko, who has held a contractor’s license since “approximately September 2006.” Ms. Nagano and HC Builders were also insured by Evanston Insurance. The house, started by PMX was finished by HC Builders.
The Hus authorized construction to begin in July 2003, but “construction did not commence until approximately October 2004 and, even after commencement, there were numerous delays resulting in months of inactivity on the Project.” The Hus had expressed to Mr. Nagano and PMX “that the construction period could not exceed twelve months after July 1, 2003.” As a result of the delays, “the Hus’ community association fined them because of the prolonged construction and the Hus’ construction lender assessed extension fees and fines for exceeding the term of the loan.”
The Hus noted that the project did not have a licensed contractor from March through September 2006. In the end, the Hus “allege that Defendants did not fulfill the obligations under the Construction Contract,” and that “the Project was ‘grossly delayed’ and the construction was ‘riddled with defects.’” Despite an Owner’s Notice of Completion filed in December 2007, the residence “had no electricity, no hot water, ... no installed appliances” and “parts of the flooring were either missing or incomplete.” And then it leaked.
The Naganos tendered the defense to Evanston. The Naganos “allege the defense is limited because Evanston: allowed default to be entered against the Naganos (the default was later set aside); delayed retaining experts; and limited the ability of the Naganos’ retained counsel to perform necessary actions to advance the case.” Evanston argues that it “does not have a duty to defend or indemnify Defendants against the Hus’ claims,” as the Hus’ claims are not covered under the policy. Further, the PMX policies have an exclusion for breach of contract.
The court concluded that all of the claims made by the Hus were based in contract and therefore were outside of the terms of the Naganos insurance coverage, as the courts have "construed Hawaii law as not providing for insurance coverage for contract related claims." Therefore, Evanston does not have a duty to defend the Naganos.
Read the court’s decision…
Delaware “occurrence” and exclusions j(5) and j(6)
June 10, 2011 — CDCoverage.com
In Goodville Mut. Cas. Co. v. Baldo, No. 09-338 (D. Del. June 2, 2011), claimants condominium association and unit owners sued project developer Rehoboth and general contractor Capano seeking damages because of moisture penetration property damage to common elements and individual units resulting from construction defects. Rehoboth and Capano filed a third party complaint against insured property manager Baldo alleging that, if Rehoboth and Capano were liable to claimants, Baldo was also liable because of Baldo’s failure to properly manage, maintain, and repair the property
Read the full story…
Reprinted courtesy of CDCoverage.com
Claims Under Colorado Defect Action Reform Act Count as Suits
July 10, 2012 — CDJ Staff
The Colorado Court of Appeals has affirmed the judgment of the lower court in Melssen v. Auto-Owners Insurance. The Melssens built a custom home for the Holleys, during which time the Melssens retained a comprehensive general liability policy from Auto-Owners, which “obligated Auto-Owerns to defend the Melssens with respect to any ‘suit’ seeking damages for ‘property damage’ during the policy period.” Soon after the house was constructed, cracks developed in the drywall, then outside stucco and basement slab. The Holleys contended that “approximately $300,000 of damages to the Holleys’ property was caused by the Melssens’ engineering and construction defects” and filed a claim under the Colorado Defect Action Reform Act (CDARA). The Melssens “demanded Auto-Owners defend and indemnify the Melssens and forwared Auto-Owners the notice of claim.”
Although the Melssens notified Auto-Owners in June 2008, it was not until October 2008 that Auto-Owners denied coverage stating that the claims were sustained outside the policy period. The Melssens filed an action against Auto-Owners. At trial, the jury ruled in favor of the Melssens awarding them damages, to which the trial court added costs and attorney fees.
On appeal, Auto-Owners contended that the trial court erred in allowing the Melssens to argue that the CDARA notice of claim “was the functional equivalent of a complaint commencing a suit.” The appeals court found that “the CDARA notice of claim process constituted an alternative dispute resolution proceeding under the policy.” The court agreed that jury should not have been asked to determine if a CDARA action is a “suit,” but as the jury found for the Melssens, the concluding it “constituted harmless error.” Further, the court found that an action under the CDARA satisfied the definition of a “suit.”
The court found for the Melssens, affirming the lower court’s decision and remanding the case to the lower court for the awarding of appeals costs to the Melssens.
Read the court’s decision…