Instant Hotel Tower, But Is It Safe?
March 28, 2012 — CDJ Staff
Broad Sustainable Building has leapfrogged in China’s construction boom by building a thirty-story hotel in just fifteen days in the city of Changsha. According to an article in the Los Angeles Times, most of the building was prefabricated, but most prefabricated buildings require a longer time for assembly. Broad claimed that it cut no corners on safety. However, Zhang Li, a Beijing architect, told the Times that “incredible speed also means incredible risk.”
At the completion date, the interior was still partially finished. Some rooms were furnished, while others weren’t quite so ready. The hotel will be used to house clients who are visiting Broad and some of its employees.
Broad called their process “the most profound innovation in human history” and predicted that soon a third of new buildings worldwide would be constructed this way. The company anticipates using the same process to build taller buildings, with hopes of eventually constructing a 150-story building.
China is currently undergoing a building boom which Zhang attributed to a desire to catch up to the developed world. As a result of this boom, he noted that building inspections are often skipped in China to speed up building.
Read the full story…
Repair of Part May Necessitate Replacement of Whole
February 10, 2012 — CDJ Staff
Judge Gleuda E. Edmonds, a magistrate judge in the United States District Court of Arizona issued a ruling in Guadiana v. State Farm on January 25, 2012. Judge Edmonds recommended a partial summary judgment in favor of the plaintiff.
Ms. Guandiana’s home had water damage due to pluming leaks in September 2004. She was informed that polybutylene pluming in her house could not be repaired in parts “it must be completely replaced.” She had had the plumbing replaced. State Farm denied her claim, arguing that “the tear-out provision did not cover the cost of accessing and replacing those pipes that were not leaking.”
In September 2007, State Farm filed a motion to dismiss. The court rejected this motion, stating that “If Guadiana can establish as a matter of fact that the system that caused the covered loss included all the pipes in her house and it was necessary to replace all the pipes to repair that system, State Farm is obligated to pay the tear-out costs necessary to replace all the pipes, even those not leaking.”
In March 2009, State Farm filed for summary judgment, which the court granted. State Farm argued that “the tear-out provision only applied to ‘repair’ and not ‘replace’ the system that caused the covered leak.” As for the rest of the piping, State Farm argued that “the policy does not cover defective materials.”
In December 2011, Ms. Guadiana filed for summary judgment, asking the court to determine that “the policy ‘covers tear-out costs necessary to adequately repair the plumbing system, even if an adequate repair requires replacing all or part of the system.”
In her ruling, Judge Edmonds noted that Ms. Guadiana’s claim is that “the water damage is a covered loss and she is entitled to tear-out costs necessary to repair the pluming system that caused that covered loss.” She rejected State Farm’s claim that it was not obligated to replace presumably defective pipes. Further, she rejected State Farm’s argument that they were only responsible for the leaking portion, noting “Guadiana intends to prove at trial that this is an unusual case where repair of her plumbing system requires replacement of all the PB plumbing.”
Judge Edmonds concluded by directing the District Court to interpret the tear out issue as “the tear-out provision in State Farm’s policy requires State Farm to pay all tear-out costs necessary to repair the plumbing system (that caused the covered loss) even if repair of the system requires accessing more than the leaking portion of the system.”
Read the court’s decision…
Insurance Company Prevails in “Chinese Drywall” Case
June 17, 2011 — CDJ Staff
The Louisiana Court of Appeals rejected an appeal to reverse a summary judgment granted to Louisiana Citizens Property Insurance Company. Terrence and Rhonda Ross contracted for a remodel of their home in which Chinese-made drywall was used. When the drywall emitted harmful gasses, the Rosses filed a claim under their insurance policy. This claim was rejected under four exclusions: for faulty materials, latent defect, loss by corrosion, and loss by pollution. After the claim was denied, the Rosses sued Louisiana Citizens.
In April 2010, the lower court granted a summary judgment, followed by a May, 2010 order dismissing the Rosses’ claims against Louisiana Citizens. The Rosses appealed this decision. In the court’s review, they agreed with Louisiana Citizens and the lower court on all counts. Although the Rosses maintained that the drywall was not defective (as it still functioned as drywall), the court ruled that its emission of sulfuric gases was a defect. Further, as it was in place for two years before this became evident, it was also a latent defect. Damage to the Rosses’ home consisted of corrosion damage caused by the pollutants in the drywall.
The Rosses made an additional claim that since their policy covered smoke damage, this should be covered, as the harm was done by sulfuric gases. The court noted that the contract specifies “fumes or vapors from a boiler, furnace, or related equipment,” none of which apply in this case.
Read the court’s decision
Louisiana Politicians Struggle on Construction Bills, Hospital Redevelopment
June 16, 2011 — CDJ Staff
Louisiana politicians are still working on a compromise in the state’s construction budget, as reported in the Times-Picayune. Rob Marrianneax, the chair of the Senate Revenue and Fiscal Affairs Committee, removed a $45 million request from Governor Bobby Jindal and added $4 million for projects that Jindal vetoed last year.
Two senators have formed competing plans to fund redevelopment construction for New Orleans’s Methodist Hospital. Mitch Landrieu, the mayor of New Orleans, hoped for $30 million dollars in state bonds. Senator Cynthia Willard-Lewis proposed an amendment that would supply $1.6 million, while Senator J.P. Morrell has an amendment that would supply $4 million.
Read the full story…
Florida trigger
May 18, 2011 — May 18, 2011 - CDCoverage.com
In Johnson-Graham-Malone, Inc. v. Austwood Enterprises, Inc., No. 16-2009-CA-005750-XXXX-MA (Fla. 4th Cir. Ct. Duval County, April 29, 2011), insured JGM was the general contractor for an apartment project completed in 1998. In 2007, the project owner sued JGM seeking damages for defective construction resulting in moisture penetration property damage. JGM tendered its defense to Amerisure. Amerisure denied a defense. JGM defended and settled the underlying suit and then filed suit against Amerisure seeking recovery of defense and settlement costs. The trial court granted JGM’s motion for partial summary judgment. The court first addressed Amerisure’s duty to defend. Applying Florida law, the court held that, although the underlying complaint alleged that the property damage was not discovered until after expiration of the Amerisure policies
Read the full story…
Reprinted courtesy of CDCoverage.com
New Construction Laws, New Forms in California
July 10, 2012 — CDJ Staff
New construction laws came into effect in California on July 1. Writing for the Martindale-Hubble Legal Library, Glenn Mau, J. Michael McGuire, and John Tonsing, all of Archer Norris, discuss these changes. They note that the most important part of the changes to California construction law is that “all mechanics liens, stop notices and bond claims recorded after July 1, 2012 must use the new standardized forms and follow the new definitions, notice prerequisites and statutory release form language.”
Read the full story…
Construction Defect Case Not Over, Despite Summary Judgment
November 7, 2012 — CDJ Staff
The Supreme Court of Oregon has concluded in an en banc decision that a motion to reconsider a summary judgment is not a motion for a new trial. In coming to their conclusion the court overturned an earlier Oregon Supreme Court case, Carter v. U.S. National Bank. Although the decision does not bear on construction defects, the underlying case did. Due to the decision, these claims can now be evaluated in a trial.
The case, Association of Unit Owners of Timbercrest Condominiums v. Warren, came about after an apartment complex was converted into condominium units. The developers hired Big Al’s Construction for some of the remodeling work. The condominium association later sued the developer and the contractor over claims of construction defects. The defendants filed a motion for summary judgment, which the court granted.
But that wasn’t the end of things. The plaintiff soon filed a “motion to reconsider,” noting that the summary judgment seemed to be in conflict with both law and other recent rulings, and additionally, the grounds for the decision were not in the order. The judge then notified the parties that the court had “pulled the trigger too quickly” and had seven questions for the parties to answer.
The court dismissed all claims against the defendants. The defendants filed their responses, objecting that that “‘there is no such thing’ as a motion for reconsideration.” Further, while “the rules do allow for post-judgment review of pre-judgment rulings through a motion for a new trial,” the plaintiffs had not filed for a new trial. But did they need one? They did file an appeal.
The judge in the case admitted that there was no such thing as a motion to reconsider, and felt bad about prematurely signing the judgment. The case was sent to the Court of Appeals to determine if the motion to reconsider was a request for a new trial. The Court of Appeals concurred.
In reviewing the decision, the Oregon Supreme Court concluded that there were a maximum of three questions to address. Was the motion for reconsideration a motion for a new trial? If so, was the later notice of appeal premature? And if so, was the plaintiff required to file a new appeal? The court determined that the answer to the first question was no.
Prior decisions pointed to the conclusion “that a motion for reconsideration of a summary judgment amounts to a motion for a new trial,” but here the court concluded that “our prior cases erred,” and turned to the summary judgment rule for clarification. The court noted that “the rule contemplates that summary judgment and trial are separate and distinct events.” With this conclusion, the Oregon Supreme Court remanded the case to the Court of Appeals for further proceedings.
Read the court’s decision…
Former Zurich Executive to Head Willis North America Construction Insurance Group
March 1, 2012 — CDJ Staff
Insurance Journal reports that Sean McGroarty will be directing surety operations for their construction practice in North America. Previously, Mr. McGroarty was the senior vice president and head of international surety with Zurich Financial Services. He has also worked for Liberty Mutual Group and the St. Paul Companies.
Mr. McGroarty will be leading a team of professionals offering brokerage services for contract and commercial surety.
Read the full story…
Steps to Defending against Construction Defect Lawsuits
July 21, 2011 — CDJ Staff
Writing in Claims Journal, Bryan Rendzio notes that the decline in construction has not been matched by a decline in construction defect lawsuits over condominiums. He reviews the ways in which lawyers representing developers can help protect their clients. He identifies four important considerations in defending developers from claims of construction defects.
He advocates a careful review of the contract. “Under a breach of contract claim, the insured’s duties to the party who brought the claim against the insured flow from the contract. Commonly, construction contracts limit the scope of recoverable damages, such as by waiving consequential damages.’
The next step, according to Rendzio is to check of a settlement agreement is already in place, noting that these are “a familiar occurrence in the construction industry, regardless of any lawsuits having been filed.”
He considers the statute of repose “the single-most decisive weapon an insured possesses in its arsenal during a condo defect lawsuit.” He notes that no lawsuits can be brought for construction defects after the end specified by the statute of repose, and if a lawsuit is brought beforehand, no additional parties can be named once the statute has taken effect.
Finally, he warns adjusters to be suspicious when a condo association requests contractual indemnification. He notes that the pitfall in this is that developers and the subsequent condominium association often have similar names, given the theoretical example of a condo project built by “Fake Lakes LLC” and later run by the “Fake Lakes Condominium Association.” Writing in regards to Florida law, he notes that condominium associations do not have successor interest in contracts developers made with contractors.
Read the full story…
There is No Non-Delegable Duty on the Part of Residential Builders in Colorado
August 2, 2012 — Brady Iandiorio, Higgins, Hopkins, McLain & Roswell, LLC
Recently, in the Arapahoe District Court, the Honorable Michael Spear, issued an order holding that builders do not owe a non-delegable duty to homeowners. In Marx and Corken v. Alpert Custom Homes, Inc., et al., Judge Spear’s order came in response to plaintiffs’ motion for determination of question of law seeking a finding that the defendants owed a non-delegable duty to the plaintiffs and thus, to strike defendants’ designation of nonparties at fault. After being fully briefed, Judge Spear, found that such a non-delegable duty does not exist.
The case arises from the construction of a single-family residence in Aurora, Colorado. Through the construction and interaction with Alpert Custom Homes, Inc. and Scott and Sally Alpert, the defendants, Paul Marx and Kay Corken, the plaintiffs claimed they suffered various damages and losses, and brought claims for breach of contract-warranty, breach of contract, violation of the Colorado Consumer Protection Act, breaches of the implied covenant of good faith, promissory estoppel, willful breach of contract, and quantum meruit. During litigation, the defendants filed a designation of nonparties at fault, which named several parties which were at fault for the alleged construction defects at issue in the case. The pertinent nonparties named were subcontractors of defendant Alpert Custom Homes, Inc. during the construction of the residence.
Read the full story…
Reprinted courtesy of Brady Iandiorio, Higgins, Hopkins, McLain & Roswell, LLC. Mr. Iandiorio can be contacted at iandiorio@hhmrlaw.com
Kentucky Court Upholds Arbitration Award, Denies Appeal
June 15, 2011 — CDJ Staff
The Kentucky Court of Appeals has ruled in Lake Cumberland Community Action Agency v. CMW, Inc. affirming the arbitration award. CMW, Inc. was responsible for the construction of a facility to be used for pre-school students and the housing of Alzheimer patients and senior citizens. An agreement was made that any disputes would be heard by an arbitrator selected by the construction industry.
The plaintiff alleged that there were design and construction defects in the building trusses, violation of the Kentucky Building Code, and problems with the HVAC system. The arbitrator awarded $106,000 to the plaintiff which then sought to vacate the award. The circuit court upheld the arbitrator’s decision.
The Court of Appeals found that there was no basis for rejecting the arbitrator’s decision, noting “there is nothing to show that there was any fraud or bias on the part of the arbitrator.” The appeals court, with all three judges concurring, upheld the arbitration award.
Read the court’s decision
Surveyors Statute Trumps Construction Defect Claim in Tennessee
June 19, 2012 — CDJ Staff
The Tennessee Court of Appeals has issued an opinion in the case of Dale v. B&J Enters. (Tenn. App., 2012), affirming the ruling of the Chancery Court for Knox County. The homeowners purchased properties in Knoxville, Tennessee in 2007 and 2008. Subsequently, according to the complaint, they found “significant sink holes and depressions throughout the subdivision.” The plaintiffs determined that a previous developer in 2004 had been aware of the sink holes. The Knox County Metropolitan Planning Commission, upon giving approval, made requirements that included that sink holes, even if they were filled, had to be designated on the site plans. The developer did not indicate these locations on the final plans. The plaintiffs made claims of “failure to disclose, misrepresentation, misrepresentation by concealment, and violation of the Tennessee Consumer Protection Act.” They filed their suit in June 2009.
The defendants in the initial case, argued that they did not create the final plat, the site plan indicating the features and lot lines. This had been the work of the previous developer. In September, 2009, the plaintiffs amended their complaint to include the previous developer and its engineering firm. The engineering firm disavowed any responsibility. The developer noted that the surveyor, Benchmark Associates, had “failed to properly include the sink holes and/or depressions on the final plat.” In June, 2010, the plaintiffs added Benchmark.
Benchmark argued that the plaintiffs’ claims should be dismissed, as Tennessee has a four-year statute of limitations on claims against surveyors. The final plat was recorded on May 19, 2006, and the plaintiff filed their claims against Benchmark on June 16, 2010, slightly less than a month over four years. The plaintiffs argued that “the real issue [was] the tortious misrepresentation by Benchmark.” The Chancery Court found for Benchmark.
On appeal, the plaintiffs raised three issues. They argued that the trial court applied the wrong section of the law, and should have applied the section applying to construction and not surveyors. They also argued that the timeliness of the claim should be based on when the defects were discovered. The also raised the question of whether the laws concerning surveyors bar claims for misrepresentation. The appeals court upheld the decision of the Chancery Court.
For the plaintiff’s first claim, although the statute addressing deficiencies in construction mentions surveying, an earlier court ruling found that the legislature had removed a reference to surveyors in one part of the statute, but failed to do so in the second part. The earlier court had concluded that the “obvious intent of the legislature was to place all limits on actions against surveyors into the new statute.” As the applicable statute states that “any such action not instituted within this four (4) year period shall be forever barred,” the court held that the plaintiffs’ claims must be time barred. Further, as the intent of the legislature was determined to “place all limits on actions against surveyors into one statute,” the court felt that it could not apply the Consumer Protection Act.
Read the court’s decision…
Court Clarifies Sequence in California’s SB800
December 20, 2012 — CDJ Staff
As California’s Right-To-Repair law, SB800, nears its ninth birthday, it has remained “largely untested in the legal system” as noted by Megan MacNee of Wood, Smith, Henning & Berman LLP on the site RealEstateRama. She writes that some homeowners have requested documents prior to filing a claim, which she describes as an attempt to “game the system,” and “analogous to requiring a party to litigation to comply with discovery before a complaint is filed.”
The court determined that homeowners may not request documents from the builder until they have actually filed a claim. The court noted that SB800 lacks any clear indication that homeowners may request documents before filing a claim (and also does not indicate that a builder would have to provide documents in these circumstances). The court concluded that the section that sets up the prelitigation procedures occurs before they section on documents discovery.¬? “Because the document request is part of the prelitigation procedure, and the prelitigation procedure does not begin until the homeowner has served notice of a claim, it follows that there can be no prelitigation obligation to produce documents under section 912, subdivision (a) unless the homeowner has commenced the prelitigation procedure by serving notice of a claim.”
Read the full story…
When Does a Claim Against an Insurance Carrier for Failing to Defend Accrue?
November 7, 2012 — David McLain, Colorado Construction Litigation
The following is an update on our December 20, 2010 article regarding United States Fire Insurance Company v. Pinkard Construction Company, Civil Action No. 09-CV-01854-MSK-MJW, and its underlying dispute, Legacy Apartments v. Pinkard Construction Company, Case No. 2003 CV 703, Boulder County Dist. Ct. That article can be found here.
The present action, St. Paul Fire and Marine Insurance Co., et al. v. The North River Insurance Co., et al., Civil Action No. 10-CV-02936-MSK-CBS, encompasses the coverage battle that ensued between Pinkard’s insurers, Travelers Indemnity Company of America (“Travelers”) and United States Fire Insurance Company (“USFI”), following the settlement of Legacy’s construction defect claims against Pinkard. A short history of the underlying facts is as follows:
In 1995, Pinkard constructed the Legacy Apartments housing complex in Longmont, Colorado. Following construction, Legacy notified Pinkard of water leaks associated with various elements of construction. Legacy ultimately filed suit against Pinkard in 2003, and would go on to clarify and amend its defect claims in 2004, 2006, and again in 2008. Following Pinkard’s notification of Legacy’s claims, USFI provided a defense to Pinkard, but Travelers refused to do so, on the purported basis that Legacy’s allegations did not implicate property damage under the terms of Travelers’ policy.
Read the full story…
Reprinted courtesy of David M. McLain, Higgins, Hopkins, McLain & Roswell, LLC. Mr. McLain can be contacted at mclain@hhmrlaw.com
After $15 Million Settlement, Association Gets $7.7 Million From Additional Subcontractor
November 7, 2012 — CDJ Staff
The stucco subcontractor for a condominium complex did not join in with the other defendants in a settlement of more than $15 million, preferring to take the case to a jury trial. That jury has found the stucco installer liable for $7.7 million to make repairs. Mark Wiechnik of Herrick Feinstein LLP wrote about the case on the Lexology web site. Mr. Wiechnik notes that the jury was shown “samples of rotted wood taken from the property as well as numerous pictures of damage resulting from the various defects.”
Read the full story…
Appropriation Bill Cuts Military Construction Spending
June 15, 2011 — CDJ Staff
The Hill reports that HR 2055, the Military Construction, Veterans Affairs (VA) and Related Agencies bill, has passed with only five votes in opposition. The bill cuts the budget for military construction spending by $2.6 billion due to anticipated base closures.
The bill includes $186 million for family housing construction by the Army, $100 million for family housing construction by the Navy and Marines, and $84 million for family construction by the Air Force, with an additional $50 million allocated for the DOD outside the military branches. By the act, these funds will remain available until September 30, 2016.
Read the full story…
Read HR 2055
Georgia Law: “An Occurrence Can Arise Where Faulty Workmanship Causes Unforeseen or Unexpected Damage to Other Property”
March 5, 2011 — By
CDCoverage.com, March 5, 2011
In American Empire Surplus Lines Ins. Co. v. Hathaway Development Co., Inc., No. S10G0521 (Ga. March 7, 2011), insured plumbing subcontractor Whisnant was sued by general contractor Hathaway seeking damages for costs incurred by Hathaway in repairing damage to property other than Whisnant’s plumbing work resulting from Whisnant’s negligently performed plumbing work on three separate projects. On one project, Whisnant installed a pipe smaller
Read the full story...Reprinted courtesy of CDCoverage.com
Nevada Budget Remains at Impasse over Construction Defect Law
June 1, 2011 — CDJ Staff
Negotiations for the Nevada state budget have stalled over proposals to amend the state’s construction defect laws. Assembly Republicans had offered changes to the law to make it friendlier to contractors; however, after a state Supreme Court ruling that the state could not move a local government entity’s funds into state coffers, pressure has increased on the governor to lift the expiration dates of taxes approved in 2009.
The Reno Gazette-Journal quotes John Madole, a construction industry lobbyist, “We agree with them that you have to address the issue of the attorney fees, and for all practical purposes, they are automatically awarded when anybody brings any kind of suit.”
Speaker of the Assembly, John Oceguera, a Democrat, has proposed a bill that “makes it absolutely crystal clear that the only time you get attorney's fees is if you're the prevailing party.”
Read the full story…