California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 — CDJ Staff
The California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Record-Setting Construction in Fargo
November 7, 2012 — CDJ Staff
Prairie Business reports that Fargo is experiencing the most new construction it has ever seen, totaling $434 million in value, which exceeds the previous high in 2006 of $428 million. Many of the construction starts are for single family homes, although there is also an increase in construction of apartments and townhomes.
The Home Builders Association of Fargo-Moorhead also noted that there was also a large of remodeling projects. Terry Becker, the president of the HBA, said that “remodeling is just huge right now.”
Read the full story…
Building Boom Leads to Construction Defect Cases
August 2, 2012 — CDJ Staff
Professor Evan McKenzie of the University of Illinois at Chicago says that rise of construction defect litigation in the Las Vegas area followed the same pattern it did in other places, according to an article in the Las Vegas Review Journal. “Step one,” according to Professor McKenzie, “there was this enormous growth in construction. Then these attorneys began to swarm in from all over, especially Southern California.” McKenzie noted that during a building boom, construction “outpaces the ability of building inspectors to do their job.”
But, despite his contention that “rapid growth in housing stock” leads to “shoddy construction,” another problem of growth was that “eventually there were too many lawyers chasing too many condominium complexes and subdivisions.” What came next was that “attorneys start coming up with cases that really aren’t good cases.” It’s in the interest of these attorneys that HOA boards sue.
Read the full story…
State Audit Questions College Construction Spending in LA
August 17, 2011 — CDJ Staff
A state audit of the Los Angeles Community College District found many problems with their construction spending. Their report, as described in the Los Angeles Times, found construction money spent for other purposes, such as promotional photography and public relation tours, $28.3 million spent on projects that were later cancelled, and oversight committees that provided no oversight.
Earlier this year, the LA Times ran a series of articles detailing problems with the Los Angles Community College District’s construction program. The LA Times reported that the State Controller’s audit reached many of the same conclusions.
The Community College District disputed the findings.
Read the full story…
Hawaii State Senate Requires CGL Carriers to Submit Premium Information To State Legislature
March 20, 2011 — March 20, 2011 Construction Defect Journal Staff
In light of the decision in Hawaii’s Intermediate Court of Appeals in Group Builders, Inc.,v. Admiral Insurance Company, 231 P.3d 67(2010), Hawaii’s state senate is requesting that "every domestic and foreign insurance company that has ever issued commercial general liability policies in the State is requested to submit information to the Legislature on the total premiums received for their commercial general liability policies during the past ten years"
Read Full Text of Hawaii State Senate Resolution
Builder to Appeal Razing of Harmon Tower
August 2, 2012 — CDJ Staff
An attorney for Tutor Perini, George Ogilvie, has said that he will appeal to the state Supreme Court to stop Clark County District Court Judge Elizabeth Gonzalez’s ruling from taking effect. She has given the go-ahead to MGM Resorts and CityCenter to implode the building. Ogilvie described the demolition as “a do-over at Perini’s expense” in protesting Gonzalez’s order. Gonzalez has said that she will instruct jurors that the demolition was an admission that the building was badly built. Ogilvie says this is “allowing MGM to bury its mistakes.”
MGM claims that it is only following the directive of county safety officials. “When Clark County demanded that CityCenter abate the potential hazard created by faulty construction at the Harmon, we determined that demolition is the surest, safest and fasted way to do so.”
Read the full story…
Arizona Contractor Designs Water-Repellant Cabinets
September 9, 2011 — CDJ Staff
Dubbing his product “Baltic Duck,” a Mesa, Arizona building contractor is offering household cabinets made with specially treated water-repellent plywood instead of the usual particle board. Pete Celano calls his product Baltic Duck because the plywood is made in the Baltic region of Eastern Europe. To further protect the cabinets from moisture, a silicone-based sealant is applied to the corners and edges.
Celano’s cabinets use standard decorative fronts. The design of the cabinets allows spilled liquids to drain away without encountering the decorative wood.
Read the full story…
Defense for Additional Insured Not Barred By Sole Negligence Provision
August 11, 2011 — Tred Eyerly, Insurance Law Hawaii
A general contractor was entitled to a defense as an additional insured when the underlying complaint did not allege it was solely negligent. A-1 Roofing Co. v. Navigators Ins. Co., 2011 Ill. App. LEXIS 656 (Ill. Ct. App. June 24, 2011).
A-1 was the general contractor for a roof resurfacing job at a high school. Jack Frost Iron Works Inc. (“Frost”) was one of A-1’s subcontractors. Frost had a CGL policy with Navigators Insurance Company under which A-1 was an additional insured.
An employee of Frost’s subcontractor Midwest Sheet Metal Inc. was killed at the job site when a boom-lift he was operating flipped over. The boom-lift had been leased by another Frost subcontractor, Bakes Steel Erectors, Inc. (BSE). The deceased's estate filed suit against A-1, BSE and two other defendants.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
No Duty to Indemnify When Discovery Shows Faulty Workmanship Damages Insured’s Own Work
November 7, 2012 — Tred Eyerly, Insurance Law Hawaii
Our post last week addressed the duty to defend when alleged faulty workmanship caused loss to property adjacent to where the insured was working. See Pamerin Rentals II, LLC v. R.G. Hendricks & Sons Constr., Inc., 2012 Wis. App. LEXIS 698 (Wis. Ct. App. Sept. 5, 2012) [post here]. Today, we report on recent developments in the same case where the court determined, despite earlier finding the insurer owed a defense, it had no duty to indemnify. Pamperin Rentals II, LLC v. R.G. Hendricks & Sons Constr., Inc., 2012 Wisc. App. LEXIS 793 (Wis. Ct. App. Oct. 10, 2012).
Hendricks contracted to “prepare the site and supply and install concrete, tamped concrete, and colored concrete” at several service stations. The owner sued Hendricks, alleging the concrete “was defective and/or the work performed was not done in a workman-like manner and resulted in damages, and will require replacement.”
Pekin Insurance Company agreed to defend Hendricks subject to a reservation of rights.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
California Supreme Court Binds Homeowner Associations To Arbitration Provisions In CC&Rs
September 13, 2012 — Stephen A. Sunseri and Aarti Kewalramani, Gatzke Dillon & Ballance LLP (http://www.gdandb.com).
The California Supreme Court ruled in Pinnacle Museum Tower Assn. v. Pinnacle Market Development (August 16, 2012, S186149) __ Cal.4th __ [2012 WL 3516134], that arbitration provisions within the covenants, conditions, and restrictions (“CC&Rs”) for condominium projects are enforceable against their homeowner associations. The ruling — two years in the making — was based on legislative history of laws governing common interest developments, and decades of decisional authority involving contracts and arbitration provisions.
In Pinnacle, a homeowners association sued a condominium builder for construction defects and resultant property damage to the common areas, and to the separate property interests held by the individual members. The builder moved to compel arbitration, based on a provision contained in the CC&Rs which required resolution of all construction disputes through binding arbitration. The association argued it could not be compelled to arbitrate these claims because it was not a party to the agreement to arbitrate, asserting “the Association did not bargain with [the builder] over the terms of the Project CC&R's or participate in their drafting.”
The Supreme Court rejected the association's argument on the grounds that the builder-authored CC&Rs complied with the Davis-Stirling Act (“the Act”) (Civil Code §1350, et seq.) ? the law that governs all common interest developments in California. Under the Act, builders and sellers of common interest residential units are required to provide a copy of the CC&Rs to all purchasers, as well as copies of the Department of Real Estate's public report, which informs purchasers of their rights and remedies as members of the association, and encourages each prospective purchaser to review the terms carefully before entering into any agreement. Further, the Act states all CC&Rs are enforceable, unless unreasonable, and inure to the benefit of and bind all owners in the development. (Civ. Code, §1354, subd. (a).) The Court found each owner who purchased a condominium in the project either expressly consented to the terms and provisions of the CC&Rs or was deemed to have consented to the terms at the time of purchase.
The Court also did not find the arbitration provision to be unconscionable. The Court indicated the provision was drafted and recorded in accordance with the Act, which allowed each prospective purchaser to make an informed decision prior buying a condominium unit. The provision also limited arbitration to construction defect disputes. The Court did not find any evidence the provision “shocked the conscience” or was “oppressive” in any way.
Pinnacle settles a decades-long conflict over whether arbitration provisions in CC&Rs for condominium projects are enforceable against homeowner associations and their members. It remains unclear, however, whether Pinnacle’s rationale will be applied to cases involving homeowner associations for single-family residences (as opposed to condominiums), assuming those CC&Rs have similar arbitration requirements. Regardless, the result of Pinnacle is clear, if arbitration provisions contained in condominium CC&Rs meet the fairness and unconscionability tests set out by the Court, more condominium construction defect cases brought by homeowner associations will be resolved through the arbitration process.
Read the court’s decision…
Printed courtesy of Stephen A. Sunseri and Aarti Kewalramani, Gatzke Dillon & Ballance LLP. Mr. Sunseri can be contacted at ssunseri@gdandb.com and Ms. Kewalramani can be contacted at akewalramani@gdandb.com.
Limiting Plaintiffs’ Claims to a Cause of Action for Violation of SB-800
November 18, 2011 — Samir R. Patel, Esq. and Todd E. Verbick, Esq., Lorber, Greenfield & Polito, LLP
There has been a fair share of publicity about the SB-800 amendments to the Civil Code (Civil Code section 896, et seq.) that codified construction defect litigation in 2002. Most of the publicity is geared toward the pre-litigation standards allowing a builder the right to repair before litigation is commenced by a homeowner. Less focus and attention has been given to the fact that violation of the SB-800 performance standards is being used by plaintiff’s counsel as an additional tool in the plaintiff’s pleading tool box against builders. Closer scrutiny to SB-800 reveals that those provisions should in fact act as a limitation to the pleading tools available to plaintiffs and an additional tool for builders in the defense of cases governed by SB-800.
The typical construction defect complaint contains the boiler plate versions of numerous causes of action. These causes of action include Strict Liability, Negligence, Negligence Per Se, Breach of Contract, Breach of Contract – Third-Party Beneficiary, Breach of Express Warranties, Breach of Implied Warranties, among others. The wide array of causes of action leave a defendant “pinned to the wall” because they require a complex defense on a multitude of contract and tort related causes of action. Furthermore, the statutes of limitations as to these claims widely differ depending upon if the particular defect is considered latent or patent. The truth of the matter remains, no matter what the circumstances, if a construction defect matter ultimately goes to trial, it is inevitable that plaintiffs will obtain a judgment on at least one of these causes of action.
On its own, the Strict Liability cause of action can be a thorn in a defendant’s side. A builder is obviously placing a product into the stream of commerce and strict liability is a tough standard to defend against, particularly when it concerns intricate homes comprised of multiple components that originally sold for hundreds of thousands of dollars. A Negligence cause of action can also be difficult to defend because the duty of care for a builder is what a “reasonable” builder would have done under the circumstances. An interpretation of this duty of care can easily sway a jury that will almost always consist of sympathetic homeowners. A Negligence Per Se cause of action can also leave a defendant vulnerable to accusations that a builder violated the Uniform Building Code or a multitude of other obscure municipal construction-related code provisions during the construction of the home. Lastly, the Breach of Contract cause of action leaves a builder relying on dense and intricate purchase and sale agreements with dozens of addenda which leave the skeptical jurors turned off by what they view as one-side, boilerplate provisions. Ultimately, when a matter is about to go to trial, the complexity of these complaints can benefit a plaintiff and increase a plaintiff’s bargaining power against a defendant who is attempting to avoid a potentially large judgment.
Enter the SB-800 statutes. The SB-800 statutes apply to all homes sold after January 1, 2003. Civil Code section 938 specifically states that “[t]his title applies only to new residential units where the purchase agreements with the buyer was signed by the seller on or after January 1, 2003.” (Civil Code §, 938.) As time progresses, more residential construction defect cases will exclusively fall under the purview of SB-800. Slowly but surely more SB-800 governed litigation is being filed, and its exclusive application is looming on the horizon.
On its surface, this “right to repair” regime has left builders with a lot to be desired despite the fact that it is supposed to allow the builder the opportunity to cure any deficiencies in their product before litigation can be filed by potential plaintiffs. However, the application of the time line for repair has shown to be impractical for anything but the most minor problems involving only small numbers of residential units. Moreover, the fact that the fruits of the builder’s investigation into the claimed defects in the pre-litigation context can freely be used as evidence against it in litigation makes builders proceed with trepidation in responding with a repair. For these reasons, more SB-800 litigation can be expected to result due to the shortcomings of the pre-litigation procedures, and savvy defense counsel should anticipate the issues to be dealt with in presenting the defense of such cases at trial.
This fact should not necessarily be met with fear or disdain. Within the SB-800 statutes, the legislature made it clear that they were creating a new cause of action for construction defect claims, but it further made it clear that this cause of action is a plaintiff’s exclusive remedy. The legislature giveth, but at the same time, the legislature taketh away. Throughout numerous provisions within the SB-800 statutes, the Civil Code states that claims for construction defects as to residential construction are exclusively governed by the Civil Code, and that the Civil Code governs any and all litigation arising under breaches of these provisions. Civil Code section 896 specifically states:
In any action seeking recovery of damages arising out of, or related to deficiencies in, the residential construction … the claimant’s claims or causes of action shall be limited to violation of, the following standards, except as specifically set forth in this title. (Civil Code §, 896.)
Civil Code section 896 then provides approximately fifty-plus standards by which a construction defect claim is assessed under that provision. Civil Code section 896 covers everything from plumbing to windows, and from foundations to decks, and in several instances expressly dictates statutes of limitations as to specific areas of construction that severely truncate the 10-year latent damage limitations period. As for any construction deficiencies that are not enumerated within Civil Code section 896, Civil Code section 897 explicitly defines the intent of the standards and provides a method to assess deficiencies that are not addressed in Civil Code section 896. Civil Code section 897 states:
Intent of Standards
The standards set forth in this chapter are intended to address every function or component of a structure. To the extent that a function or component of a structure is not addressed by these standards, it shall be actionable if it causes damage. (Civil Code §, 897.)
Therefore, Civil Code section 897 acts as a catch-all by which defects that are not covered within Civil Code section 896 can be evaluated on a damage standard mirroring the Aas case (damages must be present and actual). The result of sections 896 and 897 being read in combination is a comprehensive, all-inclusive set of performance standards by which any defect raised by Plaintiffs can be evaluated and resolved under a single SB-800 based cause of action.
Civil Code section 943 makes clear that a cause of action for violation of SB-800 performance standards is a plaintiff’s sole remedy for a residential construction defect action. Specifically, Civil Code section 943 states:
Except as provided in this title, no other cause of action for a claim covered by this title or for damages recoverable under 944 is allowed. In addition to the rights under this title, this title does not apply to any action by a claimant to enforce a contract or express contractual provision, or any action for fraud, personal injury, or violation of a statute. (Civil Code §, 943.)
Civil Code section 944 provides the method for computing damages within a construction defect action, as follows:
If a claim for damages is made under this title, the homeowner is only entitled to damages for the reasonable value of repairing any violation of the standards set forth in this title, [and] the reasonable cost of repairing any damages caused by the repair efforts… . (Civil Code §, 944.)
A cursory review of these statutes yields the conclusion that the legislature was attempting to create an exclusive cause of action that trumps all other causes of action where SB-800 applies. The remedy available to plaintiffs is limited to that allowed by the Civil Code. As noted above, “[n]o other cause of action for a claim covered by this title…is allowed.” (Civil Code §, 943.) Therefore, Civil Code sections 896, 897, 943, and 944 specifically prohibit the contract-based and tort-based causes of action typically pled by plaintiffs.
Plaintiff’s counsel has seized upon the language of section 943 to advance the argument that SB-800 still allows a plaintiff to advance typical contract and tort based causes of action. On the surface, this argument may seem compelling, but a minimum of scrutiny of the express language of section 943 dispels this notion. Section 943 says that it provides rights “[i]n addition” to those under the SB-800 Civil Code provisions. Clearly, the language in section 943 is intended to expressly underscore the fact that a plaintiff is not precluded from seeking relief in addition to that allowed under SB-800 for damages not arising from a breach of the SB-800 standards or for damages in addition to those recoverable under Section 944. This language does not provide an unfettered license to bring a Strict Liability, Negligence or other cause of action against a builder where SB-800 applies.
In fact, this language only keeps the door open for plaintiffs to pursue such causes of action not arising from a breach of the SB-800 standards should there be such supporting allegations. For example, if a plaintiff alleges that a builder breached an “express contractual provision” related to the timing of the completion of the home and close of escrow, and the contract specifies damages in this regard, a plaintiff may have a viable separate cause of action for Breach of Contract for recovery of those damages precisely because that is not an issue expressly dealt with in SB-800 in the performance standards under sections 896 and 897, or in the damage recovery terms under 944. As it stands, the vast majority of complaints are seeking redress for violation of the same primary right; that is, defects specifically outlined in Section 896 and 897 or which result in damages as stated in Section 944.
So, how does a builder defend against a complaint that contains multiple causes of action regarding construction defects for a home sold after January 1, 2003? There are numerous ways to approach this. First and foremost, these superfluous and improper causes of action can be attacked by demurrer seeking dismissal of all causes of action other than the cause of action alleging violation of SB-800. If the the time period within which to file a demurrer has passed already, a motion for judgment on the pleadings can be utilized to attack the improper causes of action in the same way as a demurrer can be used for this purpose.
The limitation to a demurrer or motion for judgment on the pleadings is that the judge is restricted to viewing only the four corners of the pleading when making a ruling. It is typical for plaintiffs’ counsel to cleverly (or one might even say, disingenuously) leave the complaint purposely vague to avoid a successful defense attack on the pleadings by not including the original date the residence was sold. In that instance, a motion for summary adjudication can be used to attack a plaintiff’s complaint. By simply providing evidence that the homes were originally sold after January 1, 2003, the improper causes of action should be subject to dismissal by summary adjudication. If the plaintiff is a subsequent purchaser, the builder still has recourse to enforce the pleading limitations under SB-800. Civil Code section 945 states that “[t]he provisions, standards, rights, and obligations set forth in this title are binding upon all original purchasers and their successors-in-interest.” (Civil Code §, 945.)
Attacking a plaintiff’s complaint to eliminate multiple causes of action can have numerous benefits. The practical result is that a plaintiff will only have one viable cause of action. The advantage is that the SB-800 performance standards include the defined performance standards and shortened statutes of limitations periods with regard to specific issues. Furthermore, as to defects which are not specifically provided for in Civil Code section 896, Civil Code section 897 requires a proof of actual damages. Therefore, a plaintiff must provide evidence of current damages and not simply conditions that may potentially cause damage in the future.
The Appellate Courts have yet to directly address and interpret these SB-800 provisions. The time for that is undoubtedly drawing near. For now, however, plaintiffs will have to find ways to accurately plead construction defect claims within the confines of one cause of action for breach of the performance standards enumerated within the Civil Code.
Printed courtesy of Lorber, Greenfield & Polito, LLP. Mr. Patel can be contacted at spatel@lorberlaw.com and Mr. Verbick at tverbick@lorberlaw.com.
Green Buildings Could Lead to Liabilities
March 28, 2012 — CDJ Staff
Attempts to build “green,” reducing energy costs and increasing the use of sustainable building materials, may lead to more lawsuits, according to a report issued by the British Columbia Construction Association. The report warned those who were going to build green look into the implications. The report looked at the result of green building practices and requirements adopted in the United States.
The report warns that “the use of novel, less harmful building material or new construction techniques may give rise to liability due to: contractor inexperience with installation; lack of long-term evaluation of green materials; lack of understanding of how new building materials may impact existing traditional building systems; or warranties provided unintentionally about the durability or effectiveness of unproven materials or techniques.”
Manley McLachlan, president of the BCAA noted that they are aware of “legal action around the performance of the buildings,” noting that while fast-growing trees help toward LEED certification, their wood is more prone to mold. He also felt that low-VOC paints needed more testing to prove their durability as exterior finishes.
Read the full story…
Arbitration Clause Found Ambiguous in Construction Defect Case
October 28, 2011 — CDJ Staff
The California Court of Appeals ruled on September 28 in the case of Burch v. Premier Homes. Ms. Burch bought a home after negotiating various addendums to the contract. The contract was a standard California Association of Realtors contract to which both the buyer and seller made additions. At issue in this case was paragraph 17 of the contract which included that “Buyer and Seller agree that any dispute or claim in Law or equity arising between them out of this Agreement or resulting transaction, which is not settled through mediation, shall be decided by neutral, binding arbitration.”
The seller/defendant’s Addendum 2 “included provisions relating to the arbitration of disputes that may arise.” Ms. Burch’s realtor, Lisa Morrin, told Burch that “she had never seen a proposed contractual provision that would require a home buyer to agree to arbitrate with a builder over construction defects.” Ms. Burch told Morrin that she did not want to buy the property if she would have to give up her rights under California law.
As part of Addendum 2, the buyer had to buy a warranty from the Home Buyers Warranty Corporation. The sale was held up for a while, as Ms. Burch waited for a copy of the warranty. When she received it, she took further exception to Addendum 2. Scott Warren of Premier Homes said he could not sell the property without Addendum 2. Ms. Burch told her realtor that despite the claims made by Mr. Warren that this was for her benefit, she felt it was more to the benefit of Premier Homes. Don Aberbrook of HBW agreed to the clause, contained in the final sentence of Addendum 2, being struck.
Subsequent to buying the home, Burch submitted a claim concerning construction defects. HBW denied the claim and Burch began an action against the defendants. Premier filed a motion to compel arbitration which Burch opposed.
The trial court ruled that the striking out of the arbitration clause at the end of Addendum 2 “created a conflict with respect to the parties’ intent as to the scope of arbitration.” The trial court found that “the parties’ intention was to preserve Burch’s right to make state law claims including her right to a jury trial for any non-warranty claims against the builder.”
The appeals court in their ruling looked at the standard of review and concluded that the purchase agreement was ambiguous and that extrinsic evidence was required to resolve that ambiguity. As the contract contained contradictory provisions as to whether or not arbitration was required, it was necessary for the trial court to examine these claims. The appeals court found that the evidence supported the conclusions of the trial court.
Finally, the appeals court found that “there was no valid agreement to arbitrate disputes.” The court noted that arbitration can only happen by mutual consent and “it is clear that Burch did not enter into an agreement to arbitrate any construction defect disputes she might have.”
Read the court’s decision…
Godfather Charged with Insurance Fraud
July 1, 2011 — CDJ Staff
Texas-based Godfather Construction is a recipient of a fraud suit from the Cook County state attorney’s office. The firm incorporated in Illinois in April 2010, moving there to do business after storms damaged homes in the Chicago suburbs, according to a report in the Chicago Tribune. The state attorney alleges that Godfather brought unlicensed out-of-state workers and the work they performed was “incomplete or shoddy.” Godfather is claimed to have received about $60,000 from Illinois homeowners. The prosecutors are seeking restitution for Godfather’s clients and seek to forbid the firm from doing business in Illinois.
Read the full story…
Court Will Not Compel Judge to Dismiss Construction Defect Case
August 2, 2012 — CDJ Staff
The Fourteenth Court of Appeals of Texas has denied a petition for a writ of mandamus. The parties involved, Bonner Ball, Thomas Zenner, and Rallin Welch, are lmited partners of Black Diamond Builders, LLP. Black Diamond is the recipient of a lawsuit from Grier and Camille Patton, for whom Black Diamond built a home. The Pattons are alleging construction defects.
The Black Diamond partners argue that Judge Jeff Shadwick, presiding judge of the 55th District Court of Harris County, Texas should have granted their motion to dismiss. They sought to have the Fourteenth Court of Appeals compel that action.
The Black Diamond Partners claims that “the homowners failed to satisfy statutory prerequisites before filing suit, and dismissal of the suit was automatic under the applicable statues in effect at the time the Pattons noticed alleged defects in their home.”
The court noted that “a trial court will be held to have abused its discretion only if the party requesting mandamus relief establishes that the trial court could have reached but one decision.” The court did not concur with this and denied the petition for a writ of mandamus.
Read the court's decision…
Supreme Court of New York Denies Motion in all but One Cause of Action in Kikirov v. 355 Realty Assoc., et al.
April 28, 2011 — April 28, 2011 Beverley BevenFlorez - Construction Defect Journal
In the construction defect suit Kikirov v. 355 Realty Associates, LLC, et al., the Supreme Court of the State of New York granted a dismissal of the plaintiff’s fourth cause of action, but denied the defendants’ motion in all other respects. The plaintiff alleged breach of contract, among other claims. “355 Realty was the sponsor of 355 Kings Highway Condominium, a condominium project located at 355 Kings Highway, in Brooklyn, New York. The condominium units were allegedly marketed as ‘ultra luxury condos,’ and a ‘Manhattan style condominium building,’ which would be the ‘epitome of luxury and quality.’ The construction of the six-story 28 unit residential condominium building began in approximately November 2003. […] Plaintiff entered into a purchase agreement, dated December 21, 2005, with 355 Realty (which was executed on behalf of 355 Realty by Michael Marino, as its member) for the purchase of Unit 2G in the building.”
The plaintiff alleged that construction defects emerged soon after moving into the unit: “After taking occupancy of his condominium unit, plaintiff allegedly experienced serious leakage and moisture problems in his unit, which caused a dangerous mold condition to develop, in addition to causing actual damage to the structural elements of his unit. According to plaintiff, the walls, moldings, and wood floors of his unit are constantly wet and moist, and there is severe buckling of the wood floors. Plaintiff claims that these problems have caused his unit to be uninhabitable. Plaintiff alleges that he has been forced to remove all of his personal belongings from his unit and has been unable to occupy his unit.”
According to the plaintiff, Foremost attempted to repair the defects, but only made the situation worse: “Specifically, plaintiff asserts that Foremost’s contractors opened his walls to remove the stained drywall, but never corrected the cause of the leaks, destroyed the walls, and never properly taped and painted the sheet rock. Plaintiff alleges that Foremost repaired the openings in a defective manner. Plaintiff also claims that his floor was repaired at that time by a subcontractor hired by Foremost, but the basic structural problem was never resolved and the leaks continued, compromising the beams and causing the mold conditions, in addition to all of the physical damage present in the unit. On or about July 16, 2009, plaintiff allegedly sent a notice of the defects to 355 Realty and to the managing agent designated by the condominium board, by certified mail, return receipt requested. Plaintiff asserts that defendants have failed and refused to repair and remedy the defective condition, and that the damage is extensive and requires major structural repairs.”
The plaintiff filed suit on May 4, 2010, and the original complaint asserted eight causes of action. “By decision and order dated September 13, 2010, the court granted a motion by defendants to dismiss plaintiff’s second cause of action for breach of implied covenants of good faith and fair dealing, his third cause of action for breach of implied warranties, his fifth cause of action for negligence as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his seventh cause of action for negligence as against Vision, Foremost, and MMJ, and his eighth cause of action for violations of General Business Law § 349 and § 350, and granted plaintiff leave to replead his first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his fourth cause of action for breach of statutory warranties, and his sixth cause of action for breach of contract as against Vision, Foremost, and MMJ.”
The plaintiff amended their complaint on October 18, 2010, and “has repleaded these three causes of action by asserting a first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, a second cause of action for breach of statutory warranties, and a third cause of action for breach of contract as against Vision, Foremost, and MMJ. In addition, plaintiff, in his amended complaint, has added a fourth cause of action for fraud.”
The defendants, on the other hand, “argue that each of the four causes of action alleged by plaintiff in his amended complaint fail to state a claim upon which relief may be granted, and that plaintiff’s amended complaint must be dismissed pursuant to CPLR 3211 (a) (7). Defendants also cite to CPLR 3211 (a) (1), and (5), asserting that dismissal is also required based upon documentary evidence and the Statute of Limitations contained in the limited warranty.”The defendants’ motion to dismiss the first cause of action, breach of contract against 355 Realty, was denied: “While defendants dispute that the alleged defects are actually structural in nature, plaintiff’s allegations as to their structural nature are sufficient, at this juncture, to withstand defendants’ motion to dismiss. Thus, dismissal of plaintiff’s first cause of action must be denied.”
Next, the court reviewed the second cause of action, which was breach of statutory warranties: “Defendants’ motion also seeks dismissal of plaintiff’s second cause of action for breach of statutory warranties, which alleges that, under applicable law, including General Business Law § 777-a, et seq., the sponsor warranted to purchasers of units that the units would be constructed in a skillful, careful, and workmanlike manner, consistent with proper design, engineering, and construction standards and practices, and free of material latent, design, and structural defects. Defendants argue that General Business Law § 777-a, known as the housing merchant implied warranty, is inapplicable to this case because it is limited to the construction of a ‘new home,’ defined in General Business Law § 777 (5) as ‘any single family house or for-sale unit in a multi-unit residential structure of five stories or less.’ As noted above, the building in which plaintiff’s condominium unit is located is a six-story building.”
The motion to dismiss the second cause of action is denied. The court provided this reasoning: “the full text of the offering plan has not been provided, the court is unable to examine the entire written agreement so as to determine the purpose of the inclusion of the text of General Business Law § 777.”
In the third cause of action, the plaintiff alleges “a breach of contract claim as against Vision, Foremost, and MMJ based upon their contract with 355 Realty, pursuant to which they agreed to be the general contractors/construction managers for the condominium, to undertake oversight responsibility for the design and construction of the condominium, to prepare and/or review drawings, plans, and specifications for the condominium, and to otherwise manage and oversee the project. Plaintiff alleges that Vision, Foremost, and MMJ breached their contractual obligations in that the condominium units were improperly and inadequately designed and constructed, and completed in an incompetent and unworkmanlike manner, with material design and construction defects.”
The motion to dismiss the third cause of action was denied as well: “Plaintiff alleges, in his amended complaint, that Vision, Foremost, and MMJ have acknowledged notice of the defects and have not denied that they are responsible for providing a warranty to plaintiff. Plaintiff also refers to this warranty, in his amended complaint, by noting that paragraph 16 of the purchase agreement stated that the ‘[s]eller shall not be liable to . . . the [p]urchaser for any matter as to which an assignable warranty . . . has been assigned . . . to [p]urchaser and in such case the sole recourse of such . . . [p]urchaser . . . shall be against the warrantor . . . except that in the event a contractor or subcontractor is financially unable or refuses to perform its warranty . . . [s]eller shall not be excused from its obligations enumerated in the [offering p]lan under Rights and Obligations of Sponsor.’ Consequently, the court finds that dismissal of plaintiff’s third cause of action as against Foremost and MMJ must also be denied.”
In the fourth cause of action, the plaintiff alleges “that defendants made false statements and representations orally, in advertisements, and in the purchase agreement, that the condominium was properly and adequately designed and constructed and completed in a competent and workmanlike manner, in accordance with the condominium plans and specifications and proper design, engineering, and construction standards and practices consistent with applicable standards for a first class, luxury condominium in Brooklyn.”
The court dismissed the fourth cause of action stating, “it must be dismissed because it is duplicative of his first cause of action for breach of contract.” Therefore, “defendants’ motion to dismiss plaintiff’s amended complaint is granted to the extent that it seeks dismissal of plaintiff’s fourth cause of action, and it is denied in all other respects.”
Read the court’s decision…
US Courts in Nevada Busy with Yellow Brass
August 2, 2012 — CDJ Staff
Judge Robert C. Jones, the chief judge of the United States District Court of Nevada, and Judge Peggy A. Leen, a magistrate judge with the same court, have issued orders in cases involving allegations of high-zinc yellow brass plumbing components. Judge Jones issued orders on Waterfall Homeowners Association v. Viega, Inc. and Greystone Nevada, LLC v. Anthem Highlands Community Association on July 9, 2012. Judge Leen issued orders on Southern Terrace Homeowners Association v. Viega, Inc. on July 10, and The Seasons Homeowners Association, Inc. v. Richmond American Homes of Nevada, Inc. on July 19.
Chief Judge Jones held an omnibus hearing on Waterfall v. Viega on June 12. During that hearing “Chief Judge Jones had already agreed that the claims against the product manufacturers should be be severed from the majority of the other claims and that discovery should proceed on different tracks.” Judge Leen ordered that the Southern Terrace claims be referred to Chief Judge Jones to determine if it should be consolidated with other yellow brass cases.
Chief Judge Jones’s decision in Greystone Nevada rests on issues of whether the affected homeowners had signed arbitration agreements. The judge found that the “Defendant’s claims that the seven homeowners they have identified are subsequent purchasers who need not arbitrate with Greystone is definitively refuted by the evidence.”
Judge Leen cites the Greystone decision in her ruling on Seasons Homeowners Association v. Richmond American Homes of Nevada. Richmond seeks to compel individual arbitration, stating that “the arbitration clause used singular rather than plural terms, and therefore, class arbitration was foreclosed.” Judge Leen determined that “under Nevada law, a homeowners association has statutory authority to represent homeowners associations in these types of actions. She did, however, accept Richmond’s argument that they could compel arbitration.
The Waterfall order involves an attempt by two homeowners associations to seek a class action against seventeen defendants, the first twelve of whom are described as “the Viega Defendants” and “the Uponor Defendants.” Chief Judge Jones notes that “many of these Defendants have been sued in identical class actions by the same law firms, but with different named defendants.” The homeowner association seek to “represent their own 998 members directly but also wish to represent up to 10,000 homeowner associations representing up to 250,000 similarly situated homeowner members throughout the Las Vega area via this class action.”
The judge has denied the Viega Defendants’ attempt to deny class certification, noting that the plaintiffs “argue that they intend to argue for class certification under Rule 23(b)(3). He also denied the motions by the two groups of the Viega Defendants. The U.S. Viega Defendants sought to be dismissed from the case for a variety of reasons. The judge noted of the claim that the plaintiffs had no injury of fact and are not alleging actual damage is contradicted by the allegations of actual damage made by the plaintiffs. ”They have alleged that the parts are defective and have already begun to corrode in at least a few sample circumstances, even if they have not yet failed.” To the argument that there re not particular claims made against defendants, the judge notes, “it is clear from the Complaint which Defendants are alleged to have manufactured and sold which brands of allegedly defective products, and which Defendants are alleged to have installed them.”
The German Viega firms also sought to be dismissed from the suit, noting that “they have no property, employees, accounts, advertisements, etc. in Nevada and have not sold any products in Nevada.” However, the judge notes that “at least Waterfall, and perhaps Red Bluff, was still under construction when Viega, Inc. became the sole shareholder of Vanguard Industries, Inc.”
Finally, both of Chief Judge Jones’s rulings cite a related case in the U.S. District Court for the District of Minnesota involving a class action settlement for those with F1807 systems. He notes in both these cases that “Plaintiffs disclaimed any claims based upon F1807 components.”
Read the courts' decisions…
Waterfall Homeowners Association v. Viega, Inc.
Greystone Nevada, LLC v. Anthem Highlands Community Association
Southern Terrace Homeowners Association v. Viega, Inc.
The Seasons Homeowners Association, Inc. v. Richmond American Homes of Nevada, Inc.
Insurer’s Motion for Summary Judgment Based on Earth Movement Exclusion Denied
October 28, 2011 — Tred Eyerley, Insurance Law Hawaii
After carefully dissecting the earth movement exclusion, the court denied the insurer’s motion for summary judgment. High Street Lofts Condominium Assoc., Inc. v. Am. Family Mut. Ins. Co., 2011 U.S. Dist. LEXIS 109043 (D. Colo. Sept. 26, 2011).
The City of Boulder performed road repair work near High Street’s property, some of which involved the use of a vibrating compactor to compact and set the roadbed. High Street noticed damage to its building, such as cracks in walls, sloping of floors and separations of porches from the building itself. High Street contacted the City of Boulder, who forwarded the complaint to its contractor, Concrete Express, Inc.
High Street also filed a claim with its business insurer, American Family, who denied the claim. American Family relied on an opinion letter by High Street’s engineer. The letter indicated that the damage was the result of "soil consolidation/settlement," in response to the construction activities. Based on this letter American Family concluded the claim was excluded under the policy’s earth movement exclusion.
High Street sued American Family, who moved for summary judgment.
Read the full story...
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com