Brown Paint Doesn’t Cover Up Construction Defects
April 25, 2012 — CDJ Staff
In a decision that describes the case as illustrating “the perils that real estate brokers and their agents assume when acting as a dual listing agent to both the buyers and sellers of the same house,” the California Court of Appeals has issued a decision in William L. Lyon & Associates v. The Superior Court of Placer County. Lyon & Associates sought summary judgment to dismiss the claims of the Henleys who bought a home in a transaction where a Lyon agent represented both sides.
The prior owners of the home, the Costas, had used a Lyon agent in purchasing their home. When they later sought to sell it, that agent “became aware of some of the house’s defects and problems.” In response, the Costas sought the help of another agent, Connie Gidal, also of Lyons & Associates. Photos taken in the presence of Ms. Gidal show defects of the paint and stucco. The Costas also took the step of painting the house dark brown. During the sale process, “rain caused many of the painted-over defects to reappear.” The Costas “purchased more dark brown paint and covered up the newly visible damage prior to inspection by the Henleys.”
With the damage concealed, the Henleys bought the home in May 2006. The agreement with Lyons & Associates noted that “a dual agent is obligated to disclose known facts materially affecting the value or desirability of the property to both parties.” Escrow closed on May 9, 2006. The contract with the broker included a two-year limit on the time to bring legal action.
The Henleys moved in during June 2006, and “began to discover construction defects that had been concealed by the Costas.” In addition to the painted-over stucco problems, the Henleys found that the Costas had “installed quartzite stone overlays on the backyard steps in a manner that caused water intrusion on the house’s stucco walls.”
In May 2009, the Henleys sued the Costas, Ron McKim Construction, Lyons & Associates, and Ms. Gidal. Their complaint alleged that Lyons & Associates had committed breach of contact, negligence, fraud, breach of fiduciary duty, and negligent nondisclosure in connection with the construction defects. The Costas named Lyons in a cross complaint. Lyons moved for summary judgments on the grounds that the two-year statute of limitations had expired before the complaint and cross-complaint were filed. Both the Henleys and the Costas opposed this claim. The court denied the motion and Lyons appealed.
The appeals court upheld the denial, noting that the both California Supreme Court decision and later action by the legislature compels real estate brokers and salespersons “to conduct a reasonably competent and diligent visual inspection of the property offered for sale.” The court noted that under California law, brokers have responsibilities to both sellers and buyers. The section of law cited by Lyons applies to seller’s agents. The court rejected the contention by Lyons that they were “cooperating brokers.” The Henleys were “not constrained by the two-year statute of limitations.”
Lyons contended that even if California’s statute did not apply, there was a contractual limit of two years. The court also rejected this, agreeing with the Henleys that “the two-year limitation period must be extended by the discovery rule.”
The court noted that “Lyon & Associates may not reap the benefit of a shortened contractual limitation period when its own alleged malfeasance contributed to the delay in the discovery of the buyer’s injury.” The court found that the Henleys could proceed with their breach of contract claim, because, “when a breach of contract is committed in secret, such as the intentional nondisclosure of a real estate broker regarding a previously visible construction defect, the contractual limitations period is properly held subject to the discovery rule.” The court felt that the interpretation favored by the California Association of Realtors would “halve the applicable statute of limitations period.”
In addition to rejecting Lyon request for summary judgment on the claims made by the Henleys, the court also rejected the request of summary judgment on the claims made by the Costas, concluding that neither claim is time-barred. Costs were awarded to both the Henleys and Costas.
Read the court’s decision…
In Colorado, Repair Vendors Can Bring First-Party Bad Faith Actions For Amounts Owed From an Insurer
December 20, 2012 — Brady Iandiorio, Higgins, Hopkins, McLain & Roswell
With the aftermath of Sandy still being felt up and down the Eastern seaboard, the question of many victims turns to how they can rebuild their lives and homes. One of the first things many people do is call on their insurance carriers to help rebuild whatever damaged property they have. In a recent case here in Colorado, those rebuilding efforts got reaffirmed by a Court of Appeals case, Kyle W. Larson Enterprises, Inc., Roofing Experts, d/b/a The Roofing Experts v. Allstate Insurance Company, --- P.3d ----, 2012 WL 4459112 (Colo. App. September 27, 2012).
The facts of the case are pretty straightforward and could describe many repair vendors in numerous situations. Roofing Experts contracted with four homeowners insured by Allstate to repair their damaged roofs. The contracts provided that repair costs would be paid from insurance proceeds. The contracts also allowed Roofing Experts full authority to communicate with Allstate regarding all aspects of the insurance claims. Before work began, Roofing Experts met with adjusters from Allstate to discuss the four homes and the amount of each claim. After receiving approval for the claims, Roofing Experts began the repairs. During construction, Roofing Experts discovered additional repairs were necessary to maintain certain manufacturer’s warranties and to conform to applicable building codes.
Read the full story…
Reprinted courtesy of Brady Iandorio, Higgins, Hopkins, McLain & Roswell, LLC. Mr. Iandorio can be contacted at iandiorio@hhmrlaw.com
Washington Court of Appeals Upholds Standard of Repose in Fruit Warehouse Case
August 4, 2011 — CDJ Staff
On July 28, the Washington Court of Appeals ruled in Clasen Fruit & Cold Storage v. Frederick & Michael Construction Co., Inc. that more than six years had passed since a contractor had concluded work and so granted a summary dismissal of the suit.
Frederick & Michael Construction Co., Inc. (F&M) was contracted to construct several buildings for Clasen Fruit and Cold Storage. These were completed in March, 1999. The buildings suffered wind damage to the roofs in 2001, 2003, 2005, and 2006. In the first two incidents, F&M repaired the roofs with Clasen paying for repairs.
In 2005, Clasen hired Continuous Gutter to make repairs. The final incident was the collapse of the roof of one building. This was attributed to “excessive moisture in the roof’s vapor barriers.” At this point, Clasen demanded that F&M pay for repair and replacement costs. In 2008, Clasen sued F&M for damages for breach of contract and negligent design and construction of the roof.
The decision then covered the meanings, in Washington law, of “termination of services” and “substantial completion.” The panel concluded that construction was “substantially completed in 1997” and “relevant services” by 2001. “But Clasen did not sue until 2008, some seven years after termination of any roof related services.”
Read the court’s decision…
Granting Stay, Federal Court Reviews Construction Defect Coverage in Hawaii
January 6, 2012 — Tred Eyerly, Insurance Law Hawaii
The federal district court ultimately stayed a construction defect case, but offered comments on the current status of coverage disputes for such defects in Hawaii. See National Union Fire Ins. Co. of Pittsburgh, Pa. v. Simpson Mfg. Co., 2011 U.S. Dist. LEXIS 128481(D. Haw. Nov. 7, 2011).
National Union filed a complaint for declaratory relief to establish it had no duty to defend or to indemnify Simpson Manufacturing Company in four actions pending in the Hawaii state courts. The state court actions concerned allegedly defective hurricane strap tie hold downs that were manufactured and sold by Simpson. The hurricane ties allegedly began to prematurely corrode and rust, causing cracking, spalling and other damage to homes.
National Union contended the underlying allegations did not constitute "property damage" caused by an "occurrence," as defined in the policies.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
San Diego Construction Defect Claim Settled for $2.3 Million
July 10, 2012 — CDJ Staff
The Nauman Law firm has settled the lawsuit by the Latitude Owners Association against CS-Crossroads and others, as reported in the Sacramento Bee from a press release by the firm. The owners at Latitude, a condominium community in San Diego, found that hillside crawl spaces were not property waterproofed, leading to rotting plywood, water intrusion, and pipe leaks. There were additional problems with retrofitted windows and repairs of outside decks. The case was filed in San Diego Superior Court, but settled after multiple mediations.
Read the full story…
Contractor Sues Supplier over Defective Products
June 28, 2011 — CDJ Staff
Fast Track Specialties has sued RJF International after needing to remove wall protection units at Methodist West Houston Hospital, according to an article in the Houston Chronicle. Fast Track claims that contractors had to disconnect gas, water, and electric from the area to facilitate removal of corner guards, handrails, and crash guards from the hospital. This cost the contractor more than $135,000.
Fast Track is claiming that RJD International has committed breach of contract, breach of warranty, and negligent representation.
Read the full story…
Remodels Replace Construction in Redding
September 9, 2011 — CDJ Staff
The Record Searchlight reports that while new construction is down in Redding, California, residential and commercial remodel permits are up 17 percent. By August 2010, there had been 63 housing and commercial business starts in Redding, while this year has seen only 15.
One such remodel, that of Parkview Market, will cost about $201,000. Safeway is planning on two $80,000 remodels of its grocery stores in Redding. In all, the 150 building permits for remodels are worth a total of $2.8 million.
Read the full story…
Was Jury Right in Negligent Construction Case?
September 30, 2011 — CDJ Staff
Yes, said the South Carolina Court of Appeals in Pope v. Heritage Communities, Inc. Heritage Communities developed Riverwalk, a community in South Carolina. During the earlier trial, HCI “conceded that construction defects existed at Riverwalk, and repairs needed to be made.” The trial court found that the construction was negligent, awarding the property owners association $4.25 million in actual damages and $250,000 in punitive damages, with the class of owners awarded $250,000 in actual damages and $750,000 in punitive damages. HCI appealed on nine issues. All were rejected by the appeals court.
The court rejected HCI’s claim that the judge’s instruction to the jury suggested to the jury that “the court had already determined that Appellants were willful, wanton, and reckless.” But here, the appeals court found “no reversible error.”
The general contractor for Riverwalk was BuildStar. Off-site management and sale were managed by Heritage Riverwalk, Inc., which also owned title to the property. Both these companies were owned by Heritage Communities, Inc. During the trial, an HCI employee testified that “the three corporations shared the same officers, directors, office, and telephone number.” The trial court found that the three entities were amalgamated. This was upheld by the appeals court.
Nor did the appeals agree with the HCI that the trial court had improperly certified a class. The owners were seen as properly constituting a class. Further, the court held that the property owners’ losses were properly included by the trial court. HCI objected at trial to the inclusion of evidence of subsequent remedial measures, however, as they did not object that it was inadmissible, the issue could not be addressed at appeal.
HCI argued on appeal that the trial court should not have allowed evidence of defects at other HCI developments. The appeals court noted that “the construction defects at the other HCI developments were substantially similar to those experienced by Riverwalk.”
The court additionally found that the negligence claims, the estimated damages (since full damage could not be determined until all defective wood was removed), and the award of punitive damages were all properly applied.
Read the court’s decision…
Water District Denied New Trial in Construction Defect Claim
August 16, 2012 — CDJ Staff
The United District Court in Tampa, Florida has rejected the motion by Tampa Bay Water for a new trial in their claims that HDR Engineering negligently designed the C.W. Bill Young Regional Reservoir. The claims went to a jury trial, at the end of nineteen days, the jury deliberated for four hours, finding for HDR Engineering. In rejecting Tampa Bay’s motion, the judge noted that “on close examination, TBW’s contentions have little to do with the factual determinations of the jury, which evidently concluded that TBW did not meet its burden of proof, an unsurprising conclusion, considering HDR’s evidence and the weaknesses in TBW’s evidence.”
The court cited an earlier decision that “a new trial may be granted where the jury’s ‘verdict is against the great, not merely the greater weight of the evidence.’” However, the court found that the jury’s verdict “was well supported by the evidence” and that “TBW’s case showed signs of weakness at virtually every turn.” TBW’s expert “changed his opinion late in the case concerning the culpability of the contractor.” As a result, “Brumund’s change in opinions effectively bolstered HDR’s faulty construction defense.”
TBW also raised claims a pre-trial order prevented it “from introducing evidence that HDR did not fulfill its contractual quality control responsibilities” and that evidentiary rulings prevented “TBW from introducing evidence concerning quality control.” However, TBW dismissed its claims over quality control, then “attempted no less than three times during ?Ķ testimony to introduce evidence of the purpose of the quality control requirement and quality control assurance.”
TBW also contended “that it was precluded from introducing evidence that HDR’s inspectors never reported that the protective layer exceeded three feet after inspecting the work as part of HDR’s quality control duties.” The court noted that “TBW asked these very questions of HDR’s Engineer of Record.” The court also found that testimony regarding photographs of the construction was properly excluded as TBW never entered the photos into evidence.
TBW had made an argument for a jury view. Prior the trial “after discussion, and to their credit, the parties agreed to a jointly-prepared helicopter ‘flyover’ video.” The court noted that “the size and physical characteristics of the reservoir were adequately and effectively depicted in the video.” The hazards the jury did not, then, have to encounter included the narrow, unpaved rim of the reservoir, snakes, and alligators.
Read the court’s decision…
School Sues over Botched Pool
October 23, 2012 — CDJ Staff
The Daily American reports that the Somerset Area School District has alleged that the contractor who repaired and renovated the district’s swimming pool “botched” the job. Now the school has filed a civil case in the Somerset County Court of Common Pleas. The contractor, Wilson Construction Co. would prefer the matter to be settled in binding arbitration.
The school district alleges that the surface installed by Wilson Construction cracked and bubbled due to improper installation. The manufacturer of the waterproofing system, Dryvit Systems, tested the installation and concluded it was an installation failure instead of a product defect. Dryvit told the district that the exterior walls would have be removed.
The school district paid Wilson Construction $591,081 for their work. In their lawsuit, they are seeking $594,596 to cover the cost of draining the pool and repairing it.
Read the full story…
Window Manufacturer Weathers Recession by Diversifying
October 28, 2011 — CDJ Staff
American Openings, a Tuscon-based window manufacturer, has responded to the loss of its sales of windows for new home construction by moving into new markets. The Arizona Daily Star reports that American Openings used to see providing windows for new homes as half their business. Now, Tom Regina, the founder and president says “single family is just dead.”
Their products are insulated windows, designed to comply with Energy Star standards. Without new homes being built, now the company is focusing on homeowners and building owners looking for more energy efficient windows. As the windows have two or three panes and special coatings, homeowners using them are eligible for tax credits.
One of their newer products combines their energy-saving coatings with “break resistant” glass. The article notes that the windows repel “all but the most determined burglars.” However, the company is still awaiting special equipment to cut the glass.
Read the full story...
Another Guilty Plea In Nevada Construction Defect Fraud Case
April 25, 2012 — CDJ Staff
The eleventh defendant has entered a guilty plea in the ongoing federal investigation of construction defect fraud in the Las Vegas area. Mahin Quintero plead guilty to producing a false authentication feature, a misdemeanor. Ms. Quintero’s part in the scheme was to falsely authenticate signatures on loan documents for straw buyers. Ms. Quintero stated in court that she had been ordered to destroy her notary book three years ago. According to her plea bargain, the straw buyers did not appear in front of her when she notarized their signatures. As part of the scheme, the straw buyers would take control of homeowners associates, sending construction defect complaints and repairs to favored firms.
Read the full story…
Negligent Misrepresentation in Sale of Building Altered without Permits
September 30, 2011 — CDJ Staff
The Supreme Court of New Hampshire has ruled in the case Wyle v. Lees. The Leeses owned a two-unit apartment building in North Conway, New Hampshire. They hired a contractor to add a third, larger apartment, including a two-car garage. The Leeses and their contractor submitted a building permit application. They were informed that site plan review was required. After receiving approval on the site plan, construction started. At no point did they obtain a building permit and the construction was never inspected. The Leeses subsequently added more space to the unit, reducing parking spaces below the minimum required. Again, they did not obtain a building permit.
In 2007, three years after all these changes were complete, the Leeses sold their building to Mr. Wyle. To the question “are you aware of any modifications or repairs made without the necessary permits?” they answered “no.” About six weeks after closing, Wyle “received a letter from the town code enforcement officer regarding the legality of the removal of a garage door from the new unit.” A subsequent inspection revealed “numerous building and life safety code violations.”
Mr. Wyle brought a claim against the Leeses for negligent misrepresentation. The defendants filed a motion “seeking to preclude economic loss damages.” At a two-day bench trial, Mr. Wyle won. The Leeses appealed.
The appeals court found that “the defendants negligently misrepresented that the premises were licensed for immediate occupancy and that the defendants had obtained all necessary permits,” and thus upheld the lower court’s finding of negligent misrepresentation. The appeals court also rejected the Leeses’ argument that damages must be apportioned on all parties, including “the plaintiff himself, the plaintiff’s building inspector, and the defendant’s contractor,” finding a lack of “adequate evidence.”
The Leeses further argued that they were unaware that modifications and repairs were accomplished without the required permits. The appeals court noted that “the trial court found that both the conditional approval and final approval for the site plan stated that a building permit and a certificate of occupancy were required prior to any use.” The court concluded that the Leeses “knew or should have known of the falsity of their representation.”
The appeals affirmed the findings of the trial court.
Read the court’s decision…
Largest Per Unit Settlement Ever in California Construction Defect Case?
October 28, 2011 — CDJ Staff
BusinessWire reports that the Chelsea Court Homeowners Association has settled their construction defect case for $5.4 million. That works out to $169,000 per unit, which BusinessWire describes as “California’s largest per-unit recovery known to be on record to date.”
Most of the money in the settlement is coming from insurance companies for the builder and thirteen subcontractors. Issues included roof and window leaks, deck failures, and unsafe walkways.
Read the full story...
Construction Defects Are Occurrences, Says South Carolina High Court
December 20, 2012 — CDJ Staff
The South Carolina Supreme Court has left the legislature’s new, expanded definition of “occurrence” in place, declining to declare it unconstitutional. South Carolina included faulty workmanship as an occurrence in response to a Supreme Court decision, which the court later reversed. One of the parties in that earlier decision, Harleysville Insurance, challenged the new law, claiming that the legislature didn’t have the power to pass a law to overturn a court ruling. The court did not concur.
However, the court did determine that the law was not retroactive and covered only claims filed after the law became effective in May 2011. The Chief Justice of South Carolina noted that “insurance coverage for construction liability lacks clarity, particularly with respect to whether construction defects constitute ‘occurrences’ under construction general insurance policies.”
Read the full story…
Construction Defect Not Occurrences, Says Hawaii Court
July 10, 2012 — CDJ Staff
Some insurers in Hawaii have made it clear that they will be covering construction defects, despite a court ruling concluding that defects are not occurrences, under Hawaii law. The case, heard by Hawaii’s Intermediate Court of Appeals found that “breach-of-contract claims based on allegations of shoddy performance are not covered under CGL policies and that tort-based claims derivative of such breach of contract claims also are not covered.”
Writing in Business Insider, Michael Bradford notes that the case, Group Builders Inc. and Tradewind Insurance Co. Ltd. vs. Admiral Insurance Co., involved improperly installed insulation at the Hilton Hawaiian Village’s Kalia Tower. Hilton was forced to close 21 floors due to extensive mold in guest rooms. Although the court did recognize this property damage, they did not feel it triggered insurance coverage, noting that if disputes over the quality of work were covered, CGL policies would become professional liability policies or performance bonds.
One critic of the decision, Warren C. Perkins, the risk manager at Boh Bros. Construction of New Orleans, noted that under the decision, “it doesn’t matter what the policy says and there is no need to investigate the policy wording.”
Read the full story…
South Carolina Legislature Defines "Occurrence" To Include Property Damage Arising From Faulty Workmanship
May 26, 2011 — Tred R. Eyerly, Insurance Law Hawaii
On May 17, 2011, South Carolina passed legislation to combat the restrictive interpretation of what constitutes an "occurrence" under CGL policies. S.C. Code Ann. sec. 38-61-70.
The legislation reversed a decision by the state's Supreme Court issued earlier this year. See Crossman Communities of North Carolina, Inc. v. Harleysville Mut. Ins. Co., 2011 W.L. 93716 (S.C. Jan. 7, 2011). Crossman had overruled an earlier decision by the South Carolina Supreme Court that holding that defective construction was an “occurrence.” Crossman, however, reversed course, holding that damages resulting from faulty workmanship were the “natural and probable cause” of the faulty work and, as such, did not qualify as an “occurrence.”
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Differing Rulings On Construction Defect Claims Leave Unanswered Questions For Builders, and Construction Practice Groups. Impact to CGL Carriers, General Contractors, Builders Remains Unclear
March 7, 2011 — March 7, 2011 Construction Defect Journal Staff
In the past year a number of state and federal courts have rendered a number of conflicting decisions that promise to alter or perhaps shift entirely the paradigm, of how builders manage risk.
According to a report today by Dave Lenckus in Property Casualty 360 “Nine state and federal courts and one state legislature over the past year have addressed whether a construction defect a defective product or faulty workmanship is fortuitous and therefore an occurrence under the commercial general liability insurance policy. Four jurisdictions determined it is; three said no; two ruled that a construction defect that causes consequential damage to property other than the work product is an occurrence; and one federal court contributed its conflicting case law that has developed in Oregon since its high court ruled in 2000 that a construction defect is not an occurrence”.
The article strongly suggests that in the absence of a clear consensus over what the recent rulings mean for builders and contractors coverage disputes will intensify and continue to proliferate.
Doing this on a state-by-state basis has caused a lot of confusion among buyers and sellers, said Jeffrey A. Segall, a Tampa-based senior vice president and the Florida Construction Practice leader at Willis of Florida, a unit of Willis Group Holdings.
Read Full Story...