Developer’s Fraudulent Statements Are His Responsibility Alone in Construction Defect Case
February 10, 2012 — CDJ Staff
The Texas Court of Appeals ruled on December 21 in the case of Helm v Kingston, a construction defect case. After purchasing what was described as “an extremely well-built” two-bedroom townhouse, Mr. Kingston made complaints of construction defects. Greenway Development did not repair the defects to Kingston’s satisfaction, and he filed notice of suit. In his suit, he claimed that GDI and its president, John Helm, had committed fraud and negligent misrepresentation. Kingston claimed that Helm “fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of workmanship was atrocious.” Helms brought a counterclaim that Kingston’s suit was frivolous.
About four years after Kingston purchased the townhome, the suit proceeded to trial. The trial court determined that Helm was not “liable in his individual capacity,” but this was reversed at appeal.
A second trial was held ten years later on the question of whether Kingston’s unit was a townhome or an apartment. A jury found that Helm “engaged in a false, misleading or deceptive act or practice that Kingston relied on to his detriment.” Kingston was awarded $75,862.29 and an additional $95,000 in attorney fees by the jury. Helms made an unsuccessful appeal to the Appeals Court, after which Kingston was awarded an additional $10,000. Helms then made an unsuccessful appeal to the Texas Supreme Court, which lead to an additional $3,000 for Kingston. There was also a verdict of $48,770.09 in pre-judgment interest and “five percent post-judgment interest accruing from the date of the judgment until the time the judgment is paid. Helm appealed.
In his appeal, Helm raised seven issues, which the court reorganized into five Kingston raised one issue on cross-appeal.
Helms’ first claim was that Kingston “failed to satisfy the requirement of” Texas’s Residential Construction Liability Act and that by not filing under the RCLA, Kingston’s fraud and misrepresentation claims were preempted. Further Helms claimed that the RCLA limited Kingston’s damages. The court rejected this, as the RCLA deals with complaints made to a contractor and not only did Helm fail to “conclusively establish” his “status as a ‘contractor’ under the statutory definition,” Helm testified that he was “not a contactor” at the pre-trial hearing.
Helms’s second claim was that Kingston’s later claim of a misconstructed firewall should be barred, claiming that Kingston “‘had knowledge of a defect in the firewall’ as early as 1997 but did not assert them until 2007.” The court rejected this because Kingston’s claim was that “Helm ‘fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of the workmanship was atrocious.’”
Helms also challenged whether his statements that the residence was of “good quality” constituted fraud and misrepresentation under Texas’s Deceptive Trade Practices-Consumer Protection Act. The court concluded that Helm was in a position to make knowledgeable statements and further that “residential housing units are not artistic works for which quality is inherently a matter of subjective judgment.” Helm also claimed that Kingston could have avoided certain repair expenses through the “exercise of reasonable care.” Helms argued that the repairs could have been made for $6,400. The court disagreed, as these claims were cited only to invoke the DTPA, and that later petitions established additional defects.
Helms’s next claim was that he was not allowed to designate responsible third parties. The court rejected this because there GDI represented matters concerning the residence only through Helm’s statements. The court noted that “Helm is correct that?third parties may be liable for fraud if they ‘participated in the fraudulent transactions and reaped the benefits,’” but they note that “Helm never specifically alleged that GDI or CREIC participated in Helm’s alleged fraudulent transactions.
The final issue in the decision was about court costs, and here the court denied claims on both sides. Helm argued that the award of legal fees were excessive, as they exceeded the actual damages. The court noted that they “may not substitute our judgment for that of the jury,” and also that “the ratio between the actual damages awarded and the attorney’s fees is not a factor that determines the reasonableness of the fees.” But the court also rejected Kingston’s claim for post-judgment interest on $10,312.30 that Helm had deposited in the trial court’s registry. The court noted that the monies were to be paid out upon final judgment, but the mandate did not include any reference to interest.
Read the court’s decision…
Foundation Arbitration Doesn’t Preclude Suing Over Cracks
March 28, 2012 — CDJ Staff
The Louisiana Court of Appeals has reversed the decision of a lower court, allowing a construction defect case to go through. In Greer v. Town Construction Company, the Greers hired Town Construction to build a home in Baton Rouge. The business relationship went sour, with disputes over “costs, change orders, workmanship, and timeliness issues.”
Town Construction filed an arbitration claim for the unpaid contract balance. In the counterclaim, the Greers made claims of mold and mildew problems, and wall cracks that they attributed to a “structural defect in the foundation.” In arbitration, Town Construction was awarded the full contract balance plus extra costs and interest, while the Greers were awarded for their structural claims.
Three years later, the Greers found additional cracks and filed a suit against Town Construction. Town Construction argued that the Greer’s lawsuit should be dismissed, as the claims had already been through the arbitration process. The district court agreed with Town Construction and dismissed the suit.
The appeals court noted that the Greers would have no ground for a suit if the arbitration was a “valid and final judgment,” and went on to note that there was no evidence in the trial record that the arbitration met this qualification. The court noted that although it was clear that both parties had agreed to the decisions of the arbiter, under Louisiana law, arbitration is not final until it has been “rendered by a court with jurisdiction over subject mater and over parties.”
The court remanded the case to the lower court, noting that “the district court is obligated to first determine whether a valid arbitration award is in existence and had been confirmed before considering the merits of the exception. The court noted that their decision “should not be read to express any opinion as to the merits of the claims or as to the propriety of damages sought in the Greer’s lawsuit.”
Read the court’s decision…
Insurer’s Motion for Summary Judgment Based on Earth Movement Exclusion Denied
October 28, 2011 — Tred Eyerley, Insurance Law Hawaii
After carefully dissecting the earth movement exclusion, the court denied the insurer’s motion for summary judgment. High Street Lofts Condominium Assoc., Inc. v. Am. Family Mut. Ins. Co., 2011 U.S. Dist. LEXIS 109043 (D. Colo. Sept. 26, 2011).
The City of Boulder performed road repair work near High Street’s property, some of which involved the use of a vibrating compactor to compact and set the roadbed. High Street noticed damage to its building, such as cracks in walls, sloping of floors and separations of porches from the building itself. High Street contacted the City of Boulder, who forwarded the complaint to its contractor, Concrete Express, Inc.
High Street also filed a claim with its business insurer, American Family, who denied the claim. American Family relied on an opinion letter by High Street’s engineer. The letter indicated that the damage was the result of "soil consolidation/settlement," in response to the construction activities. Based on this letter American Family concluded the claim was excluded under the policy’s earth movement exclusion.
High Street sued American Family, who moved for summary judgment.
Read the full story...
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
No Third-Quarter Gain for Construction
November 18, 2011 — CDJ Staff
The Associated Builders and Contractors released their analysis of construction work under contract and found that there was no increase in construction backlog from the second quarter of 2011. There was still improvement, however, over 2010, as the third quarter backlog is 16.3 percent higher than that of a year ago.
The current backlog is 8.1 months, which according to Anirban Basu, the chief economist of the ABC, “is consistent with flat construction spending.” He noted that less than 8 months indicated a decline.
Read the full story…
Construction Workers Face Dangers on the Job
November 18, 2011 — CDJ Staff
OSHA calculates that for each 33,000 active construction workers, one will die on the job each year, making their risk over the course of their careers at one out of every 200 workers. This puts it many times over OSHA’s definition of “significant risk” of 1 death per 1,000 workers over the course of their careers. According to an article in People’s World, “the main risk of death is from falls.”
At a talk at the American Public Health Association’s meeting, one expert noted that “construction workers make up 6 percent to 8 percent of all workers, but account for 20 percent of all deaths on the job every year.”
Read the full story…
Association May Not Make Claim Against Builder in Vermont Construction Defect Case
October 23, 2012 — CDJ Staff
The Vermont Supreme Court issued a ruling on September 28 on Long Trail House Condominium Association. The case was heard by a panel of two Supreme Court justices, Marilyn Skoglund and Brian Burgess, and three justices specially assigned for the case, Kupersmith, Davenport, and Johnson. The decision came down with a 3-2 split; Judges Kupersmith and Johnson joining in a dissent.
In the underlying case, Stratton Corporation entered into an agreement with Engelberth Construction in which Engelberth would supply “recommendations on construction feasibility, consultation as to the selection of materials and equipment, assistance with zoning requirements and permits, and cooperation with the ‘design team’ to provide valuable engineering services.” Engelberth was not responsible to determine that the drawings and specifications were in accordance with the law and building codes, nor were they responsible “for the design team’s designs, errors, or omissions.”
Subsequent to the agreement was a construction project which culminated in the incorporation of the Long Trail House Condominium Association. The condominium owners initiated a lawsuit over alleged defects. Stratton, Intrawest, and the association settled claims for $7,025,00 with Stratton and Intrawest both pursuing claims against Engelberth. This case is still unsettled.
The association progressed on remediation, which cost about $1,500,00 more than was provided by the settlement, and so the association also sued Engelberth. In this case, the court granted a summary judgment to Engelberth, concluding that negligence claim was barred both “by the economic loss rule and that the absence of contractual privity was fatal to the warranty claims.”
The court upheld both determinations of the lower court. The court noted that “the economic loss rule ‘prohibits recovery in tort for purely economic losses’” and that “in tort law, duties are imposed by law to protect the public from harm.” A negligence claim could only be supported with evidence of “some accompanying physical harm, which does not include economic loss.”
The association made the claim that the economic loss rule applies only when there is a contractual relationship between the two parties. The court rejected this argument, citing a reference that “economic interests are protected, if at all, by contract principles, rather than tort principles.”
Nor did the court find it persuasive that a “professional services” exception to the economic loss doctrine applied, noting that the court has rejected this notion in two prior cases. The noted that the association’s losses were purely economic, and their inability to settle those claims with Engelberth did not mean that they had not means of settling them, as they were able to settle these very claims with Stratton and Intrawest.
The association also raised claims of an implied warranty, resting on the construction contract between Engelberth and Stratton. This was also rejected by the court, noting that Vermont “case law plainly contemplates the existence of contractual privity before a breach of implied warranty claim can be raised.” The court noted that there was neither a contract nor a sale between Engelberth and the association, and thus there were no grounds for an implied warranty. The court concluded that “the Association’s warranty remedy lies against the entity that sold it the condominium units and implicitly warranted through the sale that the units were built in a good and workmanlike manner and that they were suitable for habitation.”
Read the court’s decision …
OSHA Extends Temporary Fall Protection Rules
March 1, 2012 — CDJ Staff
OSHA announced that its current rules on fall protection for residential construction will remain in place until September 15, 2012. The current measures became effective in June 2011. Under the new rules, falls must be prevented by fall protection measures unless the measures can be shown to be unfeasible or even hazardous.
Under the extension of the temporary enforcement measures, contractors who ask for compliance assistance with OSHA are given top priority and penalties can be reduced. OSHA has conducted more than 1,000 outreach sessions on the new rules.
Read the full story…
Safety Officials Investigating Death From Fall
September 9, 2011 — CDJ Staff
California safety officials are looking into the circumstances surrounding the death of a construction worker who fell from a roof in Tiburon, California. Another worker found Gabriel Vasquez unconscious at the site. Vasquez was later pronounced dead. The State Division of Occupational Safety and Health are trying to determine how Vasquez fell.
Read the full story…
Harmon Towers Duty to Defend Question Must Wait, Says Court
March 1, 2012 — CDJ Staff
The Harmon Towers project in Las Vegas was eventually halted short of the planned forty-seven stories after “it was determined that there was substantial defective construction, including defective installation of reinforcing steel throughout the Harmon.” The American Home Insurance Company and Lexington Insurance Company put forth a claim that they had no duty to defend Perini Construction, the builder of the defective Harmon Towers. Further, American Home seeks to recover the monies American reimbursed Perini. The United States District Court of Nevada ruled in the case of American Home Assurance Co. v. Perini Building on February 3, 2012.
The two insurance companies covered Perini and its subcontractors, Century Steel, Pacific Coast Steel, and Ceco Concrete Construction. Century Steel was the initial subcontractor for the reinforcing steel; they were later acquired by Pacific Coast Steel. In this current case, Perini Construction is the sole defendant.
Perini sought a dismissal of these claims, arguing that without the subcontractors joined to the case, “the Court cannot afford complete relief among existing parties.” The court rejected this claim, noting that the court can determine the duties of the insurance companies to Perini, which the court described as “separate and distinct from those of the subcontractors.” The subcontractors “have not claimed an interest in the subject matter of the action.” The court concluded that it could determine whether Perini was entitled or not to coverage without affecting the subcontractors. The court rejected Perini’s claim.
Perini also asked the court to abstain from the case, arguing that it was better heard in a state court. The court noted that several considerations cover whether a case is heard in state or federal courts. The court noted that if the case weighed heavily on state law, the state courts would be the obvious location. Further, if there were a parallel action in the state courts, “there is a presumption that the whole suit should be heard in state courts.” This is, however, no parallel state suit, although the court noted that Perini has “threatened” to do so.
However, the issue of who is to blame for the problems at Harmon Towers has not been resolved. The court concluded that until the “underlying action” was concluded, it was premature to consider the issues raised in this case while the earlier lawsuit was still in progress. The court denied Perini’s motion to dismiss the case. Given that the outcome of the earlier construction defect case may lead to further litigation in state court, the District Court granted Perini’s motion to abstain, but staying their judgment until the construction defect case is resolved.
Read the court’s decision…
Windows and Lawsuits Fly at W Hotel
July 5, 2011 — CDJ Staff
An Austin, Texas lawyer has filed a lawsuit against Starwood Hotels and Resorts, the operator of the W Hotel Austin, after two people were struck by glass which fell from the hotel’s balconies. YNN in Austin reports that the hotel has been closed indefinitely as construction workers removed panels. An additional three panels fell before work started. Randy Howry, the lawyer representing the injured parties, notes that in May glass falling from the W Hotel in Atlanta killed one woman and injured another. “Seventeen days pass and we put them on notice, our clients have put them on notice, yet nothing has been done an only after the glass fell yesterday did they do something about it,” YNN quotes Howry.
The hotel released a statement that they will be replacing all of the balcony glass to ensure safety for their guests and the general public. They relocated all hotel guests and coordinated with Austin officials to close adjacent sidewalks and roads. The statement identifies the firms involved with the design and construction of the balconies.
Read the full story …
District Court Awards Summary Judgment to Insurance Firm in Framing Case
August 4, 2011 — CDJ Staff
In the case of Continental Western Insurance Company v. Shay Construction Inc., Judge Walker Miller has granted a summary judgment against Shay Construction and their co-defendant, Milender White Construction Company.
Shay was the framing subcontractor for Milender White on what the court described as “a major construction project in Grand County, Colorado.” Two of Shay’s subcontractors, Wood Source Inc. and Chase Lumber Company furnished materials, labor, and equipment to Shay. They subsequently sued for nonpayment and sought to enforce mechanic’s liens, naming both Shay and Milender as defendants. Milender White alleged that Shay had “breached its obligation under its subcontracts with Milender White.”
Shay’s insurance provider, Continental Western, stated that its coverage did not include “the dispute between Shay, its subcontractors, particularly the cross claims asserted by Milender White.” Shay then sued Continental Western, alleging breach of contract and statutory bad faith.
The court, however, has found with Continental Western and has granted them a summary judgment. They found “no genuine issue as to any material fact.” The judge did not side with Continental Western on their interpretation of the phrase “those sums that the insured becomes legally obligated to pay as damages.” The court found that the Colorado courts have not limited this to tort actions only. However, as Milender’s cross claim included claims of faulty workmanship on the part of Shay, Judge Miller found for Continental.
Read the court’s decision…
Builder Cannot Receive Setoff in Construction Defect Case
July 10, 2012 — CDJ Staff
The California Court of Appeals has dismissed an appeal in a San Diego construction defect case. In Smith v. Walters Group, Christopher and Maud Smith sued The Walters Group, a real estate developer, and Galen C. Pavelko, Inc, the builder of their home. Walters had bought five lots and hired Pavelko to build houses on them, selling one of these homes to the Smiths. “After moving in, the Smiths noticed a strong and obnoxious odor permeating the house.” The Smiths sued but were ordered to arbitrate instead, pursuant to a clause in the purchase contract. The Smiths were awarded $1.5 million at arbitration.
Walters requested that the arbitration remain open to determine if Walters was entitled to a setoff for settlements from defendants not involved in the arbitration. During this time, Pavelko made a settlement with the Smiths, which the court found was in good faith. At the same time, the arbitrator “reached the opposite conclusion.” The arbitrator concluded that “only settlements made ‘in good faith before verdict or judgment’ qualified for setoff.”
Walters moved that the trial court “‘correct’ the award,” but the trial court declined to do so and confirmed the award. In the appeal, Walters raised the issue of “whether Pavelko’s settlement occurred ‘before verdict or judgment.’” The appeals court dismissed the appeal, noting that “Walters would not be entitled to a $500,000 setoff if we reversed the trial court’s order determining the Smith-Pavelko settlement was made in good faith because Pavelko’s $500,000 payment was expressly conditioned on such an order.” They add that “were we to reverse the trial court’s order, Pavelko would have no obligation to pay the Smiths the $500,000.” This would then “deprive Walters of the corresponding statutory right to a setoff.”
Read the court’s decision…
Damron Agreement Questioned in Colorado Casualty Insurance v Safety Control Company, et al.
February 10, 2012 — CDJ Staff
Safety Control and EMC appealed the judgment in Colorado Casualty Insurance Company versus Safety Control Company, Inc., et al. (Ariz. App., 2012). The Superior Court in Maricopa County addressed “the validity and effect of a Damron agreement a contractor and its excess insurer entered into that assigned their rights to sue the primary insurer.” Judge Johnsen stated, “We hold the agreement is enforceable but remand for a determination of whether the stipulated judgment falls within the primary insurer’s policy.”
The Opinion provides some facts and procedural history regarding the claim. “The Arizona Department of Transportation (“ADOT”) hired DBA Construction Company (“DBA”) to perform a road-improvement project on the Loop 101 freeway. Safety Control Company, Inc. was one of DBA’s subcontractors. As required by the subcontract, Safety Control purchased from Employer’s Mutual Casualty Company (“EMC”) a certificate of insurance identifying DBA as an additional insured on a policy providing primary coverage for liability arising out of Safety Control’s work.”
A collision occurred on site, injuring Hugo Roman. Roman then sued ADT and DBA for damages. “Colorado Casualty tendered DBA’s defense to the subcontractors, including Safety Control. Safety Control and EMC rejected the tender. Roman eventually settled his claims against DBA and ADOT. DBA and ADOT stipulated with Roman for entry of judgment of $750,000; Roman received $75,000 from DBA (paid by Colorado Casualty) and $20,000 from ADOT, and agreed not to execute on the stipulated judgment. Finally, DBA, ADOT and Colorado Casualty assigned to Roman their rights against the subcontractors and other insurers.”
Colorado Casualty attempted to recover what “it had paid to defend DBA and ADOT and settle with Roman. However, Roman intervened, and argued that “Colorado Casualty had assigned its subrogation rights to him as part of the settlement agreement.” The suit was not dismissed, but the Superior Court allowed Roman to intervene. “Roman then filed a counterclaim against Colorado Casualty and a cross-claim against the subcontractors.”
All claims were settled against all of the defendants except Safety Control and EMC. “The superior court ruled on summary judgment that EMC breached a duty to defend DBA and that as a result, ‘DBA was entitled to settle with Roman without EMC’s consent as long as the settlement was not collusive or fraudulent.’ After more briefing, the court held the stipulated judgment was neither collusive nor procured by fraud and that EMC therefore was liable to Roman on the stipulated judgment and for his attorney’s fees. The court also held Safety Control breached its subcontract with DBA by failing to procure completed-operations insurance coverage and would be liable for damages to the extent that EMC did not satisfy what remained (after the other settlements) of the stipulated judgment and awards of attorney’s fees.” Safety Control and EMC appealed the judgment.
Four reasons were given for the decision of the ruling. First, “the disagreement between Roman and Colorado Casualty does not preclude them from pursuing their claims against EMC and Safety Control.” Second, “the settlement agreement is not otherwise invalid.” Third, “issues of fact remain about whether the judgment falls within the EMC policy.” Finally, “Safety Control breached the subcontract by failing to procure ‘Completed Operations’ coverage for DBA.”
In conclusion, the Superior Court affirmed in part, reversed in part, and remanded . “Although, as stated above, we have affirmed several rulings of the superior court, we reverse the judgment against EMC and remand for further proceedings consistent with this Opinion to determine whether the stipulated judgment was a liability that arose out of Safety Control’s operations. In addition, we affirm the superior court’s declaratory judgment against Safety Control but remand so that the court may clarify the circumstances under which Safety Control may be liable for damages and may conduct whatever further proceedings it deems appropriate to ascertain the amount of those damages. We decline all parties’ requests for attorney’s fees pursuant to A.R.S. § 12-341.01 without prejudice to a request for fees incurred in this appeal to be filed by the prevailing party on remand before the superior court.”
Read the court’s decision…
New Construction Laws, New Forms in California
July 10, 2012 — CDJ Staff
New construction laws came into effect in California on July 1. Writing for the Martindale-Hubble Legal Library, Glenn Mau, J. Michael McGuire, and John Tonsing, all of Archer Norris, discuss these changes. They note that the most important part of the changes to California construction law is that “all mechanics liens, stop notices and bond claims recorded after July 1, 2012 must use the new standardized forms and follow the new definitions, notice prerequisites and statutory release form language.”
Read the full story…
Florida Construction Defect Case Settled for $3 Million
June 19, 2012 — CDJ Staff
The Runaway Beach Club Condominium Association of Kissimmee, Florida has settled its construction defect claims against the parties involved in the construction and development of the buildings. The association claimed that defective roofs and improperly installed windows had lead to leaks and associated damages. A trial date had been set, but parties involved were able to reach this settlement instead.
Read the full story…
Construction Defect Not Occurrences, Says Hawaii Court
July 10, 2012 — CDJ Staff
Some insurers in Hawaii have made it clear that they will be covering construction defects, despite a court ruling concluding that defects are not occurrences, under Hawaii law. The case, heard by Hawaii’s Intermediate Court of Appeals found that “breach-of-contract claims based on allegations of shoddy performance are not covered under CGL policies and that tort-based claims derivative of such breach of contract claims also are not covered.”
Writing in Business Insider, Michael Bradford notes that the case, Group Builders Inc. and Tradewind Insurance Co. Ltd. vs. Admiral Insurance Co., involved improperly installed insulation at the Hilton Hawaiian Village’s Kalia Tower. Hilton was forced to close 21 floors due to extensive mold in guest rooms. Although the court did recognize this property damage, they did not feel it triggered insurance coverage, noting that if disputes over the quality of work were covered, CGL policies would become professional liability policies or performance bonds.
One critic of the decision, Warren C. Perkins, the risk manager at Boh Bros. Construction of New Orleans, noted that under the decision, “it doesn’t matter what the policy says and there is no need to investigate the policy wording.”
Read the full story…
Geometrically Defined Drainage Cavities in EIFS as a Guard Against Defects
July 10, 2012 — CDJ Staff
The blog Stucco & Insulation Contractor writes up some details on a “relatively new modification to modern Exterior Insulation Finish Systems,” known as “geometrically defined insulation boards.” They note that the insulation has grooves cut in the back to provide a route for water to drain, instead of getting trapped. They note that when EIFS is installed by a skilled applicator, this is unnecessary. However, with less experienced (and cheaper) installers, problems are more likely.
By cutting these channels, the application of EIFS is rendered “idiot proof,” as they note. Their preference would be that EIFS installers take the time to do the job right, but call this “a step in the right direction.”
Read the full story…
BUILD Act Inching Closer To Reality
July 8, 2011 — Douglas Reiser, Builders Counsel
A select group of Senators have launched a marketing campaign for the BUILD Act. If this is the first you are hearing about the BUILD Act, do not fret. The Act still has a long way to go, but if successful it would bring a national infrastructure bank.
I have been fascinated with the concept of a national infrastructure bank for quite some time. The idea has been around since the Clinton years ? and perhaps beyond. The Act’s purpose is to create a national bank (American Infrastructure Financing Authority) to provide loans and loan guarantees to encourage private investment in upgrading America’s infrastructure. For a number of years, we have seen similar legislation float around Congress. But, none of those initiatives have gained as much traction as BUILD.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com