Ohio Court of Appeals Affirms Judgment in Landis v. Fannin Builders
April 20, 2011 — April 20, 2011 Beverley BevenFlorez - Construction Defect Journal
The Ohio Court of Appeals affirmed the judgment in Landis v. William Fannin Builders. Landis contracted Fannin Builders to build their home. The case involved staining problems on the T1-11 siding chosen by the plaintiffs.
After a year and a half of discussion on how to resolve the problem of uneven staining on the siding, Landis filed suit “against Fannin Builders, alleging claims for breach of contract, breach of the express limited warranty, and violation of the Ohio Consumer Sales Practices Act (“OCSPA”). Fannin Builders, in turn, filed a third-party complaint against 84 Lumber, alleging claims for breach of contract and indemnification. With the trial court’s leave, Fannin Builders also later amended its answer to add a counterclaim against appellees for breach of contract and unjust enrichment. In the counterclaim, Fannin Builders alleged that appellees still owed it $3,908.98 for the construction of appellees’ home.”
“In its decision, the trial court found in appellees’ favor on their breach of contract claim and against appellees on their claims for breach of the express limited warranty and violation of the OCSPA. Additionally, the trial court found in Fannin Builders’ favor on its counterclaim for breach of contract and against Fannin Builders on its third-party claims for breach of contract and indemnity. The trial court determined that appellees’ damages amounted to $66,906.24, and after setting off the $3,908.98 that appellees owed Fannin Builders under the construction contract, the trial court awarded appellees $62,997.26. The trial court reduced its decision to judgment on May 18, 2010.”
Fannin Builders appealed this judgment and assigned the following errors:
[1.] The Trial Court Erred as a Matter of Law by Concluding that Appellant Breached its Contract with Appellees when it provided a Semi-Transparent Oil-Based Stain that Simply did not Meet their Approval.
[a.] The Contract does not Contain a Satisfaction Clause.
[b.] Even if the Court Implies a Satisfaction Clause, the Court Should Apply an Objective Standard.
[2.] The Trial Court Erred as a Matter of Law by Failing to Consider Appellant’s Right to Cure.
[3.] The Trial Court committed Reversible Error by not Assessing Damages Using “Diminished Value Standard,” and by Creating a Remedy that Constitutes Economic Waste.
[4.] The Trial Court Erred as a Matter of Law by Concluding that Appellant is Barred from Seeking Indemnification When 84 [Lumber] Never Fulfilled its Obligations Pursuant to the Settlement Agreement Entered on August 2, 2005.
In response to the first assigned error, the Court of Appeals stated: “Because the failure to provide siding of a uniform color, not appellees’ displeasure, breached the contract, we reject Fannin Builders’ contention that the trial court implied a satisfaction clause into the contract and found a breach of that clause. Accordingly, we overrule Fannin Builders’ first assignment of error.”
The Court of Appeals overruled the second assignment of error and provided the following reasoning: “Although Fannin Builders depends upon a term of the limited warranty for its right to cure, the trial court concluded that no breach of the limited warranty occurred. Fannin Builders breached the duty of workmanlike conduct implicit in the construction contract, not the limited warranty requiring it to satisfy the BIA’s Quality Standards. Consequently, the limited warranty does not apply to this case, and thus, it does not prevent appellees’ recovery of damages.”
The Appeals Court found “the trial court’s award of damages” was “both reasonable and supported by competent, credible evidence,” and therefore concluded “that the trial court did not err in setting appellees’ damages at $62,997.26.” The Fannin Builders third assignment of error was overruled.
The fourth and final assignment of error was also overruled by the Court of Appeals. “While Fannin Builders correctly asserts that 84 Lumber never installed the replacement siding, it ignores the fact that it ordered 84 Lumber to remove the replacement siding from appellees’ property. Thus, Fannin Builders precluded 84 Lumber from completely performing under the August 2, 2005 letter agreement. […] Consequently, Fannin Builders cannot now claim that the letter agreement is unenforceable or that it is entitled to indemnification from 84 Lumber. Because Fannin Builders assumed all liability for the defective siding in the letter agreement, it is responsible for appellees’ damages.”
James A. Zitesman, Columbus, Ohio Business Attorney, compared the case to Jones v. Centex (Ohio App. 2010), which had a different verdict:
“The common thread is the implied warranty of good workmanship. In the Jones case, the Court found that the buyers had in fact waived all implied warranties, including the implied warranty of good workmanship. In the contract between Jones and Centex, the builder stated that it “…would not sell the property to Purchasers without this waiver.” Probably should have been a sign to the buyers.
In the Landis case, the Court stated, “Contracts for the future construction of a residence include a duty, implied by law, that the builder must perform its work in a workmanlike manner.” The Court gave significant weight to the concept of the implied warranty of good workmanship. The builder relied upon the BIA Warranty which limits builders’ liability and exposure to legal issues. The trial court concluded there was no breach of the limited warranty, rather the builder “breached the duty of workmanlike conduct implicit in the construction contract, not the limited warranty requiring it to satisfy the BIAs Quality Standards.”
The Supreme Court of Ohio has accepted the Jones v. Centex Homes case for review.
Read the full story...
Cleveland Condo Board Says Construction Defects Caused Leaks
March 1, 2012 — CDJ Staff
A Cleveland condo association has sued the developer of their building, claiming that construction defects resulted in water intrusion. The K&D Group, which still owns forty units in the 160-unit building, claim that it’s a maintenance issue that they’d like to see fixed, but it’s their responsibility as the developer. Doug Price, CEO of K&D calls it a “frivolous lawsuit.” He blames a “hostile board” and told The Plain Dealer “there’s simple maintenance that they refuse to do.”
An outside company evaluated Stonebridge Towers. According to the condo board’s lawyer, Laura Hauser, the building design and construction are to blame for the water intrusion. Hauser said that the board’s “goal through this litigation is to find a resolution for the association, the building and the owners.”
David Kaman, a Cleveland attorney not involved in the lawsuit, told the Plain Dealer that construction litigation in the Cleveland area had fallen off from 2007, but he sees it on the rise, which he attributes to cost-cutting on recently finished projects. “If an owner moves in and two years later the wallpaper needs to be replaced because the wall is leaking, that’s a construction defect.”
Read the full story…
Harmon Towers Duty to Defend Question Must Wait, Says Court
March 1, 2012 — CDJ Staff
The Harmon Towers project in Las Vegas was eventually halted short of the planned forty-seven stories after “it was determined that there was substantial defective construction, including defective installation of reinforcing steel throughout the Harmon.” The American Home Insurance Company and Lexington Insurance Company put forth a claim that they had no duty to defend Perini Construction, the builder of the defective Harmon Towers. Further, American Home seeks to recover the monies American reimbursed Perini. The United States District Court of Nevada ruled in the case of American Home Assurance Co. v. Perini Building on February 3, 2012.
The two insurance companies covered Perini and its subcontractors, Century Steel, Pacific Coast Steel, and Ceco Concrete Construction. Century Steel was the initial subcontractor for the reinforcing steel; they were later acquired by Pacific Coast Steel. In this current case, Perini Construction is the sole defendant.
Perini sought a dismissal of these claims, arguing that without the subcontractors joined to the case, “the Court cannot afford complete relief among existing parties.” The court rejected this claim, noting that the court can determine the duties of the insurance companies to Perini, which the court described as “separate and distinct from those of the subcontractors.” The subcontractors “have not claimed an interest in the subject matter of the action.” The court concluded that it could determine whether Perini was entitled or not to coverage without affecting the subcontractors. The court rejected Perini’s claim.
Perini also asked the court to abstain from the case, arguing that it was better heard in a state court. The court noted that several considerations cover whether a case is heard in state or federal courts. The court noted that if the case weighed heavily on state law, the state courts would be the obvious location. Further, if there were a parallel action in the state courts, “there is a presumption that the whole suit should be heard in state courts.” This is, however, no parallel state suit, although the court noted that Perini has “threatened” to do so.
However, the issue of who is to blame for the problems at Harmon Towers has not been resolved. The court concluded that until the “underlying action” was concluded, it was premature to consider the issues raised in this case while the earlier lawsuit was still in progress. The court denied Perini’s motion to dismiss the case. Given that the outcome of the earlier construction defect case may lead to further litigation in state court, the District Court granted Perini’s motion to abstain, but staying their judgment until the construction defect case is resolved.
Read the court’s decision…
Avoid Gaps in Construction Defect Coverage
July 10, 2012 — CDJ Staff
The language may be standardized, but the way different states’ courts interpret it is not. That’s the problem discussed by William F. Knowles and Brendan Winslow-Nason in an article in Business Insurance. One of the major issue through the country is whether a construction defect claim and the resultant damage are an occurrence. Additionally, there are questions whether certain exclusions apply, such as “your work” or “your product” exclusions. They note that many courts “ agree that they are intended to exclude defective construction itself, while providing coverage for unintended consequences.” They further note that these are not the only insurance issues, “making it difficult for construction companies operating across state lines to ensure adequate coverage.”
Their recommendations to contractors are that they pay careful attention to where they’ve done business and “if the states have issued decisions or if there is legislation in place address the scope of coverage under additional insured endorsements.” Additionally, they suggest determining whether a contractor can negotiate a choice of law provision in their policy. The conclude that “construction companies can take proactive steps to protect themselves by identifying the applicable states’ laws, determining whether insurance is adequate under those laws, and then taking steps to resolve any gaps in their coverage.”
Read the full story…
Bad Faith and a Partial Summary Judgment in Seattle Construction Defect Case
February 10, 2012 — CDJ Staff
The US District Court of Washington has issued a ruling in the case of Ledcor Industries v. Virginia Surety Company, Inc. Ledcor was the builder of a mixed-use real estate project in Seattle called the Adelaide Project. Ledcor purchased an insurance policy from Virginia Surety covering the project. After the completion of the project, Ledcor received complaints of construction defects from the homeowners, which they forwarded to Virginia Surety.
Virginia Surety denied coverage on several grounds. Absent any lawsuit, Virginia claimed that there was “not yet any duty to defend or indemnify.” Further, as the policy commenced ten days after work on the project was substantially completed, Virginia cited a provision in the policy that excluded coverage for damage that occurred before the policy began. As problems included water intrusion, Virginia noted an exclusion for fungal damage. Finally, Virginia noted that it was not clear whether damage was due to Ledcor’s own actions.
The homeowners sued over the construction defects. Ledcor settled these suits before trial. In this, they were defended by, and settlements were paid by American Home, another of Ledcor’s insurers. Ledcor claims that Virginia Surety acted in bad faith by denying coverage and by its failure to investigate the ongoing nature of the work at the project.
The judge determined that Virginia Surety acted in bad faith when it invoked the fungus exclusion. Virginia noted that fungal damage “‘would have been’ referenced in the list of construction defects,” however, the HOAs claimed only “water stains” and “water damage,” and made no mention of mold or fungus. The court found that Virginia Surety “was not entitled to deny coverage simply because it may have suspected that mold or fungus damage existed.” The court noted that further proceedings would be needed to determine what portion of the settlement Virginia is obligated to pay.
The court found that there were matters of fact to be determined on the further issues in the case. The judge wrote that although Virginia acted in bad faith in invoking the fungus exclusion, it still had to be determined if they were in breach of contract by failing to defend Ledcor. Ledcor still needs to show that the damages claimed by the HOA were due to work actually covered by Virginia Surety.
Ledcor made an additional claim that Virginia Surety violated Washington’s laws concerning the insurance industry. Here, the court noted that the improper exclusion for fungus issues “constitutes a per se unfair trade practice.” Six other claims were made under this law. The court found that Virginia Surety did not misrepresent “pertinent facts or insurance policy provisions.” It also issued its denial letter promptly, satisfying the fifth provision. However, Virginia Surety did violate the second provision, in that it failed “to acknowledge and act reasonably promptly upon communications with respect to claims.” Two other issues could not be determined.
Judge Martinez’s decision granted a summary judgment to Ledcor on the issue of bad faith. An additional summary judgment was granted that Virginia Surety violated Washington’s Insurance Fair Conduct Act. Judge Martinez did not grant summary judgment on any of the other issues Ledcor raised.
Read the court’s decision…
Georgia Supreme Court Rules Construction Defects Can Constitute an Occurrence in CGL Policies
April 5, 2011 — April 5, 2011 Beverley BevenFlorez - Construction Defect Journal
Recently, the Supreme Court of Georgia reversed the decision in American Empire Surplus Lines Insurance Company v Hathaway Development Company, Inc. stating that because Whisnant’s faulty workmanship caused damage to the surrounding properties, the construction defects constituted “occurrences” under the Commercial General Liability (CGL) policy. Unlike the South Carolina Supreme court ruling in the case of Crossman Communities v Harleysville Mutual, the Georgia Supreme Court stated that an accident can happen intentionally if the effect is not the intended result.
Interestingly, the only dissenting judge, J. Melton, disagreed with his colleagues on the basis that “although the term ‘accident’ is not specifically defined in the policy, it is axiomatic that an ‘accident’ cannot result from ‘intentional’ behavior.” It is clear that what constitutes an occurrence in CGL policies is still being hotly debated.
Read the full story...
Ninety-Day Extension Denied to KB Home in Construction Defect Insurance Claim
July 10, 2012 — CDJ Staff
A magistrate judge has denied a request by KB Home Nevada to extend the time for service an additional ninety days. KB claims that St. Paul Fire & Marine Insurance Company has failed to defend them in a construction defect claim. However, the judge did grant KB an additional twenty days to effectuate service, noting that the request for additional time may be renewed.
Read the court’s decision…
California Supreme Court Binds Homeowner Associations To Arbitration Provisions In CC&Rs
September 13, 2012 — Stephen A. Sunseri and Aarti Kewalramani, Gatzke Dillon & Ballance LLP (http://www.gdandb.com).
The California Supreme Court ruled in Pinnacle Museum Tower Assn. v. Pinnacle Market Development (August 16, 2012, S186149) __ Cal.4th __ [2012 WL 3516134], that arbitration provisions within the covenants, conditions, and restrictions (“CC&Rs”) for condominium projects are enforceable against their homeowner associations. The ruling — two years in the making — was based on legislative history of laws governing common interest developments, and decades of decisional authority involving contracts and arbitration provisions.
In Pinnacle, a homeowners association sued a condominium builder for construction defects and resultant property damage to the common areas, and to the separate property interests held by the individual members. The builder moved to compel arbitration, based on a provision contained in the CC&Rs which required resolution of all construction disputes through binding arbitration. The association argued it could not be compelled to arbitrate these claims because it was not a party to the agreement to arbitrate, asserting “the Association did not bargain with [the builder] over the terms of the Project CC&R's or participate in their drafting.”
The Supreme Court rejected the association's argument on the grounds that the builder-authored CC&Rs complied with the Davis-Stirling Act (“the Act”) (Civil Code §1350, et seq.) ? the law that governs all common interest developments in California. Under the Act, builders and sellers of common interest residential units are required to provide a copy of the CC&Rs to all purchasers, as well as copies of the Department of Real Estate's public report, which informs purchasers of their rights and remedies as members of the association, and encourages each prospective purchaser to review the terms carefully before entering into any agreement. Further, the Act states all CC&Rs are enforceable, unless unreasonable, and inure to the benefit of and bind all owners in the development. (Civ. Code, §1354, subd. (a).) The Court found each owner who purchased a condominium in the project either expressly consented to the terms and provisions of the CC&Rs or was deemed to have consented to the terms at the time of purchase.
The Court also did not find the arbitration provision to be unconscionable. The Court indicated the provision was drafted and recorded in accordance with the Act, which allowed each prospective purchaser to make an informed decision prior buying a condominium unit. The provision also limited arbitration to construction defect disputes. The Court did not find any evidence the provision “shocked the conscience” or was “oppressive” in any way.
Pinnacle settles a decades-long conflict over whether arbitration provisions in CC&Rs for condominium projects are enforceable against homeowner associations and their members. It remains unclear, however, whether Pinnacle’s rationale will be applied to cases involving homeowner associations for single-family residences (as opposed to condominiums), assuming those CC&Rs have similar arbitration requirements. Regardless, the result of Pinnacle is clear, if arbitration provisions contained in condominium CC&Rs meet the fairness and unconscionability tests set out by the Court, more condominium construction defect cases brought by homeowner associations will be resolved through the arbitration process.
Read the court’s decision…
Printed courtesy of Stephen A. Sunseri and Aarti Kewalramani, Gatzke Dillon & Ballance LLP. Mr. Sunseri can be contacted at ssunseri@gdandb.com and Ms. Kewalramani can be contacted at akewalramani@gdandb.com.
Pipes May Be Defective, But Owners Lack Standing
September 13, 2012 — CDJ Staff
The United States District Court in Minnesota has determined that Steven and Cecilia Thundander cannot make a class-action claim against Uponor, Inc. over the plumbing in their home, as they do not have Article III standing. In this situation, the alleged defect is that Uponor made fraudulent claims that the pipes met National Sanitation Foundation (NSF) standards for use in potable water systems. Uponor submitted samples of other pipes, and their substitution was discovered when the NSF made an inspection of the manufacturing facility. The court noted that “the Thunanders contend that Uponor failed to inform homeowners, plumbers and consumers that it had been selling pipe that failed to meet NSF toxicity requirements at the time of sale and installation.”
The Court noted that the Thunanders have not tested their piping to determine if they “demonstrate toxicity or lack of compliance with the NSF 61 standards,” noting also that the Complaint seeks to require Uponor to instruct the plaintiffs on “how to test the piping and water to determine the level of risk.” Lacking testing, the Court could not find that the Thundanders have defective pipes. The Court found that the “Plaintiffs have failed to adequately plead an injury in fact sufficient to confer standing as to their product liability claims.”
The Court also concluded that it could not determine if the Plaintiff’s warranty actions could not be applied, as they “have failed to allege a plausible defect.” Even in the presence of a defect, the Court noted that more than eight years had passed before the filing of the suit, when the warranties under both Indiana and Minnesota law have a four-year statute of limitations. The Court also rejected the Thunanders tort claims, once again because “Plaintiffs have not tested their pipes,” noting that “a tort requires the existence of an injury.”
In conclusion, Judge Nelson rejected the entirety of the complaint, granting the motions to dismiss by the defendants. However, despite the problems with the Thunanders’ claims, she found that they were not “patently frivolous or groundless.” Therefore, she denied attorney fees requested by one of the defendants.
Read the court’s decision…
New Safety Standards Issued by ASSE and ANSI
March 28, 2012 — Melissa Dewey Brumback, Construction Law North Carolina
The American National Standards Institute (ANSI) and the American Society of Safety Engineers (ASSE) have recently announced their approval of two new safety standards to enhance construction site safety.
The two new standards, which are set to take effect during June 2012, are the ANSI/ASSE A10.1-2011 Pre-Project and Pre-Task Safety and Health Planning for Construction and Demolition Operations, and the ANSI/ASSE A10.26-2011 Emergency Procedures for Construction and Demolition Sites.
The new A10.1-2011 standard was designed to assist construction owners, contractors, and designers by ensuring that safety and health planning were standard parts of their pre-construction planning. It is also intended to help owners of construction sites to establish a process for evaluating constructor candidates with regard to their safety and health performance planning.
The A10.26 standard applies to emergency situations, including fires, collapses, and hazardous spills. The standard deals with emergency rescue, evacuation, and transportation of injured workers, and also plans for coordinating with emergency medical facilities ahead of potential disasters.
Read the full story…
Reprinted courtesy of Melissa Dewey Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
JDi Data Introduces Mobile App for Litigation Cost Allocation
October 23, 2012 — CDJ Staff
JDi Data of Fort Lauderdale, Florida has announced that they are about to release a mobile app for their Vendor Cost Control service. Their mobile app is a web app, and so can be used by customers on the iOS, Android, or Blackberry platforms. It provides a secure link to their database with no risk of releasing proprietary information. JDi Data notes that their product will allow users to “track their full subscribed case listings,” give them “easy access to carrier allocations, payments, and outstanding balances reports,” and to “call or email case managers directly from their mobile application.
James DeRosa, the founder of JDi Data says that “pushing the boundaries of technology has enabled us to further our goal of providing credible reporting and cost allocation expertise to insured, carriers and the legal community.”
Read the full story…
Continuous Trigger of Coverage Adopted for Loss Under First Party Policy
August 2, 2012 — Tred Eyerly, Insurance Law Hawaii
The Seventh Circuit predicted that the Wisconsin Supreme Court would adopt the continuous injury trigger for first party property loss that extends over several policy periods. Miller v. Safeco Ins. Co. of Am., 2012 U.S. App. LEXIS 12940 (7th Cir. June 25, 2012).
A home inspection report performed before the Millers purchased their home showed a soft spot on the roof. The stucco's finish color was also uneven and stained. Further, some water damage was found in the study and skylights above the kitchen sink. But the report advised that the exterior walls, chimney, grass roof, flashings, floor joists/beams and columns, garage walls and floor appeared serviceable. A roof specialist determined the soft spot was not significant and could be repaired for $1,500.
The Millers purchased a homeowner's policy from Safeco on June 30, 2005. The policy went into effect the next day when the Millers closed on the property. But the Millers did not see the policy's terms until Safeco mailed them a copy of the policy at the end of July.
Before receiving the policy, the Millers discovered severe inner wall water leaks and significant water infiltration on three of the home's exterior walls.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Pictorial Construction Terminology Dictionary — A Quick and Helpful Reference
July 10, 2012 — CDJ Staff
Does it seem like contractors speak their own language? Construction defect professionals can be hampered by not knowing the terminology. The Bert L. Howe & Associates, Inc. web site has a handy Pictorial Construction Terminology Dictionary in which more than a thousand terms are not only defined, but illustrated with pictures that give a visual component to each definition.
Whether you’re wondering what a balustrade is, or you need to identify a joist girder, or hundreds of other terms, the Pictorial Construction Terminology Dictionary is there to help you. It can be found at http://www.berthowe.com/bhapedia.php.
New Buildings in California Soon Must Be Greener
June 19, 2012 — CDJ Staff
The California Energy Commission has approved new energy efficiency standards for new homes and commercial buildings. The 2013 Building Energy Efficiency Standards are set to go into effect on January 1, 2014, and will require 30% more energy efficiency for non-residential construction and 25% more for homes. The standards do not affect hospitals, nursing homes, or prisons.
Buildings covered under the standard will have to have roofs that ready for the installation of solar panels. Additionally, non-residential buildings will require high-performance windows, advanced lighting controls, and cool-roof technologies. Residential requirements include insulated hot-water pipes, whole house fans, and more efficient windows.
The new standards are expected to add 3,500 new building industry jobs. One thing these construction workers won’t be building are power plants, since over the next thirty years, the standards are expected to save as much as six power plants.
Read the full story…
Firm Sued For Construction Defects in Parking Garage
October 23, 2012 — CDJ Staff
Northhampton County, Pennsylvania is suing a contractor who resurfaced a parking garage in 2009. According to the Express-Times, three years later, the surface is cracked and the county is seeking $700,000 for repairs. Additionally, they have withheld $44,000 of the $2.2 million contract because of the problems. John Stoffa, Northampton County Executive, says that the garage is stable, but not up to safety standards.
Read the full story…
Ohio “property damage” caused by an “occurrence.”
May 18, 2011 — May 18, 2011 - CDCoverage.com
In JTO, Inc. v. State Automobile Mut. Ins. Co., No. 2010-L-062 (Ohio Ct. App. March 25, 2011), general contractor JTO was sued by hotel project owner Marriott for breach of contract and warranties seeking damages for the repair of construction defects resulting in moisture penetration property damage to interior components. JTO filed a third party complaint against subcontractor Farizel and also tendered its defense as an additional insured under Farizel’s State Auto CGL policy.
Read the full story…
Reprinted courtesy of CDCoverage.com
Census Bureau, HUD Show Declines in Residential Construction
May 17, 2011 – CDJ Staff
The U.S. Census Bureau and the Department of Housing and Urban Development released their summary of residential construction for April 2011 on May 17.
Building permits for privately owned housing units were down 4% from last month and 12% from last year. Similarly, privately-owned housing starts were down 10% from March and 23% below the previous year.
For further details, read the Census Bureau/HUD report
Court Strikes Down Reasonable Construction Defect Settlement
December 20, 2012 — CDJ Staff
The Court of Appeals of Washington has struck down a construction defect settlement between a building owner and the companies she hired to repair the siding, among other repairs to bring the building up to code. Yuan Zhang hired Hawk Construction LLC to do repair work. Hawk, in turn, hired Ready Construction LLC for some aspects of the project. Hawk and Ready were both insured by Capital Specialty Insurance Corporation.
There were several problems with Ready’s work. After removing old siding, they did not protect the building, nor did they remove all of the damaged layers. Ready covered, but did not fix, a mildew problem under the old siding. When new siding was reattached, the nails used were too short to adequately attach it.
After paying for an inspection of the work, Zhang had Hawk and Ready begin the repairs again, but the work was abandoned without being completed. Zhang sued Hawk for breach of contract. Hawk then sued Ready, claiming that “Ready was liable to Hawk to the extent that Hawk was liable to Zhang.” Capitol retained defense for both contractors.
Zhang settled with Hawk, in an agreement that gave her “the right to collect and/or pursue all costs and attorney fees paid by Hawk or its insurance company defending against the Zhang’s claims and pursuing claims against Ready.” Subsequently, she also settled with Ready. Both companies ceased operations.
Zhang had the settlements reviewed by a court, which concluded that the settlements were reasonable. Capital was allowed to appeal, claiming that the settlement included costs that were Zhang’s responsibility. The appeals court did not examine the question of the reasonableness of the settlement, concluding that Capitol’s interests were relevant only to “questions of bad faith, collusion, and fraud.”
In the case of Zhang, the court concluded that the relationship between Zhang and her former contractors was collusive. The court noted that “bad faith or collusion may exist when the evidence indicates a joint effort to create, in a non-adversarial atmosphere, a resolution beneficial to both parties, yet highly prejudicial to the insurer as intervener.” The court noted that both companies had minimal assets which were, in any case, exempted from the agreement. Further, the court found that the agreements failed to determine “what amount of the repairs related to preexisting water damage.” Zhang’s calculation of costs also included her expenses for architectural and engineering services, which the court points out, “where always Zhang’s costs to bear.”
The court concluded that “the overall structure of the settlements is highly probative of collusion, fraud, or bad faith.” Zhang’s agreements with Hawk and Ready allowed her to collect compensation from Hawk and then collect Ready’s compensation to Hawk for their portion of the settlement, allowing Zhang to collect the monies twice. Further, she was allowed to pursue Capitol for Hawk’s attorney expenses, even though Hawk had none. “The right to recover Hawk’s fees merely set up a windfall recovery for Zhang.” The court described the agreements among Zhang, Hawk, and Ready as “precisely the type of manipulation [the law] is intended to preclude.”
Read the court’s decision…
OSHA Cites Construction Firm for Safety Violations
August 16, 2012 — CDJ Staff
S.J. Louis Construction of Texas Ltd. has been cited by OHSH for one serious and one repeat safety violation, according to a report in Insurance Journal. OSHA officials saw S.J. Louis employees working in an unshored trench along a highway service road. The company had cited for this violation previously. Without shoring of trenches deeper than five feet there is a risk of serious injury or death.
Read the full story…