Colorado Senate Bill 12-181: 2012’s Version of a Prompt Pay Bill
May 10, 2012 — W. Berkeley Mann, Jr., Higgins, Hopkins, McLain & Roswell, LLC
A potentially important legislative bill has been introduced in waning days of the 2012 legislative session, which would change many of the commercial practices that prevail in the construction industry. Senate Bill 12-181 applies to all building and construction contracts and would prohibit any contract provision that requires a contractor, subcontractor, or supplier to waive their lien in advance of payment. It also would ban any “choice of law” provisions that make a Colorado-based construction contract subject to enforcement only in another state, or under the laws of another state.
The bill also seeks to change many existing commercial practices between contractors, subcontractors, and suppliers. It is presently unclear whether the bill allows parties to contract around these payment procedure provisions, or whether these requirements are simply “gap filling” provisions that pertain if there are no written contract terms specified on these issues. The proposed statute would mandate payment to subcontractors and material suppliers due within seven days in the absence of a dispute about the work or materials being billed. After this seven day period, the bill would require the payment of interest at the rate of 1.5% monthly (18% annually). In any later suit for payment, the creditor would also be able to collect reasonable attorneys’ fees. Additionally, non-payment to a subcontractor or supplier who is later found to be entitled to prompt payment would excuse the subcontractor or supplier, and its surety bond provider, from any further performance under the contract.
It is presently unclear whether the bill allows parties to contract around these payment procedure provisions. However, it is clear that the bill provides some leeway for change orders, as long as there is (1) negotiation in good faith between the parties concerning the changed scope of work, and (2) a 50% payment of a subcontractor’s costs by the changing party within 30 days of the change order work being done. Additionally, the bill provides for retainage, but in an amount of no more than 5%.
The bill is presently set for hearing before the Colorado Senate Committee on Business, Labor, and Technology Committee on May 2, 2012 at 1:30 p.m.
Read the full story…
Reprinted courtesy of W. Berkeley Mann, Jr. of Higgins, Hopkins, McLain & Roswell, LLC. Mr. Mann can be contacted at mann@hhmrlaw.com.
Faulty Workmanship may be an Occurrence in Indiana CGL Policies
April 7, 2011 — April 7, 2011 Beverley BevenFlorez - Construction Defect Journal
The question of whether construction defects can be an occurrence in Commercial General Liabilities (CGL) policies continues to find mixed answers. The United States District Court in Indiana denied the Plaintiff’s Motion for Summary Judgment in the case of General Casualty Insurance v. Compton Construction Co., Inc. and Mary Ann Zubak stating that faulty workmanship can be an occurrence in CGL policies.
Judge Theresa L. Springmann cited Sheehan Construction Co., et al. v. Continental Casualty Co., et al. for her decision, ”The Indiana Supreme Court reversed summary judgment, which had been granted in favor of the insurer in Sheehan, holding that faulty workmanship can constitute an ‘accident’ under a CGL policy, which means any damage would have been caused by an ‘occurrence’ triggering the insurance policy’s coverage provisions. The Indiana Supreme Court also held that, under identically-worded policy exclusion terms that are at issue in this case, defective subcontractor work could provide the basis for a claim under a CGL policy.”
As we reported on April 1st, South Carolina’s legislature is currently working on bill S-431 that would change the wording of CGL policies in their state to include construction defects. Ray Farmer, Southwest region vice president of the American Insurance Association spoke out against the bill. “CGL policies were never meant to cover faulty workmanship by the contractor,” he said. “The bill’s supplementary and erroneous liability provisions will only serve to unnecessarily impact construction costs in South Carolina.”
Read the Opinion and order...
Read the court’s ruling...
Read the American Insurance Association statement...
Allowing The Use Of a General Verdict Form in a Construction Defect Case Could Subject Your Client to Prejudgment Interest
August 16, 2012 — Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC
A recent opinion from the Colorado Court of Appeals is a cautionary tale concerning the calculation of pre-judgment interest. See Hendricks v. Allied Waste Transportation, Inc., 2012 WL 1881004 (Colo. App. 2012). The Hendricks sued Allied after one of its drivers backed into the corner of their home with an Allied garbage truck. At trial, a jury awarded the Hendricks $160,100 in damages. Although the jury was instructed on the cost of repairs, diminution in value, and non-economic damages, the parties agreed to a general verdict form that did not ask the jury to specify the types of damages awarded. Id. at *1. The Hendricks sought to amend the judgment to include prejudgment interest and costs, which the trial court granted.
Allied appealed, arguing that the trial court erred by awarding the Hendricks prejudgment interest from the date their property was damaged. Id. at *7. The Colorado Court of Appeals found no error, and affirmed.
Read the full story…5
Reprinted courtesy of Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC. Ms. Anderson can be contacted at anderson@hhmrlaw.com
Safer Schools Rendered Unsafe Due to Construction Defects
February 10, 2012 — CJD Staff
Built on a program for safer school buildings, schools in Neenan County, Colorado have been shown to have mild-to-moderate structural problems, rendering some of them unsafe. The Denver Post reports that a third-party review of schools built by the Neenan Company has shown structural issues in all fifteen school buildings.
One school, Meeker Elementary, has been closed as it could collapse under high winds or during an earthquake. Sargent Junior-Senior High School is in use, but there are plans to evacuate the buildings if winds exceed 25 mile per hour. Two schools have roofs that are unable to bear expected loads of snow during the winter.
The Neenan Company says that the school buildings are not up to their standards and is working with the school districts to repair the buildings. Repairs are expected to be complete by August.
Read the full story…
MGM Seeks to Demolish Harmon Towers
September 1, 2011 — CJD Staff
Citing public safety concerns and the cost of repair, MGM Resorts International is seeking to demolish the unfinished hotel tower. The company has a few hurdles to go through before they start laying the charges to implode the structure. Any plans would have to be approved by not only Clark County officials, but also the district court has an order blocking any activity during litigation between MGM and the general contractor on the project, Perini Building Company.
Architectural Record reports that MGM states it would take “approximately 18 months to conduct test and come up with an approved, permitted design to fix the Harmon.” MGM feels that repairs would then take another two to three years. Perini contends that they could “provide stamped drawings detailing all necessary repairs within three months.” They attribute MGM’s desire to demolish the building as “buyer’s remorse.”
Read the full story…
New Jersey Court Rules on Statue of Repose Case
May 26, 2011 — CDJ Staff
A three-judge panel issued a per curium ruling on May 23 in Fairview Heights Condo. v. Investors (N.J. Super., 2011), a case which the members of a condominium board argued: “that the judge erred by: 1) dismissing plaintiff’s claims against RLI based upon the statute of repose; 2) dismissing the breach of fiduciary duty claims against the Luppinos based upon a lack of expert opinion; 3) barring the testimony of Gonzalez; and 4) barring the May 23, 1989 job site report.” The court rejected all claims from the condominium board.
The court found that the building must be unsafe for the statute of repose to apply. They noted, “the judge made no findings on whether the water seepage, or the property damage caused by such seepage, in any way rendered the building, or any of the units, unsafe.” Further, “without a specific finding on the question of whether the defects had rendered the building ‘unsafe,’ defendants were not entitled to the benefit of the ten-year statute of repose.“
On the second point, the court also upheld the lower court’s findings regarding the management company:
“The report submitted by Berman establishes that the EIFS product was defective in its design and would therefore have failed from the outset. The defects in that product were, according to Berman, not prone to repair or other mitigation. Therefore, even if defendants did not appropriately inspect or repair the EIFS, their failure to do so would have had no impact on the long-term performance of the EIFS exterior cladding. As plaintiff failed to raise a genuine issue of material fact on these questions, the judge properly granted summary judgment to the Luppinos on plaintiff’s breach of fiduciary duty claim.”
On the final two points, the judges noted “plaintiff maintains that the judge committed reversible error when he excluded the Gonzalez certification and the 1989 job site report prepared by Raymond Brzuchalski.” They saw “no abuse of discretion related to the exclusion of the Gonzalez certification, and reject plaintiff’s arguments to the contrary.” Of the job site report, they found, “no abuse of discretion in the judge's finding that the Brzuchalski 1989 job site report did not satisfy the requirements of N.J.R.E.803(c)(6).”
Read the court’s decision
Green Buildings Could Lead to Liabilities
March 28, 2012 — CDJ Staff
Attempts to build “green,” reducing energy costs and increasing the use of sustainable building materials, may lead to more lawsuits, according to a report issued by the British Columbia Construction Association. The report warned those who were going to build green look into the implications. The report looked at the result of green building practices and requirements adopted in the United States.
The report warns that “the use of novel, less harmful building material or new construction techniques may give rise to liability due to: contractor inexperience with installation; lack of long-term evaluation of green materials; lack of understanding of how new building materials may impact existing traditional building systems; or warranties provided unintentionally about the durability or effectiveness of unproven materials or techniques.”
Manley McLachlan, president of the BCAA noted that they are aware of “legal action around the performance of the buildings,” noting that while fast-growing trees help toward LEED certification, their wood is more prone to mold. He also felt that low-VOC paints needed more testing to prove their durability as exterior finishes.
Read the full story…
Defense for Additional Insured Not Barred By Sole Negligence Provision
August 11, 2011 — Tred Eyerly, Insurance Law Hawaii
A general contractor was entitled to a defense as an additional insured when the underlying complaint did not allege it was solely negligent. A-1 Roofing Co. v. Navigators Ins. Co., 2011 Ill. App. LEXIS 656 (Ill. Ct. App. June 24, 2011).
A-1 was the general contractor for a roof resurfacing job at a high school. Jack Frost Iron Works Inc. (“Frost”) was one of A-1’s subcontractors. Frost had a CGL policy with Navigators Insurance Company under which A-1 was an additional insured.
An employee of Frost’s subcontractor Midwest Sheet Metal Inc. was killed at the job site when a boom-lift he was operating flipped over. The boom-lift had been leased by another Frost subcontractor, Bakes Steel Erectors, Inc. (BSE). The deceased's estate filed suit against A-1, BSE and two other defendants.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Contractor Manslaughter? Safety Shortcuts Are Not Worth It
August 11, 2011 — Douglas Reiser, Builders Counsel
It’s been a while since I discussed the importance of safety. But, a recent article on ENR.com compelled this brief article. Don’t shortcut safety — you could be facing serious criminal repercussions.
A New York crane company owner and one of his employees are each facing a second-degree manslaughter charge for the death of two construction workers.  The charges stem from the collapse of a crane in New York City. The district attorney determined that the crane owner cut a few corners to reduce its operation costs, significantly sacrificing safety.
Another example was the 2010 trial of another New York crane operator who was charged with manslaughter. In that case, the criminal charges failed to stick, but an administrative judge found that the contractor used a damaged sling to support the steel collar binding the tower-crane mast to the 18th floor of a high-rise building being constructed. The company also used four slings instead of the eight, as specified by the crane manufacturer; improperly attached the slings and failed to pad or soften them.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Colorado Court of Appeals holds that insurance companies owe duty of prompt and effective communication to claimants and repair subcontractors
March 1, 2011 — Courtesy
Colorado Construction LitigationIn Dunn v. American Family Insurance, 09CA2173, 2010 WL 4791948 (Colo. App. Nov. 24, 2010), the Dunns reported a claim to American Family on their homeowners insurance policy after sewer and water backup caused sewage to flood their basement. American Family gave the Dunns contact information for a contractor (ICA) to remediate the flooding. However, ICA was unsuccessful and sewage began to infiltrate the Dunns’ HVAC system. Subsequently, black mold was detected in the HVAC system, the Dunns suffered health and respiratory problems, and they soon after vacated the home. The Dunns hired and fired two more contractors for unsatisfactory work throughout the winter before hiring a fourth to finish the job. Because the home remained vacant and unheated throughout the winter, the water pipes ruptured. The mold spread throughout the entire home and all of the contents needed to be replaced, which amounted to a claim of $340,000 on the policy.
American Family agreed to pay the full $340,000. However, the Dunns brought suit claiming that American Family breached the implied duty of good faith and fair dealing by: 1) failing to screen ICA for expertise; 2) failing to screen ICA for liability insurance coverage; 3) failing to monitor ICA’s work; 4) failing to advise them that flooding can cause further damage, including freezing pipes and mold; and, 5) failing to adequately and promptly communicate with them and remediation subcontractors in the course of investigating and handling their claim.The trial court found no duty owed by American Family beyond adjustment and timely payment of claims. Because American Family paid timely and in full, they dismissed all of the Dunns’ claims. However, the Court of Appeals reversed in part.
Read the full story...
Reprinted courtesy of Chad Johnson, Higgins, Hopkins, McLain & Roswell, LLC. Mr. Johnson can be contacted at johnson@hhmrlaw.com
Construction Defect Claim Did Not Harm Homeowner, Court Rules
September 30, 2011 — CDJ Staff
The Minnesota Court of Appeals has ruled in Creswell v. Estate of Howe, a case in which a woman bought a home and then sued the seller’s estate, both sets of real estate agents, and the homeowner’s association over construction defects. A district court ruled against her, granting summary judgment to the other parties.
After buying a townhome “as is,” Catherine Creswell claims to have shared a thought with her agent that the homeowners association was, in the words of her agent, “trying to hide something.” Later, Creswell found that a few days before her closing, the board had discussed problems with “roofs, siding and soundproofing of the townhomes.” The court noted that “it was clear from the documents that appellant [Creswell] received that the association had known about various construction defects for many years, some of which affected [her] unit.”
Creswell initially sued the estate, the man who negotiated the sale for his mother’s estate, the real estate companies and the agents involved, the homeowners association, and four board members. Later she sued for punitive damages, dropped a claim for interference with contractual relations, and dismissed her claims against the individual board members. The court dismissed all of Creswell’s claims awarding costs to those she sued.
The appeals court has affirmed the decision of lower court, noting that Creswell “did not provide us with any argument why the district court erred in dismissing her unjust-enrichment, breach of contract, or rescission claims against the various respondents.” Nor did she provide evidence to support her claims of “breach of duty, fraud, and violation of consumer protection statutes.”
The court noted that Creswell could not sue the homeowners association over the construction defects because she “failed to prove that she was damaged by the association’s nondisclosure.” The court noted that “there are no damages in this case,” as Creswell “was never assessed for any repairs, she had not paid anything out-of-pocket for repairs, and she has presented no evidence that the value of her individual unit has declined because of the alleged undisclosed construction defects.”
The court granted the other parties motion to dismiss and denied Creswell’s motion to supplement the record. Costs were awarded to the respondents.
Read the court’s decision…
Restitution Unlikely in Las Vegas Construction Defect Scam
October 23, 2012 — CDJ Staff
The San Francisco Chronicle reports that the money lost in the Las Vegas HOA fraud cause is probably not recoverable. Victims of the scam have asked the court for restitution, but Judge Lloyd George doubts any of the money will be found, saying “the money is not available, it would appear.”
One Vistana board members not part of the conspiracy told reporters that the $8 million construction defect settlement never went for needed repairs. “Within six months that money was gone,” said Bruce Wallace, a retired Air Force colonel. After the construction defect account was depleted to $450,000, two board members disappeared with the funds.
Read the full story…
Florida “get to” costs do not constitute damages because of “property damage”
August 11, 2011 — CDCoverage.com
In Palm Beach Grading, Inc. v. Nautilus Ins. Co., No. 10-12821 (11th Cir. July 14, 2011), claimant general contractor Palm Beach Grading (?PBG?) subcontracted with insured A-1 for construction of a sewer line for the project.  A-1 abandoned its work and PBG hired another subcontractor to complete construction of the sewer line.  The new subcontractor discovered that A-1?s work was defective requiring repair and replacement of portions of the sewer line which also required the destruction and replacement of surrounding work.
Read the full story…
Reprinted courtesy of CDCoverage.com
Dust Infiltration Due to Construction Defect Excluded from Policy
September 9, 2011 — CDJ Staff
A summary judgment was affirmed in the case of Brown v. Farmers Group, by the California Court of Appeals. The Browns bought a new home in Oakley, California. At the time, they signed disclosure statement “acknowledging that the area around their home experienced gusty winds and would be in development for years to come, which might result in dust and airborne mold.”
The Browns found an unusual amount of dust in their home, which became worse when they ran their heating and air conditioning system. Shelia Brown was later diagnosed with chronic valley fever, which was attributed to airborne mold. The Browns contacted Farmers which investigated the house. Although the adjustor from Farmers said the Browns would be covered, Farmers denied the claim.
After the Browns moved out of the house, an inspector found that the HVAC line in the attic was disconnected, sending dust into the home. The Browns brought action against Mid-Century Insurance, which managed the policy, and Farmers. The identified the HVAC defect, window problems, and valley fever as causes, suing for breach of contact, breach of implied covenant of good faith and fair dealing, and the intentional infliction of emotional distress.
The court rejected all these claims. The policy with Farmers excluded losses due to defective construction. This ruled out the faulty HVAC system and any problems there might have been from the windows. The policy also specifically excluded losses from contamination, fungi, pathogens, and noxious substances. The court further found that the adjustor’s opinion was irrelevant to the question of what the policy actually covered. Finally, the court found no evidence of intentional infliction of emotional stress.
On review, the appeals court upheld the trial court’s conclusions and affirmed the summary judgment.
Read the court’s decision…
Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses
April 25, 2012 — Douglas Reiser, Builders Cousel
Ever had that lingering problem with a contracting partner that went away for awhile and then came back to bite you ? years later? In Washington, construction contract claims can be raised for up to six years after substantial completion. Six years!? Why would I want to wait that long to find out if I have a problem? You don’t have to.
Over the past few years, I have discussed the notion of “contractual claim periods” on The Builders Counsel. For today’s Save a Legal Fee column, I cannot think of a better topic. These provisions are specifically intended to save you from unnecessary legal fees that might arise if a problem goes unnoticed for too long.
Contractual claim periods are simply a way to reduce the amount of time that a contracting party has to raise a claim against its contracting partner. For example, a subcontractor might require that a general contractor raise any claim that it might have ? for defective or incomplete work, injury, damages, etc ? within a particular amount of time or forever lose the ability to raise the claim in a legal proceeding.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Discovery Ordered in Nevada Construction Defect Lawsuit
August 16, 2012 — CDJ Staff
Gemstone LVS was sued by the Manhattan Homeowners Association in Las Vegas, after which Chartis Specialty Insurance informed Gemstone that they “had no duty to defend or indemnify Gemstone under the Commercial Umbrella Liability Policy.” Gemstone “asserts that at the time the Policy was purchased, it was understood that Chartis would provide insurance coverage for a construction defect lawsuit” and now seeks discovery “to prove Chartis’ bad faith purpose in drafting an illusory Policy.”
The opinion notes that “the Court conducted a preliminary peek at the pending motion for partial summary judgment and finds that Chartis has not made the strong showing necessary to support the requested stay.” Further, the court notes that “when ambiguity in the language of a policy exists, the court may consider not only the language of the policy but also the ‘intent of the parties, the subject matter of the policy, and the circumstances surrounding its issuance.’” The court concludes that “this type of discovery is relevant to understanding the intent of the parties, more specifically, whether it was understood that Chartis would provide insurance coverage given the construction defect lawsuit.”
Accordingly, the court denied Chartis’ motion for stay of discovery and established a schedule for discovery, expert designations, rebuttal expert designations, and other matters related to the trial.
Read the court’s decision…
Construction Law Client Alert: Hirer Beware - When Exercising Control Over a Job Site’s Safety Conditions, You May be Held Directly Liable for an Independent Contractor’s Injury
April 6, 2011 — April 6, 2011 - By Mark VonderHaar and Yvette Davis in the Haight Brown & Bonesteel Blog
On February 24, 2011, the California Court of Appeal held in Jeffrey Tverberg, et al v. Fillner Construction, Inc. that the imposition of direct liability on a hirer turns on whether the hirer exercised retained control of worksite safety in such a manner that affirmatively contributed to the independent contractor’s injury. Twice, Tverberg, an independent contractor hired by a general contractor's subcontractor, asked the general contractor to make the job site safe by covering up open holes created by another unrelated subcontractor while Tverberg was working at the site. After Tverberg was injured at the site by falling in a hole, he sued both the general contractor and the subcontractor which had hired him.
The Court of Appeal reasoned that when the general contractor instructed another subcontractor to create a condition that was potentially dangerous (i.e., creating open and uncovered bollard holes), and simultaneously required Tverberg to perform unrelated work near the open holes, the general contractor s conduct may have constituted a negligent exercise of its retained control which affirmatively contributed to Tverberg’s injury. The Court also reasoned that the general contractor affirmatively assumed responsibility for the safety of the workers near the holes by only requiring stakes and safety ribbon, and negligently discharged that responsibility which resulted in injury.
Read the full story...
Reprinted courtesy of Mark VonderHaar and Yvette Davis of Haight Brown & Bonesteel. Mr. VonderHaar can be contacted at mvonderhaar@hbblaw.com and Ms. Davis at ydavis@hbblaw.com.
The Complete and Accepted Work Doctrine and Construction Defects
August 16, 2012 — CDJ Staff
Matthew C. Bouchard of Lewis & Roberts PLLC, writes how North Carolina is “bucking the trend” on the “complete and accepted work doctrine.” As he notes, in most states “a contractor can be found liable for personal injuries suffered by third parties from accidents occurring after the contractor’s work is completed and accepted.” But one exception is North Carolina.
He gives the example of a case, Lamb v. D.S. Duggins Welding, Inc., in which a site superintendent was “injured by the alleged negligence of the project’s steel deck installer, a sub-subcontractor in the contractual chain” “after the sub-sub’s work had been completed and accepted.” The trial court held that the “completed and accepted work doctrine” ended the subcontractor’s liability. The case noted that “employees of the general contractor had modified the installation of the perimeter safety cable in question after the sub-sub had demobilized from the site.”
Mr. Bouchard notes that “once a project is accepted and turned over, the contractor typically loses control over maintenance of the new facility.” However, he notes that “where the contractor’s work constitutes negligence ?Ķ the doctrine may not apply.” Nor does it end breach of contract claims. It only covers third parties.
Read the full story…