Read Her Lips: “No New Buildings”
November 18, 2011 — CDJ Staff
Martha Johnson, the head of the General Services Administration, has said that her agency will not be building any new buildings in the near future. Among other duties, the GSA is responsible for the building, renovating, and leasing of federal office space. The White House had proposed $840 million in new construction, the Senate only $56 million. The House did not appropriate any money for the agency to use for new construction.
In addition to cutbacks on new buildings, Congress is suggesting only $280 million in repairs of existing government buildings. In order to cut back, the GSA has dropped plans to renovate their own offices in favor of renovations at the Department of Homeland Security and the Food and Drug Administration.
Read the full story…
Florida trigger
May 18, 2011 — May 18, 2011 - CDCoverage.com
In Johnson-Graham-Malone, Inc. v. Austwood Enterprises, Inc., No. 16-2009-CA-005750-XXXX-MA (Fla. 4th Cir. Ct. Duval County, April 29, 2011), insured JGM was the general contractor for an apartment project completed in 1998. In 2007, the project owner sued JGM seeking damages for defective construction resulting in moisture penetration property damage. JGM tendered its defense to Amerisure. Amerisure denied a defense. JGM defended and settled the underlying suit and then filed suit against Amerisure seeking recovery of defense and settlement costs. The trial court granted JGM’s motion for partial summary judgment. The court first addressed Amerisure’s duty to defend. Applying Florida law, the court held that, although the underlying complaint alleged that the property damage was not discovered until after expiration of the Amerisure policies
Read the full story…
Reprinted courtesy of CDCoverage.com
Green Buildings Could Lead to Liabilities
March 28, 2012 — CDJ Staff
Attempts to build “green,” reducing energy costs and increasing the use of sustainable building materials, may lead to more lawsuits, according to a report issued by the British Columbia Construction Association. The report warned those who were going to build green look into the implications. The report looked at the result of green building practices and requirements adopted in the United States.
The report warns that “the use of novel, less harmful building material or new construction techniques may give rise to liability due to: contractor inexperience with installation; lack of long-term evaluation of green materials; lack of understanding of how new building materials may impact existing traditional building systems; or warranties provided unintentionally about the durability or effectiveness of unproven materials or techniques.”
Manley McLachlan, president of the BCAA noted that they are aware of “legal action around the performance of the buildings,” noting that while fast-growing trees help toward LEED certification, their wood is more prone to mold. He also felt that low-VOC paints needed more testing to prove their durability as exterior finishes.
Read the full story…
Defect Claims as Occurrences? Check Your State Laws
July 10, 2012 — CDJ Staff
Although four states have defined construction defect claims as occurrences, contractors are still dealing with “coverage gaps for faulty work construction,” says Mike Tsikoudakis in a piece at Business Insurance. He quotes Julian Ehrlich, the senior VP of claims for Aon Risk Services that “one of the interesting and compelling aspects of the issue of coverage for defective construction is that jurisdictions differ, so policyholders don’t know what they’re going to get.” He further notes that “in context of construction defect, the term ‘occurrence’ is ambiguous.”
One problem, as noted by Jeffrey J. Vita, a partner at Saxe Doernberger & Vita, is that construction firms end up needing to simultaneously defend against defect claims and to also file suit to be certain their insurance firms will cover claims. Insurance for construction defect claims is described as “expensive and somewhat limited.” Mr. Vita expects more states to help this situation with new laws, clarifying what is an occurrence.
Read the full story…
Home Repair Firms Sued for Fraud
September 30, 2011 — CDJ Staff
The Illinois Attorney General has filed a lawsuit in Cook County Circuit Court alleging that two connected firms took money from homeowners and then failed to perform the contracted work. One of the three defendants, Chris Bidigare, was an owner of agent of both Fairway Construction and Maintenance Services, LLC, and Rock Construction Management, LLC.
In once case, according to the article on the OakPark Patch, one homeowner provided a $111,000 down payment, only to have the company cancel the job and refuse to return the money. One homeowner was told by Fairway that she should contact their insurance provider. The insurance provider told her that Fairway’s insurance had been cancelled due to non-payment.
The suit seeks to bar the three defendants from working in home repair in Illinois.
Read the full story…
No-Show Contractor Can’t Hide from Construction Defect Claim
June 19, 2012 — CDJ Staff
The failure of R. J. Haas to produce documents or make himself available for deposition has worn out the patience of the US District Court in San Jose. Judge Howard Lloyd issued a ruling inProbuilders Specialty Ins. Co. v. Valley Corp. (N.D. Cal., 2012).
Probuilders issued an insurance policy covering Haas for their work on the construction of a single-family home for Ty and Karen Levine. The Levines sued Haas for “shoddy and incomplete work.” Probuilders contends that Haas “made material misrepresentations with respect to verifying that the subcontractors had insurance.” Since November 2011, Haas has been without legal counsel in this matter.
Despite Probuilder’s attempts, the court noted that “Hass any not provided any documents in response to the plaintiff’s three sets of requests for production of documents.” Haas also “has refused to make himself available for deposition.” Haas was first scheduled for deposition in September, 2011. Subsequently, Haas has rescheduled his deposition repeatedly, postponing it to January 4, then February 13, and then agreed to be deposed “before the then-scheduled March 15 mediation,” after which he said he would “be unavailable to be deposed before April.
The court noted that although Haas “hay have had legitimate reasons for wishing to continue his deposition, such as illness and his attempt to retain new counsel,” however, the court concluded that “Haas has had ample time to retain new counsel and prepare for deposition.
The court also found fault with Haas’s objections to certain terms in the Request for Admissions, among them “named,” “independent contractor,” and “work,” noting that Haas called these “vague and ambiguous.” The court called it “quibbling,” and noted that the federal courts disfavor this. Later in the decision, the court made it clear that Haas “is obligated under the Federal Rules of Civil Procedure to respond to discovery requests.” And concludes, “that he has apparently been seeking to retain new counsel for over five months does not give him license to ignore plaintiff’s discovery requests entirely.
The court granted Probuilders the option of filing a motion for sanctions. Mr. Haas did not attend or participate.
Read the court’s decision…
Lien Claimant’s Right to Execute against Bond Upheld in Court of Appeals
February 10, 2012 — Douglas Rieser, Builders Counsel
Stonewood v. Infinity Homes is a simple construction dispute over a matter of about $9,000.00. But sometimes these tiny little disputes turn into expensive legal battles over mere procedural quivering. In Stonewood, a small subcontractor won a big victory yesterday when the Divison 1 Court of Appeals upheld its judgment against a lien release bond posted by an owner.
Infinity Homes contracted with Stonewood Design to lay tile in one of its customer’s homes. Stonewood did the work, but Infinity withheld roughly $9,000.00 of the contract sums for what it alleged were trade damages left on the tile. The two parties were unable to come to an agreement over payment and Stonewood proceeded with a lien under RCW 60.04. It then filed an action to enforce the lien against the homeowner, Infinity and its bonding company.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Hovnanian Increases Construction Defect Reserves for 2012
January 6, 2012 — CDJ Staff
In their fourth quarter earnings call, executives of Hovnanian Enterprises made some projections for investors, covering the company’s plans for 2012. During the call, Ara K. Hovnanian, the firm’s CEO, discussed their reserves to meet construction defect claims. The firm does an annual actuarial study of their construction defect reserves.
Mr. Hovnanian noted that there have been no changes for the past several years, but this year they are increasing their reserves by about $6.3 million. Additionally, the firm has added $2.5 million to their legal reserves. Mr. Hovnanian stated “we do not anticipate that changes of this magnitude will be recurring as we look forward to 2012.”
Read the full story…
Condo Buyers Seek to Void Sale over Construction Defect Lawsuit
November 7, 2012 — CDJ Staff
A Michigan couple seeks to void their purchase of a condo in Texas after discovering that the complex was undergoing a construction defect lawsuit. ABQ Journal reports that Charles M. Lea and Olga Y. Ziabrikova said that they would not have purchased the condo if they had known the association was already alleging construction defects. The condo association discovered the defects “by at least late 2010,” according to the suit. The couple bought their condo in August 2011 and heard of the defects only in March 2012.
The couple notes that no one involved with the sale informed them of the construction defect complaints. The community association’s lawsuit states that problems have lead to $2.5 million in damages. The developer, Vegas Verde Condo Partners, have filed a general denial of the construction problems.
Read the full story…
Delays in Filing Lead to Dismissal in Moisture Intrusion Lawsuit
September 9, 2011 — CDJ Staff
The Alabama Court of Civil Appeals has upheld a summary judgment in the case of Franklin v. Mitchell. Walter Mitchell, doing business as Southern Classic Construction built a new home for the Franklins. The Franklins moved into the home in October 2001. In April 2006 they discovered sagging floors in both the bathroom and kitchen. They contacted Mitchell who suggested the flooring might be defective. The Franklins spent eight months attempting to contact the flooring manufacturer.
In March 2007, the Franklins had the home inspected. The sagging was determined to be due to a loss of strength in the decking because of condensation from the air conditioning system. Air returns were not properly sealed and drawing moisture into the structure. There was mold on the decking and floor joints.
When Mitchell was contacted by the Franklins, he told them his one-year warranty had expired but had the HVAC subcontractor, Southern Mechanical Heating & Air (owned by Mitchell’s father, Jim Mitchell), look at the situation. SMHA replaced and braced subfloors. Later, they entered the crawl space to tape ducts, seal the air return, and insulate the air vent housing. The Franklins were not satisfied with the repairs, as not all the ducts were taped, nor were the air vent housings insulated.
Franklin complained to Walter Mitchell who again cited his one-year warranty. Jim Mitchell said he would not report complaints to his insurer, stating that the repairs were unnecessary, that the work had been done correctly in the first place, and it was only done at the request of Walter Mitchell.
In February 2009, the Franklins sued Walker Mitchell. Mitchell denied the claims, citing in part the statute of limitations. Mitchell also filed complaints against three subcontractors, including his father’s firm. Mitchell received a summary judgment as the case started after Alabama’s six-year statute of limitations.
The appeals court rejected the Franklin’s argument that the claim of damage did not start until they were aware it was due to a construction defect. The court noted that as Walter Mitchell was licensed as a “residential home builder, the statute the Franklins cite did not apply, as it concerns architects, engineers, and licensed general contactors.”
Nor did they feel that Mitchells’ claim that his warranty had expired were sufficient to override the statute of limitations, quoting an earlier case, “Vague assurances do not amount to an affirmative inducement to delay filing suit.” Their claim of subsequent negligent repairs was rejected because Mitchell did not direct the specific actions taken by his father’s firm.
Read the court’s decision…
Bar to Raise on Green Standard
November 7, 2012 — CDJ Staff
Next June, members of the U.S. Green Building Council will be voting on changes to the LEED green building standard. “The bar is getting raised,” said Navad Malin of BuildingGreen, a consulting and publishing firm, in an article in USA Today. Under the proposed guidelines, builders would have to project energy and water use for five years as part of the certification process. However, if the occupants aren’t as green as the builders anticipated, the buildings will not lose their certification.
The new rules will include higher energy standards, award points for avoiding potentially hazardous materials, and even determine what kind of plumbing items can be used.
Read the full story…
Fifth Circuit Asks Texas Supreme Court to Clarify Construction Defect Decision
November 7, 2012 — CDJ Staff
The Fifth Circuit Court has withdrawn its decision in Ewing Construction Company v. Amerisure Insurance Company, pending clarification from the Texas Supreme Court of its decision in Gilbert Texas Construction, L.P. v. Underwriters at Lloyd’s London. The Fifth Circuit had applied the Gilbert case in determining that a contractual liability exclusion barred coverage for faulty workmanship. The Insurance Journal reports that this decision was both applauded and criticized, with a concern noted that “an insurer would now have its pick of either the ‘your work’ exclusion or the contractual liability exclusion without the exception for subcontracted work.”
The Fifth Circuit is now asking the Texas Supreme Court two questions to clarify Gilbert, which Brian S. Martin and Suzanne M. Patrick see as a sign that the Court has realized that it overly expanded the scope of the earlier ruling. A response is expected from the Texas Supreme Court by spring 2013.
Read the full story…
Construction Upturn in Silicon Valley
August 17, 2011 — CDJ Staff
Work resumed after nearly three years on an office tower in Santa Clara, according to the San Jose Mercury News. Work had stalled on the building due to the economy, but now the developer is planning a second five-story building on the site. Other dormant projects in the area are also getting restarted. Santa Clara County saw the addition of 1,800 construction jobs in June.
A spokesperson for the Operating Engineers Local 3 in Alameda told the paper, “two years ago we had five thousand folks on the out-of-work list. It’s now down to about 1,700.”
Read the full story…
Unit Owners Have No Standing to Sue under Condominium Association’s Policy
February 10, 2012 — Tred Eyerly, Insurance Law Hawaii
If a condominium owner suffers damage caused by a leak from another unit, may it sue the insurer for the Association of Apartment Owner (AOAO) for coverage? The federal district court for Hawaii said "no" in a decision by Judge Mollway. See Peters v. Lexington Ins. Co., 2011 U.S. Dist. LEXIS 148734 (D. Haw. December 27, 2011).
Two cases were consolidated. In each case, Plaintiffs owned condominium units at the Watercrest Resort on Molokai. Water leaking from another unit damaged Plaintiffs’ units.
Watercrest Resort was insured by Lexington pursuant to a policy maintained by the AOAO. Plaintiffs filed claims with Lexington. Lexington hired an adjustor.
Unhappy with the adjustment of their claims, Plaintiffs sued Lexington and the adjustor.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Nevada Assembly Sends Construction Defect Bill to Senate
June 6, 2011 — CDJ Staff
In a 26 to 16 vote, the Nevada Assembly has passed Assembly Bill 401, which extends the time limit for legal action over home construction defects. According to the Las Vegas Sun, Assembly member Marcus Conklin, Democrat of Las Vegas, said the bill was about “keeping the consumer whole.” However, Ira Hansen, Republican of Sparks, told the sun that suits are happening before contractors can make repairs. The bill would allow attorney fees even if repairs are made.
Read the full story…
After $15 Million Settlement, Association Gets $7.7 Million From Additional Subcontractor
November 7, 2012 — CDJ Staff
The stucco subcontractor for a condominium complex did not join in with the other defendants in a settlement of more than $15 million, preferring to take the case to a jury trial. That jury has found the stucco installer liable for $7.7 million to make repairs. Mark Wiechnik of Herrick Feinstein LLP wrote about the case on the Lexology web site. Mr. Wiechnik notes that the jury was shown “samples of rotted wood taken from the property as well as numerous pictures of damage resulting from the various defects.”
Read the full story…
Important Information Regarding Colorado Mechanic’s Lien Rights.
November 7, 2012 — David McLain, Colorado Construction Litigation
With payment problems in the construction economy having accelerated over the past few years, there has been a substantial increase in mechanic’s lien activity and associated litigation. The typical mechanic’s lien claimant is a material supplier, a trade subcontractor, or even a general contractor that has not been paid by the developer/owner of the construction project. The reason for filing a mechanic’s lien claim is that it offers the prospect in many cases to make the unpaid construction professional a priority creditor, with a lien on the real estate that is superior to the construction lender.
One of the primary rules governing a mechanic’s lien claim is that the creditor’s formal written “Notice of Intent to File a Mechanic’s Lien” (hereafter “Lien Notice”) must be (1) served on the owner of the property for which the work was done or the materials used, and (2) served at the same time on the general contractor who has handled the construction project. After the creditor has made service of the lien claim by USPS certified mail (using the green return receipt card for proof of service) or separate personal delivery of the notice to the property owner and general contractor, ten full days must pass (not including the date of mailing of the notices) before the lien notice is filed in the public records.
After ten days have expired following the date of mailing using certified mail, or personal delivery of the notice to the property owner and the general contractor, the lien notice can be filed to make the lien valid.
Reprinted courtesy of David M. McLain, Higgins, Hopkins, McLain & Roswell, LLC. Mr. McLain can be contacted at mclain@hhmrlaw.com
Read the full story…
Retaining Wall Contractor Not Responsible for Building Damage
July 20, 2011 — CDJ Staff
The Court of Appeals of Indiana ruled on July 8 in the case of Rollander Enterprises, Inc. v. H.C. Nutting Co. Judge Baily wrote the opinion affirming the decision of the trial court.
The case involved an unfinished condominium complex, the Slopes of Greendale, in Greendale, Indiana. Rollander is a real estate development company incorporated in Ohio. One of the issues in the case was whether the case should be settled in the Indiana courts or be tried in Ohio. The project was owned by a special purpose entity limited liability corporation incorporated in Indiana.
Rollander hired Nutting to determine the geological composition of the site. Nutting’s report described the site as “a medium plastic clay containing pieces of shale and limestone.” The court summarized this as corresponding with “slope instability and landslides.” Rollander then hired Nutting to design the retaining walls, which were constructed by Scherziner Drilling.
After cracking was discovered on State Route 1, the walls were discovered to be inadequate. More dirt was brought in and a system of tie-backs was designed to anchor the walls. Not only were the tie-backs unsightly, local officials would not approve the complex for occupancy. Further, the failure of the wall below one building lead to damage of that building.
The court concluded that since almost all events occurred in Indiana, they rejected Rollander’s contention that the case should be tried in Ohio. Further, the court notes “the last event making Nutting potentially liable on both claims was an injury that occurred in Indiana and consequently, under the lex loci delicti analysis, Indiana law applies.”
Nor did the court find that Nutting was responsible for the damage to the rest of the project, citing an Indiana Supreme Court ruling, that “there is no liability in tort to the owner of a major construction project for pure economic loss caused unintentionally by contractors, subcontractors, engineers, design professionals, or others engaged in the project with whom the project owner, whether or not technically in privity of contract, is connected through a network or chain of contracts.”
The court concluded:
Because Rollander was in contractual privity with Nutting, and Indy was connected to Nutting through a chain of contracts and no exception applies, the economic loss rule precludes their recovery in tort. Damage to Building B was not damage to "other property," and the negligent misrepresentation exception to the economic loss rule is inapplicable on these facts. The trial court therefore did not abuse its discretion by entering judgment on the evidence in favor of Nutting on the Appellants' negligence and negligent misrepresentation claims.
Read the court’s decision…