Contractor Sues License Board
June 30, 2011 — CDJ Staff
Judge Kendall J. Newman of the US District Court handed down a decision on June 24 on the case of Kent v California Department of Consumer Affairs. Mr. Kent, appearing as his own counsel, had brought the suit against the California Department of Consumer Affairs and the Contractors State Licensing Board after he was arrested in a sting operation and, as the plaintiff put it, “was absurdly arrested and uncooperatively detained for a time longer than necessary or allowed by law under the false pretense of contracting with out a license.” Mr. Kent’s alleged that Rick Lopez, one of the defendants, formed him to read allow from the California Business and Professions Code. He said he was later handcuffed and placed in an uncomfortable chair, “enduring physical pain and emotional agony.”
Although Kent was given a Notice to Appear, he alleged that a further defendant, Stuart Rind, “closed the plaintiff’s case marked citation A7773 without giving written notice to anyone.” As a result, the Placer County District Attorney’s Office had no record of his Notice to Appear.
Kent alleged that subsequently his firm was essentially shut down for two years and that he was prevented from “legally contracting or selling services for any other contractor or qualifying for any other licensed capacity governed by the CSLB.” After this, the CSLB suspended the license for his firm, DSI Construction. He was assessed a $1,500 fine, after which he claims he sent a letter to the CSLB demanding money damages. The judge noted that the letter was not included in the plaintiff’s Ninth Amended Complaint.
Judge Kendall recommended that the plaintiff’s Complaints be dismissed, although he did allow that sixth, and perhaps the eighth and ninth, could be amended with a tenth amended complaint.
Read the court’s decision…
In Colorado, Primary Insurers are Necessary Parties in Declaratory Judgment Actions
December 9, 2011 — Heather M. Anderson, Colorado Construction Litigation
The United States District Court for the District of Colorado recently ruled that primary insurers are necessary parties, under Fed. R. Civ. P. 19, in a declaratory judgment action being pursued by an excess carrier. See Insurance Co. of State of Pennsylvania v. LNC Communities II, LLC, 2011 WL 5548955 (D. Colo. 2011). Federal Rule of Civil Procedure 19 is almost identical to Colorado Rule of Civil Procedure 19 and pertains to the joinder of persons needed for “just adjudication.” The Insurance Co. of the State of Pennsylvania (“ICSOP”) sought a declaratory judgment that it did not have a duty to defend or indemnify the defendants (collectively referred to as “Lennar Companies”) with regard to the underlying lawsuit brought by The Falls at Legend Trail Owners Association, Inc. (the “HOA”). Id. at *2. In its lawsuit, the HOA alleged Lennar Companies were liable for construction defects at The Falls at Legend Trail residential development.
Lennar Companies held two primary insurance policies, one issued by OneBeacon Insurance Company f/k/a General Accident Insurance Company (“General Accident”) and the other issued by American Safety Risk Retention Group, Inc. (“American Safety”). Lennar Companies also carried excess policies issued by ICSOP and Ohio Casualty Insurance Company (“Ohio Casualty”).
Read the full story…
Reprinted courtesy of Heather M. Anderson of Higgins, Hopkins, McClain & Roswell, LLP. Ms Anderson can be contacted at anderson@hhmrlaw.com
Damage During Roof Repairs Account for Three Occurrences
August 2, 2012 — Tred Eyerly, Insurance Law Hawaii
Southgate Gardens Condominium had buildings damaged by Hurricane Wilma in 2005. See Mid-Continent Cas. Co. v. Basedeo, 2012 U.S. App. LEXIS 11864 (11th Cir. June 12, 2012). First State Development Corporation was hired by Southgate to do repairs.
On November 1, 2005, First State completed tarping on the buildings. Thereafter, on November 11, 2005, First State contracted with Southgate to remove and replace the roofs of the Southgate Buildings.
The tarps placed by First State were inadequate and allowed water to enter the unit of Wayne Basdeo and cause damage. Further, when it attached the tarps, First State caused holes to be made in the roofs of buildings, leading to additional damage. First State also left open the mansards (a type of roof which has two slopes on all all sides, but with the lower slope steeper that the upper one). Finally, the peeled-back condition of the roofing allowed rain to enter.
Basdeo filed a claim with Mid-Continent.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Exclusion Bars Coverage for Mold, Fungus
October 23, 2012 — Tred Eyerly, Insurance Law Hawaii
The court considered whether rain damage to a house was barred by the policy's mold exclusion. Stewart v. State Farm Fire & Cas. Co., 2012 U.S. Dist LEXIS 127804 (D. S.D. Sept. 7, 2012).
The insureds hired DJ Construction to build a new home. Before construction was completed, it was discovered that DJ Construction and some of its subcontractors had failed to protect the partially constructed house from the elements, which allowed melting snow and rain to intrude into the house. Soon after this discovery, DJ Construction abandoned the project. The house remained incomplete and uninhabitable.
The insureds sued DJ Construction.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Tennessee Court: Window Openings Too Small, Judgment Too Large
November 18, 2011 — CDJ Staff
The Tennessee Court of Appeals has issued a ruling in the case of Dayton v. Ackerman, upholding the decision of the lower court, even as they found that the award was incorrectly computed. The Daytons purchased a house that had been designed and built by the Ackermans, who operated a construction business. The court noted that the warranty with the house promised that “for a period of 60 days, the following items will be free of defects in materials or workmanship: doors (including hardware); windows; electric switches; receptacles; and fixtures; caulking around exterior openings; pluming fixtures; and cabinet work.”
Soon, the Daytons began to experience problems with the house. Many were addressed by the Ackermans, but the Daytons continued to have problems with the windows. Neither side could specify a firm date when the Ackermans were contacted by the Daytons about the window problems. The Ackermans maintained that more than two years passed before the Daytons complained about the windows. The lower court found the Daytons more credible in this.
Initially, the Daytons included the window manufacturer in their suit, but after preliminary investigations, the Daytons dropped Martin Doors from their suit. Martin Doors concluded that the windows were improperly installed, many of them “jammed into openings that were too small for them.”
After the Daytons dismissed Martin Doors, the Ackermans sought to file a third party complaint against them. This was denied by the court, as too much time had elapsed. The Ackermans also noted that not all of the window installations were defective, however, the courts found that the Daytons ought not to have mismatched windows.
Unfortunately for the Daytons, the window repair was done incorrectly and the windows were now too small for the openings. The firm that did the repair discounted the windows and Daytons concealed the problem with plantation shutters, totalling $400 less than the original lowest estimate. However, the appeals court noted that it was here that the trial court made their computation error. Correcting this, the appeals court assessed the Ackermans $12,016.20 instead of $13,016.20.
Finally, the Ackerman’s expert was excluded as he had changed his testimony between deposition and trial. The trial reviewed the expert’s testimony and had it been admissible, it would not have changed the ruling.
Read the court’s decision…
Arizona Court of Appeals Rules Issues Were Not Covered in Construction Defect Suit
December 9, 2011 — CDJ Staff
The Arizona Court of Appeals has ruled in the case of Peters v. Marque Homes. In this case, Walter Peters provided the land and funding for Marque Homes to build a luxury residence in Glendale, Arizona. By the terms of the “Joint Venture Agreement,” Peters provided the land and funding, while Marque would not charge Peters for overhead, profits, or supervision fees. The agreement specified that profits would be divided equally.
Two years later, Marque sued Peters claiming he had breached his obligations by refusing several offers for the home. Peters replied that Marque had “failed to complete the home so it is habitable to prospective purchasers.” Peters stated he had “retained an expert inspector who had identified numerous defects.” The court appointed a Special Commissioner to list the home for sale. Peters purchased the home with two stipulations ordered by the court. At this point, the earlier case was dismissed with prejudice.
Peters then sued Marque “asserting express and implied warranty claims arising out of alleged construction defects in the home.” Marque claimed that Peters’s claims were “precluded by the prior joint venture dispute.” The court granted Marque’s motion.
The appeals court reversed the lower court’s decision, determining that Peters’s claims were not precluded by the agreement. Although there had been a prior case between the two parties, warranty issues did not form a part of that case. “Peters never raised these allegations nor presented this evidence in support of any warranty claim.”
The court also noted that the “parties never agreed to preclude future warranty claims.” Marque and Peters “agreed in the stipulated sale order that ‘the sale of the property to a third party shall be “as is” with a 10-year structural warranty.’” The court noted that the agreement said nothing about one of the parties buying the house.
The appeals court left open a claim by Marque that there are no implied or express warranties available to Peters. They asked the Superior Court to address this.
Read the court’s decision…
Construction Defects Not Occurrences under Ohio Law
November 7, 2012 — CDJ Staff
Concluding the “claims of defective construction or workmanship brought by a property owners are not claims for ‘property damage’ caused by an ‘occurrence’ under a commercial general liability policy,” the Supreme Court of Ohio has ruled in Westfield Insurance Co. v. Custom Agri Systems, Inc. In the underlying case, Custom Agri Systems, Inc. built a grain bin as a subcontractor to Younglove Construction, LLC. Younglove had been contracted by PSD Development, which withheld payment, claiming it had suffered damages due to defects in Custom Agri System’s work. Younglove filed a complaint against Custom Agri, which filed complaints against its subcontractors. Custom Agri also requested that its insurer, Westfield Insurance Company, defend and indemnify it. Westfield claimed that it had no such duty. The Ohio Supreme Court concurred.
The decision notes that “Custom was being sued under two general theories: defective construction and consequential damages resulting from the defective construction.” Westfield argued that none of the claims were “for ‘property damage’ caused by an ‘occurrence” and therefore none of the claims were covered under the CGL policy.” Further, Westfield argued that “even if the claims were for property damage caused by an occurrence, they were removed from coverage by an exclusion in the policy.”
The case was filed in the US District Court which issued a summary judgment for Westfield. The plaintiff appealed and Sixth Circuit Court of Appeals certified the questions to the Supreme Court of Ohio.
The court noted that “all of the claims against which Westfield is being asked to defect and indemnify Custom relate to Custom’s work itself.” And so, the court concluded that they “must decide whether Custom’s alleged defective construction of and workmanship on the steel grain bin constitute property damage caused by an ‘occurrence.’” However, the court noted that under the terms of the insurance contract, an occurrence is defined as “an accident, including continuous or repeated exposure to substantially the same general harmful conditions,” and the court noted that the “natural and commonly accepted meaning” of “accident” is something “unexpected, as well as unintended.”
The Ohio Supreme Court also looked at court decisions in other places, and found that in many similar cases, courts have concluded that construction defects are not occurrences.
In a dissenting opinion, Justice Pfeifer argues that “if the defective construction is accidental, it constitutes an ‘occurrence’ under a CGL policy.” Justice Pfeifer characterized the majority’s definition of “accidental” as “broad, covering unexpected, unintentional happenings.”
Read the court’s decision…
Judge Rejects Extrapolation, Harmon Tower to Remain Standing
November 7, 2012 — CDJ Staff
CityCenter has filed an emergency motion asking the Nevada Supreme Court to intervene in Judge Elizabeth Gonzalez’ order that the building’s defects cannot be extrapolated from those tested. CityCenter’s structural engineering expert “evaluated 397 of the Harmon’s critical structural elements and found all but one defective,” according to the article on Vegas.Inc. Judge Gonzalez would not permit this to be extrapolated to the untested 1,072, as the locations tested were not random.
Judge Gonzalez also ruled that if CityCenter does additional testing, they may not appeal her order that ruled the extrapolation inadmissible. CityCenter argued to the Nevada Supreme Court that “the notion that CityCenter should be forced to incur additional millions of dollars in testing costs and sanctions ?Äì on the condition that it waive its right to appeal this ruling ?Äì just to be permitted to present its own damages evidence, shocks the conscience.”
Gonzalez gave the okay to CityCenter to demolish the building, but its demolition would make any further testing impossible. Under Gonzalez’ ruling, the untested structural elements cannot b assumed to be defective.
Read the full story…
Construction Defect Claim Did Not Harm Homeowner, Court Rules
September 30, 2011 — CDJ Staff
The Minnesota Court of Appeals has ruled in Creswell v. Estate of Howe, a case in which a woman bought a home and then sued the seller’s estate, both sets of real estate agents, and the homeowner’s association over construction defects. A district court ruled against her, granting summary judgment to the other parties.
After buying a townhome “as is,” Catherine Creswell claims to have shared a thought with her agent that the homeowners association was, in the words of her agent, “trying to hide something.” Later, Creswell found that a few days before her closing, the board had discussed problems with “roofs, siding and soundproofing of the townhomes.” The court noted that “it was clear from the documents that appellant [Creswell] received that the association had known about various construction defects for many years, some of which affected [her] unit.”
Creswell initially sued the estate, the man who negotiated the sale for his mother’s estate, the real estate companies and the agents involved, the homeowners association, and four board members. Later she sued for punitive damages, dropped a claim for interference with contractual relations, and dismissed her claims against the individual board members. The court dismissed all of Creswell’s claims awarding costs to those she sued.
The appeals court has affirmed the decision of lower court, noting that Creswell “did not provide us with any argument why the district court erred in dismissing her unjust-enrichment, breach of contract, or rescission claims against the various respondents.” Nor did she provide evidence to support her claims of “breach of duty, fraud, and violation of consumer protection statutes.”
The court noted that Creswell could not sue the homeowners association over the construction defects because she “failed to prove that she was damaged by the association’s nondisclosure.” The court noted that “there are no damages in this case,” as Creswell “was never assessed for any repairs, she had not paid anything out-of-pocket for repairs, and she has presented no evidence that the value of her individual unit has declined because of the alleged undisclosed construction defects.”
The court granted the other parties motion to dismiss and denied Creswell’s motion to supplement the record. Costs were awarded to the respondents.
Read the court’s decision…
Developer’s Fraudulent Statements Are His Responsibility Alone in Construction Defect Case
February 10, 2012 — CDJ Staff
The Texas Court of Appeals ruled on December 21 in the case of Helm v Kingston, a construction defect case. After purchasing what was described as “an extremely well-built” two-bedroom townhouse, Mr. Kingston made complaints of construction defects. Greenway Development did not repair the defects to Kingston’s satisfaction, and he filed notice of suit. In his suit, he claimed that GDI and its president, John Helm, had committed fraud and negligent misrepresentation. Kingston claimed that Helm “fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of workmanship was atrocious.” Helms brought a counterclaim that Kingston’s suit was frivolous.
About four years after Kingston purchased the townhome, the suit proceeded to trial. The trial court determined that Helm was not “liable in his individual capacity,” but this was reversed at appeal.
A second trial was held ten years later on the question of whether Kingston’s unit was a townhome or an apartment. A jury found that Helm “engaged in a false, misleading or deceptive act or practice that Kingston relied on to his detriment.” Kingston was awarded $75,862.29 and an additional $95,000 in attorney fees by the jury. Helms made an unsuccessful appeal to the Appeals Court, after which Kingston was awarded an additional $10,000. Helms then made an unsuccessful appeal to the Texas Supreme Court, which lead to an additional $3,000 for Kingston. There was also a verdict of $48,770.09 in pre-judgment interest and “five percent post-judgment interest accruing from the date of the judgment until the time the judgment is paid. Helm appealed.
In his appeal, Helm raised seven issues, which the court reorganized into five Kingston raised one issue on cross-appeal.
Helms’ first claim was that Kingston “failed to satisfy the requirement of” Texas’s Residential Construction Liability Act and that by not filing under the RCLA, Kingston’s fraud and misrepresentation claims were preempted. Further Helms claimed that the RCLA limited Kingston’s damages. The court rejected this, as the RCLA deals with complaints made to a contractor and not only did Helm fail to “conclusively establish” his “status as a ‘contractor’ under the statutory definition,” Helm testified that he was “not a contactor” at the pre-trial hearing.
Helms’s second claim was that Kingston’s later claim of a misconstructed firewall should be barred, claiming that Kingston “‘had knowledge of a defect in the firewall’ as early as 1997 but did not assert them until 2007.” The court rejected this because Kingston’s claim was that “Helm ‘fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of the workmanship was atrocious.’”
Helms also challenged whether his statements that the residence was of “good quality” constituted fraud and misrepresentation under Texas’s Deceptive Trade Practices-Consumer Protection Act. The court concluded that Helm was in a position to make knowledgeable statements and further that “residential housing units are not artistic works for which quality is inherently a matter of subjective judgment.” Helm also claimed that Kingston could have avoided certain repair expenses through the “exercise of reasonable care.” Helms argued that the repairs could have been made for $6,400. The court disagreed, as these claims were cited only to invoke the DTPA, and that later petitions established additional defects.
Helms’s next claim was that he was not allowed to designate responsible third parties. The court rejected this because there GDI represented matters concerning the residence only through Helm’s statements. The court noted that “Helm is correct that?third parties may be liable for fraud if they ‘participated in the fraudulent transactions and reaped the benefits,’” but they note that “Helm never specifically alleged that GDI or CREIC participated in Helm’s alleged fraudulent transactions.
The final issue in the decision was about court costs, and here the court denied claims on both sides. Helm argued that the award of legal fees were excessive, as they exceeded the actual damages. The court noted that they “may not substitute our judgment for that of the jury,” and also that “the ratio between the actual damages awarded and the attorney’s fees is not a factor that determines the reasonableness of the fees.” But the court also rejected Kingston’s claim for post-judgment interest on $10,312.30 that Helm had deposited in the trial court’s registry. The court noted that the monies were to be paid out upon final judgment, but the mandate did not include any reference to interest.
Read the court’s decision…
Association May Not Make Claim Against Builder in Vermont Construction Defect Case
October 23, 2012 — CDJ Staff
The Vermont Supreme Court issued a ruling on September 28 on Long Trail House Condominium Association. The case was heard by a panel of two Supreme Court justices, Marilyn Skoglund and Brian Burgess, and three justices specially assigned for the case, Kupersmith, Davenport, and Johnson. The decision came down with a 3-2 split; Judges Kupersmith and Johnson joining in a dissent.
In the underlying case, Stratton Corporation entered into an agreement with Engelberth Construction in which Engelberth would supply “recommendations on construction feasibility, consultation as to the selection of materials and equipment, assistance with zoning requirements and permits, and cooperation with the ‘design team’ to provide valuable engineering services.” Engelberth was not responsible to determine that the drawings and specifications were in accordance with the law and building codes, nor were they responsible “for the design team’s designs, errors, or omissions.”
Subsequent to the agreement was a construction project which culminated in the incorporation of the Long Trail House Condominium Association. The condominium owners initiated a lawsuit over alleged defects. Stratton, Intrawest, and the association settled claims for $7,025,00 with Stratton and Intrawest both pursuing claims against Engelberth. This case is still unsettled.
The association progressed on remediation, which cost about $1,500,00 more than was provided by the settlement, and so the association also sued Engelberth. In this case, the court granted a summary judgment to Engelberth, concluding that negligence claim was barred both “by the economic loss rule and that the absence of contractual privity was fatal to the warranty claims.”
The court upheld both determinations of the lower court. The court noted that “the economic loss rule ‘prohibits recovery in tort for purely economic losses’” and that “in tort law, duties are imposed by law to protect the public from harm.” A negligence claim could only be supported with evidence of “some accompanying physical harm, which does not include economic loss.”
The association made the claim that the economic loss rule applies only when there is a contractual relationship between the two parties. The court rejected this argument, citing a reference that “economic interests are protected, if at all, by contract principles, rather than tort principles.”
Nor did the court find it persuasive that a “professional services” exception to the economic loss doctrine applied, noting that the court has rejected this notion in two prior cases. The noted that the association’s losses were purely economic, and their inability to settle those claims with Engelberth did not mean that they had not means of settling them, as they were able to settle these very claims with Stratton and Intrawest.
The association also raised claims of an implied warranty, resting on the construction contract between Engelberth and Stratton. This was also rejected by the court, noting that Vermont “case law plainly contemplates the existence of contractual privity before a breach of implied warranty claim can be raised.” The court noted that there was neither a contract nor a sale between Engelberth and the association, and thus there were no grounds for an implied warranty. The court concluded that “the Association’s warranty remedy lies against the entity that sold it the condominium units and implicitly warranted through the sale that the units were built in a good and workmanlike manner and that they were suitable for habitation.”
Read the court’s decision …
Construction Defects in Home a Breach of Contract
September 9, 2011 — CDJ Staff
The Supreme Court of North Dakota has ruled in Leno v. K & L Homes, affirming the verdict of the lower court. K & L Homes argued that district court had erred in several ways, including by refusing to instruct the jury on comparative fault, denying a request for inspection, and not allowing a defendant to testify on his observations during jury viewing.
The Lenos purchased a home constructed by K & L Homes, after which they alleged they found cracks, unevenness, and shifting, which they attributed to improper construction. They claimed negligence on the part of K & L Homes. K & L Homes responded that the Lenos were responsible for damage to the home. The Lenos dropped their negligence claim, arguing breach of contract and implied warranties.
Before the trial, after the discovery period had passed, K & L Homes requested to inspect the home. This was rejected by the court. Kelly Moldenhauer, the owner of K & L Homes sought to testify about his observations during the jury’s viewing of the house. The court denied this too. The jury found that K & L was in breach of contract and awarded damages to the Lenos.
The North Dakota Supreme Court noted that K & L Homes gave “warranties that the home had been built according to local building codes and laws, and that the house was fit for its particular purpose as a residence.” The court found that a defective home breached this warranty. Further, the home violated an implied warranty of fitness.
The district court had denied K & L’s request to inspect the home, as the discovery period had ended and it would not give the Lenos time to do further discovery of their own. At the time of the request, there was only twenty-two days before the trial. The Supreme Court ruled that this was not an abuse of discretion of the part of the district court.
The Lenos had requested that Moldenhauer’s testimony not be permitted, as it would “have the same effect as if the court had granted K & L Homes’ pretrial request for inspection.” K & L Homes agreed to this in court, replying, “okay.”
The decision affirms the judgment of the district court and the damages awarded to the Lenos by the jury.
Read the court’s decision…
Construction Defect Lawsuits? There’s an App for That
July 10, 2012 — CDJ Staff
The website ebeeky.com reviews Picture It Settled, an app designed to help people engaged in lawsuits figure out where settlement strategies would be most successful. First available for Android and then iOS, the app is now available for Blackberry. One user of the application wrote that “anyone who has set through a construction defect mediation can immediately grasp the value of this app.
The app tracks the negotiation process, allowing users to see a history of bids and counteroffers. It also models the negotiation process in order to predict the ultimate cost of settlement. These numbers are based on past similar negotiations that the user has entered.
Read the full story…
Seven Former North San Diego County Landfills are Leaking Contaminants
April 7, 2011 — April 7, 2011 Beverley BevenFlorez - Construction Defect Journal
Deborah Sullivan Brennan of the North County Times reported that seven former dumps in San Diego are leaking contaminants into the surrounding groundwater. John R. Odermatt, a senior engineering geologist for the California Regional Water Quality Control Board s San Diego region, told the North County Times, “the risk to most county residents is very small or negligible, while local water supplies located in more rural areas may be at a somewhat elevated but unquantified level of risk.”
This issue is causing heavy scrutiny of a new proposed landfill in Gregory Canyon. The landfill would be located on 308 acres of undeveloped land near Pala, alongside the San Luis Rey River. The group “Save Gregory Canyon” has been speaking out against the landfill, stating that “the project threatens major detrimental impacts to both surface and groundwater, as well as a potential compromise of the two major San Diego Water Authority pipelines nearby.” Richard Felago, a Gregory Canyon Ltd. Consultant, told the North County Times that the 8-foot-thick liner, composed of layers of gravel and synthetic material, would not leak.
The appeal hearing is being rescheduled later this month after one of the three panelists recused himself due to having a competing interest in the property, according to the article by Gary Warth in the North County Times.
Read the full story (link 1)...
Read the full story (link 2)...
Geometrically Defined Drainage Cavities in EIFS as a Guard Against Defects
July 10, 2012 — CDJ Staff
The blog Stucco & Insulation Contractor writes up some details on a “relatively new modification to modern Exterior Insulation Finish Systems,” known as “geometrically defined insulation boards.” They note that the insulation has grooves cut in the back to provide a route for water to drain, instead of getting trapped. They note that when EIFS is installed by a skilled applicator, this is unnecessary. However, with less experienced (and cheaper) installers, problems are more likely.
By cutting these channels, the application of EIFS is rendered “idiot proof,” as they note. Their preference would be that EIFS installers take the time to do the job right, but call this “a step in the right direction.”
Read the full story…
Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses
April 25, 2012 — Douglas Reiser, Builders Cousel
Ever had that lingering problem with a contracting partner that went away for awhile and then came back to bite you ? years later? In Washington, construction contract claims can be raised for up to six years after substantial completion. Six years!? Why would I want to wait that long to find out if I have a problem? You don’t have to.
Over the past few years, I have discussed the notion of “contractual claim periods” on The Builders Counsel. For today’s Save a Legal Fee column, I cannot think of a better topic. These provisions are specifically intended to save you from unnecessary legal fees that might arise if a problem goes unnoticed for too long.
Contractual claim periods are simply a way to reduce the amount of time that a contracting party has to raise a claim against its contracting partner. For example, a subcontractor might require that a general contractor raise any claim that it might have ? for defective or incomplete work, injury, damages, etc ? within a particular amount of time or forever lose the ability to raise the claim in a legal proceeding.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Drug Company Provides Cure for Development Woes
November 18, 2011 — CDJ Staff
Vertex Pharmaceuticals is poised to become the holder of Boston’s biggest commercial lease, paying $72.5 million for 1.1 million square feet on Boston’s waterfront. Vertex’s new buildings are still under construction, but the plans have spurred other development in the Fan Pier area, according to the New York Times. The Times quotes Mary A. Burke, a senior economist at the Federal Reserve Bank of Boston that the Vertex project gives “a big push” to the “momentum for economic growth.”
The Fallon Company is building Vertex’s new laboratory and office space. They are separately planning to build a high-rise with 150 luxury condominium units. According to Joseph Fallon, the chief executive and president of the Fallon Company, there is already a waiting list of 50 buyers for the condominiums.
Across the street from the Vertex site, a group including Morgan Stanley and Boston Global Investors is planning a 23-block mixed use project that would include 1.2 million square feet of retail space. Additionally, the New England Development and the Hanover Group is building a 356-unit apartment building at the adjacent Pier 4.
Read the full story…
Lien Claimant’s Right to Execute against Bond Upheld in Court of Appeals
February 10, 2012 — Douglas Rieser, Builders Counsel
Stonewood v. Infinity Homes is a simple construction dispute over a matter of about $9,000.00. But sometimes these tiny little disputes turn into expensive legal battles over mere procedural quivering. In Stonewood, a small subcontractor won a big victory yesterday when the Divison 1 Court of Appeals upheld its judgment against a lien release bond posted by an owner.
Infinity Homes contracted with Stonewood Design to lay tile in one of its customer’s homes. Stonewood did the work, but Infinity withheld roughly $9,000.00 of the contract sums for what it alleged were trade damages left on the tile. The two parties were unable to come to an agreement over payment and Stonewood proceeded with a lien under RCW 60.04. It then filed an action to enforce the lien against the homeowner, Infinity and its bonding company.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com