Construction Spending Dropped in July
September 13, 2012 — CDJ Staff
Bloomberg News reports that after four months of gains in construction spending, July saw a drop of 0.9 percent, wiping out June’s gain of 0.4 percent. Despite the overall decline in spending, there was an increase of 1.5 percent in expenditure on building new single-family homes and 2.8 percent on multifamily residential construction.
Read the full story…
No Coverage for Negligent Misrepresentation without Allegations of “Bodily Injury” or “Property Damage”
February 10, 2012 — Tred Eyerly, Insurance Law Hawaii
Jeff City Industries was the general contractor for a sewer system improvement project in Branson, Missouri. Bituminous Cas. Corp. v. United HRB Gen. Contractors, Inc., 2011 U.S. Dist. LEXIS 145666 (W.D. Mo. Dec. 19, 2011). Branson sued Jeff City, alleging breach of the construction contract for the project. The claims included improperly bedded sewer piping, improper aligning portions of trenching for the sewer piping, improper service line connections to the sewer piping, etc.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Supreme Court of New York Denies Motion in all but One Cause of Action in Kikirov v. 355 Realty Assoc., et al.
April 28, 2011 — April 28, 2011 Beverley BevenFlorez - Construction Defect Journal
In the construction defect suit Kikirov v. 355 Realty Associates, LLC, et al., the Supreme Court of the State of New York granted a dismissal of the plaintiff’s fourth cause of action, but denied the defendants’ motion in all other respects. The plaintiff alleged breach of contract, among other claims. “355 Realty was the sponsor of 355 Kings Highway Condominium, a condominium project located at 355 Kings Highway, in Brooklyn, New York. The condominium units were allegedly marketed as ‘ultra luxury condos,’ and a ‘Manhattan style condominium building,’ which would be the ‘epitome of luxury and quality.’ The construction of the six-story 28 unit residential condominium building began in approximately November 2003. […] Plaintiff entered into a purchase agreement, dated December 21, 2005, with 355 Realty (which was executed on behalf of 355 Realty by Michael Marino, as its member) for the purchase of Unit 2G in the building.”
The plaintiff alleged that construction defects emerged soon after moving into the unit: “After taking occupancy of his condominium unit, plaintiff allegedly experienced serious leakage and moisture problems in his unit, which caused a dangerous mold condition to develop, in addition to causing actual damage to the structural elements of his unit. According to plaintiff, the walls, moldings, and wood floors of his unit are constantly wet and moist, and there is severe buckling of the wood floors. Plaintiff claims that these problems have caused his unit to be uninhabitable. Plaintiff alleges that he has been forced to remove all of his personal belongings from his unit and has been unable to occupy his unit.”
According to the plaintiff, Foremost attempted to repair the defects, but only made the situation worse: “Specifically, plaintiff asserts that Foremost’s contractors opened his walls to remove the stained drywall, but never corrected the cause of the leaks, destroyed the walls, and never properly taped and painted the sheet rock. Plaintiff alleges that Foremost repaired the openings in a defective manner. Plaintiff also claims that his floor was repaired at that time by a subcontractor hired by Foremost, but the basic structural problem was never resolved and the leaks continued, compromising the beams and causing the mold conditions, in addition to all of the physical damage present in the unit. On or about July 16, 2009, plaintiff allegedly sent a notice of the defects to 355 Realty and to the managing agent designated by the condominium board, by certified mail, return receipt requested. Plaintiff asserts that defendants have failed and refused to repair and remedy the defective condition, and that the damage is extensive and requires major structural repairs.”
The plaintiff filed suit on May 4, 2010, and the original complaint asserted eight causes of action. “By decision and order dated September 13, 2010, the court granted a motion by defendants to dismiss plaintiff’s second cause of action for breach of implied covenants of good faith and fair dealing, his third cause of action for breach of implied warranties, his fifth cause of action for negligence as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his seventh cause of action for negligence as against Vision, Foremost, and MMJ, and his eighth cause of action for violations of General Business Law § 349 and § 350, and granted plaintiff leave to replead his first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his fourth cause of action for breach of statutory warranties, and his sixth cause of action for breach of contract as against Vision, Foremost, and MMJ.”
The plaintiff amended their complaint on October 18, 2010, and “has repleaded these three causes of action by asserting a first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, a second cause of action for breach of statutory warranties, and a third cause of action for breach of contract as against Vision, Foremost, and MMJ. In addition, plaintiff, in his amended complaint, has added a fourth cause of action for fraud.”
The defendants, on the other hand, “argue that each of the four causes of action alleged by plaintiff in his amended complaint fail to state a claim upon which relief may be granted, and that plaintiff’s amended complaint must be dismissed pursuant to CPLR 3211 (a) (7). Defendants also cite to CPLR 3211 (a) (1), and (5), asserting that dismissal is also required based upon documentary evidence and the Statute of Limitations contained in the limited warranty.”The defendants’ motion to dismiss the first cause of action, breach of contract against 355 Realty, was denied: “While defendants dispute that the alleged defects are actually structural in nature, plaintiff’s allegations as to their structural nature are sufficient, at this juncture, to withstand defendants’ motion to dismiss. Thus, dismissal of plaintiff’s first cause of action must be denied.”
Next, the court reviewed the second cause of action, which was breach of statutory warranties: “Defendants’ motion also seeks dismissal of plaintiff’s second cause of action for breach of statutory warranties, which alleges that, under applicable law, including General Business Law § 777-a, et seq., the sponsor warranted to purchasers of units that the units would be constructed in a skillful, careful, and workmanlike manner, consistent with proper design, engineering, and construction standards and practices, and free of material latent, design, and structural defects. Defendants argue that General Business Law § 777-a, known as the housing merchant implied warranty, is inapplicable to this case because it is limited to the construction of a ‘new home,’ defined in General Business Law § 777 (5) as ‘any single family house or for-sale unit in a multi-unit residential structure of five stories or less.’ As noted above, the building in which plaintiff’s condominium unit is located is a six-story building.”
The motion to dismiss the second cause of action is denied. The court provided this reasoning: “the full text of the offering plan has not been provided, the court is unable to examine the entire written agreement so as to determine the purpose of the inclusion of the text of General Business Law § 777.”
In the third cause of action, the plaintiff alleges “a breach of contract claim as against Vision, Foremost, and MMJ based upon their contract with 355 Realty, pursuant to which they agreed to be the general contractors/construction managers for the condominium, to undertake oversight responsibility for the design and construction of the condominium, to prepare and/or review drawings, plans, and specifications for the condominium, and to otherwise manage and oversee the project. Plaintiff alleges that Vision, Foremost, and MMJ breached their contractual obligations in that the condominium units were improperly and inadequately designed and constructed, and completed in an incompetent and unworkmanlike manner, with material design and construction defects.”
The motion to dismiss the third cause of action was denied as well: “Plaintiff alleges, in his amended complaint, that Vision, Foremost, and MMJ have acknowledged notice of the defects and have not denied that they are responsible for providing a warranty to plaintiff. Plaintiff also refers to this warranty, in his amended complaint, by noting that paragraph 16 of the purchase agreement stated that the ‘[s]eller shall not be liable to . . . the [p]urchaser for any matter as to which an assignable warranty . . . has been assigned . . . to [p]urchaser and in such case the sole recourse of such . . . [p]urchaser . . . shall be against the warrantor . . . except that in the event a contractor or subcontractor is financially unable or refuses to perform its warranty . . . [s]eller shall not be excused from its obligations enumerated in the [offering p]lan under Rights and Obligations of Sponsor.’ Consequently, the court finds that dismissal of plaintiff’s third cause of action as against Foremost and MMJ must also be denied.”
In the fourth cause of action, the plaintiff alleges “that defendants made false statements and representations orally, in advertisements, and in the purchase agreement, that the condominium was properly and adequately designed and constructed and completed in a competent and workmanlike manner, in accordance with the condominium plans and specifications and proper design, engineering, and construction standards and practices consistent with applicable standards for a first class, luxury condominium in Brooklyn.”
The court dismissed the fourth cause of action stating, “it must be dismissed because it is duplicative of his first cause of action for breach of contract.” Therefore, “defendants’ motion to dismiss plaintiff’s amended complaint is granted to the extent that it seeks dismissal of plaintiff’s fourth cause of action, and it is denied in all other respects.”
Read the court’s decision…
Background Owner of Property Cannot Be Compelled to Arbitrate Construction Defects
November 7, 2012 — CDJ Staff
In Truppi v. Pasco Engineering, John Quattro sued Property Management Contractors, Inc. over construction defects in William Truppi’s home. All parties are named in the suit. The California Court of Appeals ruled that Property Management Contractors, Inc. (PMCI) could not compel Mr. Quattro to arbitration.
The background of the case involves two houses built in Encinitas, California by PCMI: one for Mr. Truppi at 560 Neptune, and one for Mr. Quattro at 566 Neptune. Both contracts contained an arbitration provision. Mr. Quattro signed the contract for his residence and Mr. Truppi signed the other. Mr. Quattro then sued PCMI and its principal, William Gregory. Mr. Quattro claimed to be the true contracting party for the 560 Neptune residence and a third party beneficiary of the contract Mr. Truppi signed, and stated that PCMI was aware of this.
PCMI in a demurrer stated that Quattro “had only a ‘prospective beneficial interest in the property upon its eventual sale or lease.’” Mr. Quattro amended his complaint to account for the issues raised by PCMI. The court rejected PCMI’s demurrer to the amended complaint.
Finally, PCMI and Gregory asserted that Quattro was “not the real party in interest” and could not sue. PCMI continues to assert that Quattro lacks standing, but their attorney sent Quattro an e-mail stating, “While my client disputes that you are a party, and that you lack standing to assert the claim, to the extent you do so I believe you are obligated to proceed by way of arbitration.”
The court did not cover the issue of Quattro’s standing in the case, only if he could be compelled to arbitration. The court affirmed the lower court’s finding that Quattro could not be compelled to arbitrate the construction defect claim as neither he nor Gregory signed the contract in an individual capacity. Further, the court noted that PCMI and Gregory “denied the existence of an agreement between themselves and Quattro on the 560 contract,” and cannot compel arbitration on a non-existent agreement. And while non-signatories can, in some situations be compelled to arbitrate, the court found that “these cases are inapplicable because here they seek to have the alleged third party beneficiary (Quattro) compelled by a nonsignatory (Gregory).” The arbitration clause in question “expressly limited its application to persons or entities that signed the 560 contract.”
As Mr. Quattro was not a signatory to that agreement, the court found that he could not be held to its arbitration provision.
Read the court’s decision…
Court Clarifies Sequence in California’s SB800
December 20, 2012 — CDJ Staff
As California’s Right-To-Repair law, SB800, nears its ninth birthday, it has remained “largely untested in the legal system” as noted by Megan MacNee of Wood, Smith, Henning & Berman LLP on the site RealEstateRama. She writes that some homeowners have requested documents prior to filing a claim, which she describes as an attempt to “game the system,” and “analogous to requiring a party to litigation to comply with discovery before a complaint is filed.”
The court determined that homeowners may not request documents from the builder until they have actually filed a claim. The court noted that SB800 lacks any clear indication that homeowners may request documents before filing a claim (and also does not indicate that a builder would have to provide documents in these circumstances). The court concluded that the section that sets up the prelitigation procedures occurs before they section on documents discovery.¬? “Because the document request is part of the prelitigation procedure, and the prelitigation procedure does not begin until the homeowner has served notice of a claim, it follows that there can be no prelitigation obligation to produce documents under section 912, subdivision (a) unless the homeowner has commenced the prelitigation procedure by serving notice of a claim.”
Read the full story…
Courts Are Conflicted As To Whether "Good Faith" Settlement Determinations Can Be Reviewed Via Writ Petition Or Appeal
July 10, 2012 — Stephen A. Sunseri and Aarti Kewalramani, Gatzke Dillon & Ballance LLP
The Court of Appeal, Second District, Division Three, ruled in Oak Springs Villas Homeowners Association v. Advanced Truss Systems, Inc., et al., (June 14, 2012, B234568) __ Cal.App.4th __ [2012 WL 2149923], that a non-settling defendant cannot appeal a trial court's good faith settlement determination. Instead, a non-settling defendant may only file a petition for writ of mandate pursuant to Code of Civil Procedure section 877.6 to challenge a good faith determination. This decision comes on the heels of a 2011 ruling in Cahill v. San Diego Gas & Electric Co. (2011) 194 Cal.App.4th 939, which found that a writ petition is not the sole means of challenging a trial court's good faith settlement determination.
In Oak Springs Villas, supra, the condominium homeowners' association sued a developer, general contractor, and various subcontractors for alleged construction deficiencies and resultant property damage. The association eventually settled with the developer, but not with a truss manufacturer. The trial court approved the developer's motion for good faith settlement determination, and the truss manufacturer immediately appealed, instead of filing a writ petition. On appeal, the developer argued the good faith determination was not an appealable order. The truss manufacturer argued Cahill applied, as well as an older case, Justus v. Atchison (1977) 19 Cal.3d 564, which allowed for appeals when no remaining issues exist as to the appealing party.
The Court of Appeal ruled in the developer's favor and declined to follow Cahill, stating the truss manufacturer should have filed a writ petition, as expressly required under Section 877.6, subdivision (e). The Court also believed Justus was inapplicable because a non-settling party should not be allowed to have two review opportunities ?Äì one after an adverse good faith ruling, and then another after the ultimate conclusion of the case.
However, the greater effect is that Cahill and Oak Springs Villas simultaneously stand in conflict and appear to be valid law. One case allows for an appeal of a good faith settlement determination, while the other requires strict adherence to the statute. The Supreme Court is likely to review the issue. In the meantime, parties challenging good faith rulings are advised to consult the statutory requirements under Section 877.6, subdivision (e).
Printed courtesy of Stephen A. Sunseri and Aarti Kewalramani, Gatzke Dillon & Ballance LLP. Mr. Sunseri can be contacted at ssunseri@gdandb.com and Ms. Kewalramani can be contacted at akewalramani@gdandb.com.
Negligent Construction an Occurrence Says Ninth Circuit
June 30, 2011 — CDJ Staff
One June 27, the US Court of Appeals has rejected an appeal from Mid-Continent Casualty Company. Mid-Continent had appealed a summary judgment granted to Titan Construction Company.
Titan Construction had built condominiums for the Williamsburg Condominium Association, which later filed a construction defect lawsuit against Titan and other defendants. Titan settled with the developer, Kennydale, assigning its rights against Mid-Continent to Kennydale. Mid-Continent filed suit, claiming that “it had no obligation to indemnify or defend Titan, Kennydale, or various other defendants.” The district court found in favor of Mid-Continent, granting a summary judgment, concluding that Titan’s insurance covered “occurrences,” and none had taken place.
On appeal, the court found that the negligent construction of the condominiums constituted an “occurrence” The case was remanded and the district court this time found in favor of Titan, “concluding that Mid-Continent failed to raise a triable issue as to the applicability of the remaining policy exclusions.
The Ninth Circuit Court of Appeals has now affirmed that decision and Titan’s summary judgment stands.
Read the court’s decision…
Will They Blow It Up?
March 28, 2012 — CDJ Staff
The issues concerning the Harmon Towers building in Las Vegas continue to make their way through the courts. As we noted in a previous piece, Cook County building officials stated that the building could be a hazard if Las Vegas were struck by an earthquake. The question of whether the building will continue to stand is just one of the issues in front of a judge.
MGM Resorts International argued at a March 13 hearing for permission to implode the Harmon hotel building. They claim that more than 1,700 defects have been discovered in the building and that the building is a public safety hazard. Arguing against demolition, Perini Building Company, the general contractor for the hotel, and its subcontractors are claiming that imploding the building would destroy evidence and prejudice juries in the ongoing construction defect claims. They claim that MGM Resorts wishes to abandon the building due to the economic slowdown. Perini Corp, the contractor for the project, claims that the building can be fixed. Perini claims that MGM’s position in the construction trial would be improved if the building is demolished.
After Judge Elizabeth Gonzalez heard the four days of testimony on the Harmon Towers building and whether it should be demolished, she scheduled more testimony, with two days in April and an entire week in July. Judge Gonzalez will be deciding whether the building will be torn down, imploded, or left in place.
Read the full story…
Read the full story…
Another Las Vegas Tower at the Center of Construction Defect Claims
November 7, 2012 — CDJ Staff
Accusations are coming from both sides over construction defects at a Las Vegas tower, only this time, it’s not the Harmon Towers, it’s Hilton Grand Vacations, which is part of the Planet Hollywood Resort. The project was originally dubbed PH Towers Westgate, and it was developed by Westgate Resorts, which is suing the contractor, Tutor-Saliba for $10 million over late completion and construction defects.
Among the defects Westgate is claiming are cracked floor tiles in the valet lobby and cracks and delamination of the pool deck. Tutor-Saliba argues that the failure of the valet lobby floor is due to Westgate specifying only 1/16th inch-wide grouting, instead of the specified ¬º inch, and Westgate’s refusal to allow expansion joints on the pool deck has lead to problems there. Westgate’s attorney, Robert Schumacher, attributes the problems to “shoddy construction practices.”
According to the article in the Las Vegas Review Journal, plans were only 60 percent complete when construction began, leading to “thousands of change orders.” Despite not meeting an August completion deadline, Tutor-Saliba is claiming it is owed a $1.5 million bonus nevertheless.
Read the full story…
No Duty to Indemnify When Discovery Shows Faulty Workmanship Damages Insured’s Own Work
November 7, 2012 — Tred Eyerly, Insurance Law Hawaii
Our post last week addressed the duty to defend when alleged faulty workmanship caused loss to property adjacent to where the insured was working. See Pamerin Rentals II, LLC v. R.G. Hendricks & Sons Constr., Inc., 2012 Wis. App. LEXIS 698 (Wis. Ct. App. Sept. 5, 2012) [post here]. Today, we report on recent developments in the same case where the court determined, despite earlier finding the insurer owed a defense, it had no duty to indemnify. Pamperin Rentals II, LLC v. R.G. Hendricks & Sons Constr., Inc., 2012 Wisc. App. LEXIS 793 (Wis. Ct. App. Oct. 10, 2012).
Hendricks contracted to “prepare the site and supply and install concrete, tamped concrete, and colored concrete” at several service stations. The owner sued Hendricks, alleging the concrete “was defective and/or the work performed was not done in a workman-like manner and resulted in damages, and will require replacement.”
Pekin Insurance Company agreed to defend Hendricks subject to a reservation of rights.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Contractors with Ties to Trustees Reaped Benefits from LA Community College Modernization Program
March 3, 2011 — Original reporting by Gale Holland, Michael Finnegan and Doug Smith, Los Angeles Times
In the latest installment of the “Billions To Spend” series of investigative reports focused on construction defects, management, and cost issues relevant to LACC’s Community College Modernization Projects, the LA Times examines the costs associated with the various layers of construction management and benefits that accrued to contractors with ties to LACC trustees.
The reporting by the Times is seemingly critical of the project’s utilization of “body shops” an industry term for companies that function as employers of record. The article segment published today cites a number of circumstances wherein their utilization appears to have escalated costs substantially.
“To gauge the cost of the staffing system, The Times reviewed thousands of pages of financial records from April 2007, when URS began managing the program, to July 2010. Reporters identified two dozen contractors serving as conduits for pay and benefits for employees they did not supervise.
At least 230 people were employed in this manner, at a total cost of about $40 million, the records show.
Approximately $18 million of the total was paid to the employees, according to the Times analysis. The remaining $22 million went to profit and overhead for contractors, the records indicate.
For employees on its own payroll, the district says that medical and other benefits increase compensation costs 40% above base salaries. So if the district had employed its construction staff directly, the total cost for the period studied would have been $25 million instead of $40 million, a savings of $15 million, The Times calculated.”
Read Full Story...
Coverage Rejected Under Owned Property and Alienated Property Exclusions
June 6, 2011 —
Tred R. Eyerly,
Insurance Law HawaiiThe insured’s request for a defense when sued in a construction defect action was denied under the owned property exclusion and the alienated property exclusion in1777 Lafayette Partners v. Golden Gate Ins. Co., 2011 U.S. Dist. LEXIS 48562 (N.D. Cal. April 29, 2011).
In 1999, Lafayette Partners purchased an abandoned walnut processing factory to convert into living and working units. The property was developed into a rental property from 2000-2001, and thereafter rented. In May 2003, Lafayette Partners entered into a sales agreement with Wolff Enterprises LLC. The sale closed in February 2005. Wolff then converted the rental units into condominiums.
In December 2007, the Walnut Factory Owners Association sued Wolff for construction defects. In Lafayette Partners was added to the suit in 2009. The suit alleged a variety of defective conditions, including the roofs, exteriors, windows, electrical , plumbing, and mechanical components and systems.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Cabinetmaker Exceeds Expectations as Conditions Improve
October 23, 2012 — CDJ Staff
American Woodmark, the manufacturer of several national brands of cabinets and vanities, saw greater than anticipated earnings in its most recent quarter. Their revenue was $148.3 million, an increase of 13% over the same quarter a year prior. They saw a 40% increase in sales. As a result, their per-share earnings were 7 cents, instead of the projected loss of 3 cents per share. Forbes reports that the share price for American Woodmark has been rising in August 2012.
Read the full story…
South Carolina Legislature Redefining Occurrences to Include Construction Defects in CGL Policies
April 1, 2011 — April 1, 2011 Beverley BevenFlorez - Construction Defect Journal
The question of what circumstances must be in place for construction defects to be covered in a general commercial liability (CGL) policies is being raised by the courts and the legislature in South Carolina. The Insurance Journal reports that the American Insurance Association as well as the Property and Casualty Insurers Association of America are speaking out on the issue.
The problem seems to be centered on what defines an “occurrence.” CGL policies were not meant to cover faulty workmanship, according to the filing by the South Carolina Supreme Court. In January of this year, the South Carolina Supreme Court reversed the ruling in Crossmann Communities v Harleysville Mutual declaring that “Respondents cannot show the damage here was the result of an occurrence. Rather, the damage was a direct result and the natural and expected consequence of faulty workmanship; faulty workmanship did not cause an occurrence resulting in damage.” They focused their attention on the word “accident,” stating that there is a fortuity element that is not diminished.
The South Carolina legislature reacted by producing a bill that would add new language directly negating the ruling by the Supreme Court. The South Carolina bill S-431 would change the definition of an occurrence in regards to construction defects as follows: “For a liability insurance policy issued to a construction professional, an ‘occurrence’ means, at a minimum: (1) an accident; or (2) continuous or repeated exposure to substantially the same general harmful condition or substance. No additional requirement of a fortuitous event is needed to constitute an ‘occurrence.’”
S-431 is currently residing in the House Committee on Labor, Commerce and Industry.
Read the full story...
Insurer Settles on Construction Defect Claim
July 10, 2012 — CDJ Staff
Law360 reports that Arch Specialty Insurance Company has settled over claims that it wrongly denied coverage in a construction defect claim. The court dismissed Arch with prejudice. Terms of the settlement were not disclosed and the attorneys made not comment to Law360.
Read the full story…
Delaware “occurrence” and exclusions j(5) and j(6)
June 10, 2011 — CDCoverage.com
In Goodville Mut. Cas. Co. v. Baldo, No. 09-338 (D. Del. June 2, 2011), claimants condominium association and unit owners sued project developer Rehoboth and general contractor Capano seeking damages because of moisture penetration property damage to common elements and individual units resulting from construction defects. Rehoboth and Capano filed a third party complaint against insured property manager Baldo alleging that, if Rehoboth and Capano were liable to claimants, Baldo was also liable because of Baldo’s failure to properly manage, maintain, and repair the property
Read the full story…
Reprinted courtesy of CDCoverage.com
Discovery Ordered in Nevada Construction Defect Lawsuit
August 16, 2012 — CDJ Staff
Gemstone LVS was sued by the Manhattan Homeowners Association in Las Vegas, after which Chartis Specialty Insurance informed Gemstone that they “had no duty to defend or indemnify Gemstone under the Commercial Umbrella Liability Policy.” Gemstone “asserts that at the time the Policy was purchased, it was understood that Chartis would provide insurance coverage for a construction defect lawsuit” and now seeks discovery “to prove Chartis’ bad faith purpose in drafting an illusory Policy.”
The opinion notes that “the Court conducted a preliminary peek at the pending motion for partial summary judgment and finds that Chartis has not made the strong showing necessary to support the requested stay.” Further, the court notes that “when ambiguity in the language of a policy exists, the court may consider not only the language of the policy but also the ‘intent of the parties, the subject matter of the policy, and the circumstances surrounding its issuance.’” The court concludes that “this type of discovery is relevant to understanding the intent of the parties, more specifically, whether it was understood that Chartis would provide insurance coverage given the construction defect lawsuit.”
Accordingly, the court denied Chartis’ motion for stay of discovery and established a schedule for discovery, expert designations, rebuttal expert designations, and other matters related to the trial.
Read the court’s decision…
Insurance Company Prevails in “Chinese Drywall” Case
June 17, 2011 — CDJ Staff
The Louisiana Court of Appeals rejected an appeal to reverse a summary judgment granted to Louisiana Citizens Property Insurance Company. Terrence and Rhonda Ross contracted for a remodel of their home in which Chinese-made drywall was used. When the drywall emitted harmful gasses, the Rosses filed a claim under their insurance policy. This claim was rejected under four exclusions: for faulty materials, latent defect, loss by corrosion, and loss by pollution. After the claim was denied, the Rosses sued Louisiana Citizens.
In April 2010, the lower court granted a summary judgment, followed by a May, 2010 order dismissing the Rosses’ claims against Louisiana Citizens. The Rosses appealed this decision. In the court’s review, they agreed with Louisiana Citizens and the lower court on all counts. Although the Rosses maintained that the drywall was not defective (as it still functioned as drywall), the court ruled that its emission of sulfuric gases was a defect. Further, as it was in place for two years before this became evident, it was also a latent defect. Damage to the Rosses’ home consisted of corrosion damage caused by the pollutants in the drywall.
The Rosses made an additional claim that since their policy covered smoke damage, this should be covered, as the harm was done by sulfuric gases. The court noted that the contract specifies “fumes or vapors from a boiler, furnace, or related equipment,” none of which apply in this case.
Read the court’s decision