Senate Committee Approves Military Construction Funds
June 29, 2011 — CDJ Staff
With a decrease in funding, as compared to the House bill, the Military Construction and Veteran’s Affairs subcommittee of the Senate moved on a $72 billion construction bill. The House version had approved an additional half billion dollars in funding. Senator Tim Johnson, Democrat of South Carolina, said that he expected easy reconciliation with the House version. The Senate bill will move to the full Senate Appropriations Committee on June 30.
The bill, S 1255, includes funding for construction and remodeling of military housing, as well as construction and remodeling of base facilities.
Read the full story… Read S1255
Anti-Assignment Provision Unenforceable in Kentucky
December 20, 2012 — Tred Eyerly, Insurance Law Hawaii
On a certified question from the Federal District Court, the Supreme Court of Kentucky decided that an anti-assignment provision in a policy is unenforceable.Wehr Constructors v. Paducah Div. Assur. Co. of Am., 2012 Ky. LEXIS 183 (Ky. Oct. 25, 2012).
Before building an addition to its hospital, Murray Calloway County Hospital purchased a builder's risk policy from Assurance Company of America.The policy provided, "Your rights and duties under this policy may not be transferred without Assurance's written consent . . . ." The Hospital contracted with Wehr Constructors to install concrete subsurfaces and vinyl floors in order to expand the hospital. After installation, a portion of the floors and subsurface work was damaged. The Hospital submitted a claim to Assurance for $75,000, but the claim was denied.
Wehr sued the Hospital to recover money for its work on the construction project. In settling the case, the Hospital assigned to Wehr any claim or rights the Hospital had against Assurance.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Louisiana Politicians Struggle on Construction Bills, Hospital Redevelopment
June 16, 2011 — CDJ Staff
Louisiana politicians are still working on a compromise in the state’s construction budget, as reported in the Times-Picayune. Rob Marrianneax, the chair of the Senate Revenue and Fiscal Affairs Committee, removed a $45 million request from Governor Bobby Jindal and added $4 million for projects that Jindal vetoed last year.
Two senators have formed competing plans to fund redevelopment construction for New Orleans’s Methodist Hospital. Mitch Landrieu, the mayor of New Orleans, hoped for $30 million dollars in state bonds. Senator Cynthia Willard-Lewis proposed an amendment that would supply $1.6 million, while Senator J.P. Morrell has an amendment that would supply $4 million.
Read the full story…
Ohio Court Finds No Coverage for Construction Defect Claims
March 1, 2012 — Tred Eyerly, Insurance Law Hawaii
Charles and Valerie Myers hired Perry Miller to build their home. Myers v. United Ohio Ins. Co., 2012 Ohio App. LEXIS 287 (Ohio Ct. App. Jan. 26, 2012). After completion of the home, Miller was again hired to construct an addition which included a full basement, staircases, bathroom, bedroom, hallway and garage.
After the addition was completed, one of the basement walls began to crack and bow. Miller began to make repairs, but eventually stopped working on the project. Other contractors were hired to make repairs, but further problems developed. A second basement wall began to bow and crack, allowing water into the basement. The wall eventually had to be replaced. Subsequently, the roof over the addition began to leak in five or six places before the drywall could be painted. The leaks caused water stains on the drywall and cause it to separate and tear. It was discovered the roof needed to be replaced.
The Myers sued Miller and his insurer, United Ohio Insurance Company. The trial court ruled that the policy did not provide coverage for faulty workmanship, but did provide coverage for consequential damages caused by repeated exposure to the elements. United Ohio conceded liability in the amount of $2,000 to repair water damage to the drywall. United Ohio was also found liable for $51,576, which included $31,000 to repair the roof and ceiling and $18,576 to replace the basement wall.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
New OSHA Fall Rules to Start Early in Minnesota
June 14, 2011 — CDJ Staff
Minnesota has elected to implement the new OSHA rules concerning fall prevention in residential construction on June 20, well before OSHA’s September 15 deadline. Brian Johnson, reporting in Finance and Commerce, quotes Pam Perri, the executive vice president of the Builders Association of Minnesota, “this is the worst time to implement a new rule.” Ms. Perri notes “In Minnesota, education time for the residential construction industry is between November and March 1, not in the middle of the construction season.”
Mike Swanson of Rottlund Homes estimated that the new regulations would add between $200 to $500 to the cost of a house and that he felt the current safety regulations were adequate. OSHA officials are quoted that there continues “to be a high number of fall-related deaths in construction.”
Read the fully story…
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 — CDJ Staff
The California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Hospital Construction Firm Settles Defect Claim for $1.1 Million
September 13, 2012 — CDJ Staff
Law360 reports that Bovis Lend Lease has settled claims of $10 million in damages for $1.1 million. Bovis was building three annexes to a hospital in Oklahoma. The hospital alleged that a faulty moisture barrier system lead to damage throughout the hospital.
Bovis is a division of the Lend Lease Group, a multinational construction firm based Sydney, Australia.
Read the full story…
Construction Defect Notice in the Mailbox? Respond Appropriately
August 4, 2011 — Douglas Reiser, Builders Counsel
Recently, I have seen a rash of ignored construction defect notices. What is a construction defect notice? It’s a statutorily required notice, sent from a homeowner to a contractor, listing a number of defects found at their property. If you get one, don’t ignore it.
The Revised Code of Washington includes a number of provisions intended for residential construction disputes. Among them is the “Notice to Customer” requirement in RCW 18.27.114, which can preempt a contractor’s lien rights, and the “Notice of Construction Defects” found in RCW 64.50.020.
The Notice of Construction Defects is a standard notice mandated by RCW 64.50, a chapter in the Revised Code of Washington, intended to provide a pre-litigation resolution process for contractors and consumers. The chapter applies only to those losses “caused by a defect in the construction of a residence or in the substantial remodel of a residence.”(See “Action” RCW 64.50.010).
Unfortunately, many contractors will simply ignore these notices or tell the homeowner to make a warranty claim. But, the notice actually provides a contractor with a forty-five (45) day window to alleviate the dispute.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Harmon Hotel Construction Defect Update
July 18, 2011 — CDJ Staff
Coverage of the ongoing litigation concerning the Harmon Hotel continues to proliferate. Architectural Record and a number of other news outlets continue to provide additional details and coverage of the matter. Chief among the conditions alleged are improperly installed reinforcing steel inside link beams on 15 floors. MGM Claims that the conditions amount to hundreds of millions of dollars in damages, while Perini (the builder) indicated in a July 12th statement that the buildings problems are related to the design, and the they are “fixable.”
There is significant speculation that MGM Resorts International isn’t interested in repairing the hotel due to a glut of hotel rooms attendant to the troubled economy. In a statement Tuesday Perini reportedly stated that “Repairing and opening the Harmon would only create a greater glut of unused hotel rooms for MGM,” “If market conditions were better and MGM found that demand existed for the Harmon hotel rooms, MGM would not be claiming that the Harmon is unstable.”
MGM asserts that Perini failed to ”properly construct” the project. Clark County’s Department of Development Services has reportedly asked MGM to provide a plan to fix the project by August 15th.
The Harmon is part of the $8.5 billion CityCenter project that opened in the fourth quarter of 2009 and is jointly owned by MGM Resorts and Dubai World.
Prior reports indicated that the owner (MGM) had considered razing the entire project. The future of the project remains uncertain.
Construction Spending Dropped in July
September 13, 2012 — CDJ Staff
Bloomberg News reports that after four months of gains in construction spending, July saw a drop of 0.9 percent, wiping out June’s gain of 0.4 percent. Despite the overall decline in spending, there was an increase of 1.5 percent in expenditure on building new single-family homes and 2.8 percent on multifamily residential construction.
Read the full story…
Insurers Reacting to Massachusetts Tornadoes
August 11, 2011 — CDJ Staff
The Patriot-Ledger reports that insurers could pay out as much as $200 million to cover homes damaged or destroyed in the tornadoes that hit central and southern Massachusetts in June, 2011. Joseph Murphy, Commissioner of the State Division of Insurance didn?t foresee problems with insurers covering these claims. “At this point, there doesn’t seem to be any one company overexposed in that area,” he told the Patriot-Ledger.
Insurance executives did not think the tornadoes would cause them to raise rates. Steve Chevalier, CEO of NLC Companies, said, “it’s a major event for those impacted by it, but it’s not close to a financial hit to us.”
One insurer noted that the winter weather generated more claims; however the cumulative value of those claims was $15 million.
Read the full story…
New Households Moving to Apartments
December 20, 2012 — CDJ Staff
The New York Times reports that multifamily construction?Äîapartment buildings?Äîis leading the recovery in construction. Construction of single-family homes is only a third of the way up from its fall from its earlier heights, while multifamily construction has recovered two-thirds of its peak. Young adults are moving out of their parents’ homes, but instead of buying homes, they’re renting apartments.
Houston is adding thousands of new units, leading to a fear of overbuilding. Rents have been rising, but as the supply of apartment units rises, higher rents may be unsustainable. However, during the recession, young adults did not move out of their parents’ homes, leading to about two million doubled-up households. David Crowe, the chief economist of the National Association of Home Builders, noted that “all of the net addition to households since 2004 has been in rentals.”
Read the full story…
California Posts Nation’s Largest Gain in Construction Jobs
March 28, 2012 — CDJ Staff
California added about 8,900 construction jobs in January, 2012, as compared to December, 2011, leading the nation in the number of added construction jobs. Thirty-four other states also saw added construction jobs. A year prior, only twenty-eight states added construction jobs. The Associated General Contractors of America analyzed the monthly report from the Labor Department. Ken Simonson, the chief economist for the Associated General Contractors of America noted that “the gains this January partly reflect very mild weather this winter and exceptionally cold and snowy conditions a year before.”
Read the full story…
Florida Construction Defect Case Settled for $3 Million
June 19, 2012 — CDJ Staff
The Runaway Beach Club Condominium Association of Kissimmee, Florida has settled its construction defect claims against the parties involved in the construction and development of the buildings. The association claimed that defective roofs and improperly installed windows had lead to leaks and associated damages. A trial date had been set, but parties involved were able to reach this settlement instead.
Read the full story…
The Montrose Language Interpreted: How Many Policies Are Implicated By A Construction Defect That Later Causes a Flood?
March 17, 2011 — By Shaun McParland Baldwin, March 17, 2011
The Court of Appeals of Indiana recently addressed the “Montrose” language added to the CGL ISO form in 2001 in the context of a construction defect claim where a fractured storm drain caused significant flooding a year after the drain was damaged. The insuring agreement requires that “bodily injury or “property damage” be caused by an occurrence and that the “bodily injury or “property damage” occur during the policy period. The Montrose language adds that the insurance applies only if, prior to the policy period, no insured knew that the “bodily injury or “property damage” had occurred in whole or in part. Significantly, it also states that any “bodily injury” or “property damage” which occurs during the policy period and was not, prior to the policy period known to have occurred, includes a continuation, change or resumption of that “bodily injury” or “property damage” after the end of the policy period.
In Grange Mutual Cas. Co. v. West Bend Mut. Ins. Co., No. 29D04-0706-PL-1112 (Ct. App. IN March 15, 2011), http://www.ai.org/judiciary/opinions/pdf/03151109ehf.pdf, Sullivan was the General Contractor for a school construction project. Its subcontractor, McCurdy, installed the storm drain pipes. One of the storm pipes was fractured in 2005 while McCurdy was doing its installation work. More than a year later, the school experienced significant water damage due to flooding. It was later discovered that the flooding was due to the fractured storm drain. Sullivanrsquo;s insurer paid $146,403 for the water damage. That insurer brought a subrogation claim against McCurdy and its two insurers: West Bend and Grange. West Bend had issued CGL coverage to McCurdy while the construction was ongoing, including the date in which the storm pipe was fractured. Grange issued CGL coverage to McCurdy at the time of the flooding. Those two carriers jointly settled the subrogation claim and then litigated which insurer actually owed coverage for the loss. Significantly, the loss that was paid included only damages from the flooding, not any damages for the cost of repairing the pipe.
Read the full story...
Reprinted courtesy of Shaun McParland Baldwin of Tressler LLP. Ms Baldwin can be contacted at sbaldwin@tresslerllp.com
Bill Seeks to Protect Legitimate Contractors
December 20, 2012 — CDJ Staff
The California construction industry sees Senate Bill 863 as a needed help to legitimate construction businesses. The bill introduces regulations that will help shut down fraudulent contractors and help reduce workers’ compensation fraud. John Upshaw of the Independent Roofing Contractors of California described the revenue lost to California and other states as “phenomenal,” saying that “we need to continue the coordinated efforts if we are to see true workers’ compensation reform.”
Read the full story…
Kansas Man Caught for Construction Scam in Virginia
December 20, 2012 — CDJ Staff
A Virginia court sent charges of construction fraud against a Kansas man to a grand jury. Larry Foster visited homes in Bedford County, Virginia, tested the water, and told homeowners that they needed new water filtration systems. The homeowners paid, but Mr. Foster never delivered. One homeowner who testified paid him $1,690. Another paid even more, giving $3,090 to Mr. Foster. In order to dupe his victims, Foster used the address of a chiropractor as a business address, unbeknownst to the actual business there.. He is wanted for charges in other states as well.
Read the full story…
Homeowner’s Policy Excludes Coverage for Loss Caused by Chinese Drywall
November 18, 2011 — Tred Eyerley, Insurance Law Hawaii
Exclusions barred the homeowners from recovering for losses caused by Chinese drywall in their home. Ross v. C. Adams Const. & Design, L.L.C., 2011 La. App. LEXIS 769 (La. Ct. App., released for publication Oct. 5, 2011).
Two years after purchasing their home, the Rosses began experiencing chronic malfunctions in the heating, ventilation and air conditioning system. After discovering the presence of gypsum drywall, or "Chinese drywall", they submitted a claim to their insurer, Louisiana Citizens Property Insurance Company, for damages caused by the Chinese drywall. Louisiana Citizens denied the claim.
The Rosses sued. The trial court granted summary judgment to Louisiana Citizens based upon exclusions in the policy.
On appeal, the appellate court first agreed the Rosses had sustained a direct physical loss. The inherent qualities of the Chinese drywall created a physical loss to the home and the drywall had to be removed and replaced.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com